Quantitative Aptitude
Time, Work, and Projects
198 Questions
Time and work questions test the ability to calculate the time required to complete tasks involving individual or combined worker efficiency. These problems frequently appear in competitive exams to assess logical calculation skills. Topics include pipes, cisterns, group efficiency, and hourly work rates.
Combined work efficiencyMen and days calculationsWorker efficiency ratiosWorking hours per dayLeaving and joining workers
Time, Work, and Projects Questions
-
10:00 a.m. – 12 noon
-
12 noon – 2:00 p.m.
-
1:00 p.m. – 3:00 p.m.
-
2:00 p.m. – 4:00 p.m.
B
Correct answer
Explanation
Clearly, the computers would be used the most when all the three groups are working simultaneously and this happens during the period of 12 noon to 2:00 p.m.
-
4 p.m.
-
5 p.m.
-
6 p.m.
-
None of these
C
Correct answer
Explanation
The monkey climbs 30 feet and slips back 20 feet each hour, gaining 10 feet net per hour. After 7 hours (from 8 a.m. to 3 p.m.), he reaches 70 feet. At the beginning of the 8th hour (starts at 3 p.m.), he climbs 30 feet from 70 to 100 feet. At the beginning of the 9th hour (starts at 4 p.m.), he climbs from 100 to 130 feet, touching the 120-foot flag at 6 p.m. (after 10 hours from 8 a.m., which is 6 p.m.).
-
4 p.m.
-
5 p.m.
-
6 p.m.
-
None of these
C
Correct answer
Explanation
Net climb per hour = 30 - 20 = 10 ft. After 9 hours (8am to 5pm), monkey reaches 90 ft. At 5pm, starts at 90 ft, climbs 30 ft to reach 120 ft exactly. No slip back occurs because goal is reached during the climb.
-
6 days
-
14 days
-
5 days
-
10 days
-
8 days
E
Correct answer
Explanation
It is correct answer.
Let alone time of Suman be x .
Then alone time of Rahul = x/3 and that of Varun be x/4.
Suman's one day work + Rahul's one day work + Varun's one day work = Combined one day work
(1/x) + (1/(x/3)) + (1/(x/4)) = 1
x = 8
-
30 days
-
10 days
-
15 days
-
1/10 days
-
B
Correct answer
Explanation
( A + B ) 's 1 day work = 1 / 6( B + C ) 's 1 day work = 2 / 15 ( 7 1/2 = 15 /2 ) ( C + A )'s 1 day work = 1/ 10By adding
( A+ B ) + ( B + C ) + ( C + A ) 's 1 day work = 1/ 6 + 2/15 + 1/10
(A + B + B + C + C + A) 's 1 day work = 1/ 6 + 2/15 + 1/10
( 2A + 2B + 2C ) 's 1 day work = 1/6 + 2/15 + 1/10 2 ( A + B + C ) 's 1 day work = (5 + 4 + 3) /30 = 12/30 = 6 /15 (A + B + C )'s 1 day work = 6/15 x 2 = 6/30
( A + B + C ) 's 1 day work - ( C + A ) 's 1 day work = 6/30 - 1/10
= 6 - 3 /30
= 3/30 = 1 /10 B1 day work is 1/10 B can complete whole work in 1 / 1/10 = 10 days
A
Correct answer
Explanation
Work done=9/12 Balance work=1-9/12=3/12
Less work,Less days
9/12 --->21 days
3/12--->x days
Then (9/12) *x=(3/12) * 21
x=(3*12*21)/(12*9)
x=7 days
It is the correct answer.
-
28 days
-
14 days
-
4 days
-
21 days
-
8 days
C
Correct answer
Explanation
Work done by C in one day = 1/7
Work done by B in one day = 1/2(C) = 1/7 x 1/2 = 1/14
Work done by A in one day = 1/2(B) = 1/2 x 1/14 = 1/28
Work done by A, B and C together in one day = (4 + 2 + 1)/28 = 1/4
Work is done by A, B and C together in 4 days.
-
35/6 days
-
6/35 days
-
6 days
-
60/11 days
-
12 days
A
Correct answer
Explanation
A's 1 day's work = 1/10th part of the whole work and B's 1 day's work = 1/14th part of the whole work. Therefore, (A + B)'s one day's work = 1/10 + 1/14 = 6/35th part of the whole work. So, both will complete the work in 35/6 days. It is the correct answer.
-
7 days
-
6 days
-
24 days
-
5 days
-
8 days
B
Correct answer
Explanation
It is clear that 12 men = 16 women or 3 men = 4 women.
Therefore, 18 men + 8 women =18 * (4 / 3) women + 8 women
= 24 + 8 = 32 women
Now, 16 women can complete the work in 12 days.
So, 32 women will do it in 6 days.
((12 * 16) / 32 = 6 days).
It is the correct answer.
-
3 days
-
12/5 days
-
32/3 days
-
8/3 days
-
2 days
E
Correct answer
Explanation
(A + B) can do the work in (4 * 8) / (4 + 8) = 32/12 = 8/3 days
Therefore, C takes 8/3 days to complete the work.
So, (B + C) takes ((8/3) * 8)/((8/3) + 8) = 64/32 = 2 days.
It is the correct answer.
-
84 trees
-
67 trees
-
82 trees
-
37 trees
-
2 trees
A
Correct answer
Explanation
50 men working for 8 hrs cut 70 trees.
or 1 man working for 1 hr cuts 70/(50 * 8) trees.
Thus, 40 men working for 12 hrs will cut (70 * 40 * 12)/(50 * 8) trees = 84 trees.
It is the correct answer.
-
Rs. 11.25
-
Rs. 17
-
Rs. 12.75
-
Rs. 11.75
-
Rs. 21.25
C
Correct answer
Explanation
A did 1/3th of the workin 6 days.
B completed 1/4th of the work in 6 days.
Work completed by C in 6 days = 1 - (1/3) + (1/4) = 5/12th of the work
Since A, B and C did the work in 6 days 1/3th, 1/4th, 5/12th of the work, respectively.
A's share = Rs 51 * (1 / 3) = Rs. 17
B's share = Rs 51 * (1 / 4) = Rs. 12.75
C's share = Rs 51 * (5 / 12) = Rs. 21.25.
So B's share is Rs 12.75.
It is the correct answer.
A
Correct answer
Explanation
Total work = 15 × 21 × 8 = 2520 man-hours. Since 3 women = 2 men, 21 women = 14 men. Let required days = d. Then 14 × d × 6 = 2520, giving 84d = 2520, so d = 30 days. Convert women's capacity to equivalent men using the given ratio.
B
Correct answer
Explanation
5 men = 8 women, so 1 man = 8/5 woman. 3 men + 5 women = 3(8/5) + 5 = 49/5 woman-equivalent. Work done = 10 × 49/5 = 98 woman-days. To finish in 14 days: 98/14 = 7 women.
-
22½days
-
22 days
-
23 days
-
24½ days
A
Correct answer
Explanation
Let B take x days. A takes x-60 days. A works 3 times as fast, so x/(x-60) = 3. Solving: x = 3x - 180 → 2x = 180 → x = 90 (B's days), A = 30 days. Together: 1/30 + 1/90 = 4/90, so time = 90/4 = 22.5 days.