Quantitative Aptitude
Time, Work, and Projects
190 Questions
Time and work questions test the ability to calculate the time required to complete tasks involving individual or combined worker efficiency. These problems frequently appear in competitive exams to assess logical calculation skills. Topics include pipes, cisterns, group efficiency, and hourly work rates.
Combined work efficiencyMen and days calculationsWorker efficiency ratiosWorking hours per dayLeaving and joining workers
Time, Work, and Projects Questions
B
Correct answer
Explanation
If A takes 12 days, then B's efficiency being 60% more means B works at 1.6x A's rate. So B takes 12/1.6 = 7.5 days. The phrase '60% efficient than that of A' is slightly awkward but mathematically leads to option B.
D
Correct answer
Explanation
Total work = 6 × 36 = 216 painter-days. Work done in first 8 days: 6 × 8 = 48 painter-days. Remaining work = 216 - 48 = 168 painter-days. New team size = 6 + 18 = 24 painters. Days needed = 168/24 = 7 more days. Common mistake: calculating total days (8+7=15) instead of 'more days' required.
-
6 days
-
3.5 days
-
4 days
-
4.5 days
C
Correct answer
Explanation
Using the formula M1D1 = M2D2: 2 people * 12 days = 6 people * X days. 24 = 6X, so X = 4 days. The more people working, the less time it takes.
-
6 days
-
3.5 days
-
4 days
-
4.5 days
C
Correct answer
Explanation
This is an inverse proportion problem. Total man-days = 2 * 12 = 24. If 6 people work, the time taken is 24 / 6 = 4 days.
-
8 hrs
-
7 1/2 hrs
-
7 hrs
-
9 hrs
B
Correct answer
Explanation
Total work = 30 men × 20 days × 9 hours/day = 5400 man-hours. This work must be completed by 40 men in 20 days. Hours per day = 5400/(40×20) = 6.75 hours = 7.5 hours. Work done is inversely proportional to men when days are fixed.
D
Correct answer
Explanation
Bill paints 1/20 house per hour, George paints 1/30 per hour. Together they paint 1/20 + 1/30 = 5/60 = 1/12 house per hour. So time needed = 12 hours. Add rates, then take the reciprocal.
A
Correct answer
Explanation
Let total days = d. A works for (d-10) days at rate 1/20 per day. B works for d days at rate 1/30 per day. Equation: (d-10)/20 + d/30 = 1. Solving: (3(d-10) + 2d)/60 = 1 → 5d-30 = 60 → 5d = 90 → d = 18. Check: A works 8 days (8/20 = 0.4), B works 18 days (18/30 = 0.6), total = 1 job.
-
3 days
-
9/8 days
-
8/9 days
-
4 days
C
Correct answer
Explanation
Ben's rate = 1/8 work per day. Joe is 3× faster: rate = 3/8 per day. Ram is 5× faster: rate = 5/8 per day. Combined rate = 1/8 + 3/8 + 5/8 = 9/8 work per day. Time = Work ÷ Rate = 1 ÷ (9/8) = 8/9 days. This is approximately 0.89 days or about 21.3 hours.
-
3 minutes and 46 seconds
-
3 minutes and 44 seconds
-
2 minutes and 46 seconds
-
2 minutes and 44 seconds
D
Correct answer
Explanation
Ben's rate: 20/5 = 4 drinks/min. Mary's rate: 20/10 = 2 drinks/min. Harry's rate: 20/15 = 4/3 drinks/min. Combined rate = 4 + 2 + 4/3 = 6 + 1.33 = 7.33 drinks/min. Time = 20 ÷ 7.33 = 2.73 minutes = 2 minutes + 0.73×60 seconds = 2 minutes 44 seconds (approximately).
-
100 men
-
110 men
-
97 men
-
11 men
-
9.6 Days
-
8 Days
-
6 Days
-
16 Days
A
Correct answer
Explanation
A's efficiency is 50% more than B, so A's rate = 1.5 × (1/24) = 1/16. Combined rate = 1/24 + 1/16 = 5/48 work per day. Days needed = 48/5 = 9.6 days. Option D (16 days) is B's time alone, option C (6 days) would require faster workers, and option B (8 days) is too low.
C
Correct answer
Explanation
Original work = 6 x 30 x 9 = 1620 man-hours. Ten times that is 16200 man-hours. The new schedule gives 25 x 8 = 200 hours per man, so men needed = 16200 / 200 = 81, matching option C.
-
6 days
-
4 days
-
8 days
-
12 days
A
Correct answer
Explanation
Let A take x days. Then B takes x/2 and C takes x/3. Combined rate: 1/x + 2/x + 3/x = 1/2. So 6/x = 1/2, which means x = 12. B's time is x/2 = 6 days. C's time would be 4 days. A's time is 12 days.
-
12
-
18
-
22
-
24
-
None of these
D
Correct answer
Explanation
This is an inverse proportion: (Men1 * Days1) = (Men2 * Days2). 36 * 18 = 27 * Days2. Days2 = (36 * 18) / 27. Dividing 18 and 27 by 9 gives (36 * 2) / 3 = 12 * 2 = 24 days.
-
2 1/11
-
4 2/11
-
5 5/11
-
6 2/11
C
Correct answer
Explanation
A's rate is 1/10 and B's rate is 1/12. Combined rate = 1/10 + 1/12 = (6+5)/60 = 11/60. The time taken together is the reciprocal: 60/11 = 5 5/11 days. Other options represent calculation errors in the common denominator or reciprocal.