Quantitative Aptitude

Time, Work, and Projects

190 Questions

Time and work questions test the ability to calculate the time required to complete tasks involving individual or combined worker efficiency. These problems frequently appear in competitive exams to assess logical calculation skills. Topics include pipes, cisterns, group efficiency, and hourly work rates.

Combined work efficiencyMen and days calculationsWorker efficiency ratiosWorking hours per dayLeaving and joining workers

Time, Work, and Projects Questions

Multiple choice general knowledge science & technology
  1. 12

  2. 3

  3. 5

  4. 7

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Total work = 6 × 36 = 216 painter-days. Work done in first 8 days: 6 × 8 = 48 painter-days. Remaining work = 216 - 48 = 168 painter-days. New team size = 6 + 18 = 24 painters. Days needed = 168/24 = 7 more days. Common mistake: calculating total days (8+7=15) instead of 'more days' required.

Multiple choice general knowledge math & puzzles
  1. 8 hrs

  2. 7 1/2 hrs

  3. 7 hrs

  4. 9 hrs

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Total work = 30 men × 20 days × 9 hours/day = 5400 man-hours. This work must be completed by 40 men in 20 days. Hours per day = 5400/(40×20) = 6.75 hours = 7.5 hours. Work done is inversely proportional to men when days are fixed.

Multiple choice general knowledge math & puzzles
  1. 18

  2. 27

  3. 26.67

  4. 16

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let total days = d. A works for (d-10) days at rate 1/20 per day. B works for d days at rate 1/30 per day. Equation: (d-10)/20 + d/30 = 1. Solving: (3(d-10) + 2d)/60 = 1 → 5d-30 = 60 → 5d = 90 → d = 18. Check: A works 8 days (8/20 = 0.4), B works 18 days (18/30 = 0.6), total = 1 job.

Multiple choice general knowledge math & puzzles
  1. 3 days

  2. 9/8 days

  3. 8/9 days

  4. 4 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Ben's rate = 1/8 work per day. Joe is 3× faster: rate = 3/8 per day. Ram is 5× faster: rate = 5/8 per day. Combined rate = 1/8 + 3/8 + 5/8 = 9/8 work per day. Time = Work ÷ Rate = 1 ÷ (9/8) = 8/9 days. This is approximately 0.89 days or about 21.3 hours.

Multiple choice general knowledge math & puzzles
  1. 3 minutes and 46 seconds

  2. 3 minutes and 44 seconds

  3. 2 minutes and 46 seconds

  4. 2 minutes and 44 seconds

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Ben's rate: 20/5 = 4 drinks/min. Mary's rate: 20/10 = 2 drinks/min. Harry's rate: 20/15 = 4/3 drinks/min. Combined rate = 4 + 2 + 4/3 = 6 + 1.33 = 7.33 drinks/min. Time = 20 ÷ 7.33 = 2.73 minutes = 2 minutes + 0.73×60 seconds = 2 minutes 44 seconds (approximately).

Multiple choice general knowledge math & puzzles
  1. 9.6 Days

  2. 8 Days

  3. 6 Days

  4. 16 Days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

A's efficiency is 50% more than B, so A's rate = 1.5 × (1/24) = 1/16. Combined rate = 1/24 + 1/16 = 5/48 work per day. Days needed = 48/5 = 9.6 days. Option D (16 days) is B's time alone, option C (6 days) would require faster workers, and option B (8 days) is too low.

Multiple choice general knowledge math & puzzles
  1. 6 days

  2. 4 days

  3. 8 days

  4. 12 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let A take x days. Then B takes x/2 and C takes x/3. Combined rate: 1/x + 2/x + 3/x = 1/2. So 6/x = 1/2, which means x = 12. B's time is x/2 = 6 days. C's time would be 4 days. A's time is 12 days.

Multiple choice general knowledge math & puzzles
  1. 2 1/11

  2. 4 2/11

  3. 5 5/11

  4. 6 2/11

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A's rate is 1/10 and B's rate is 1/12. Combined rate = 1/10 + 1/12 = (6+5)/60 = 11/60. The time taken together is the reciprocal: 60/11 = 5 5/11 days. Other options represent calculation errors in the common denominator or reciprocal.