Rahul can do a piece of work in 15 days and Rishabh can do the same work in 10 days. If they work on it together for 5 days, then what fraction of work is left?
Reveal answer
Fill a bubble to check yourself
Rahul can do a piece of work in 15 days and Rishabh can do the same work in 10 days. If they work on it together for 5 days, then what fraction of work is left?