Quantitative Aptitude
Time, Work, and Projects
190 Questions
Time and work questions test the ability to calculate the time required to complete tasks involving individual or combined worker efficiency. These problems frequently appear in competitive exams to assess logical calculation skills. Topics include pipes, cisterns, group efficiency, and hourly work rates.
Combined work efficiencyMen and days calculationsWorker efficiency ratiosWorking hours per dayLeaving and joining workers
Time, Work, and Projects Questions
-
7 days
-
6 days
-
24 days
-
5 days
-
8 days
B
Correct answer
Explanation
It is clear that 12 men = 16 women or 3 men = 4 women.
Therefore, 18 men + 8 women =18 * (4 / 3) women + 8 women
= 24 + 8 = 32 women
Now, 16 women can complete the work in 12 days.
So, 32 women will do it in 6 days.
((12 * 16) / 32 = 6 days).
It is the correct answer.
-
3 days
-
12/5 days
-
32/3 days
-
8/3 days
-
2 days
E
Correct answer
Explanation
(A + B) can do the work in (4 * 8) / (4 + 8) = 32/12 = 8/3 days
Therefore, C takes 8/3 days to complete the work.
So, (B + C) takes ((8/3) * 8)/((8/3) + 8) = 64/32 = 2 days.
It is the correct answer.
-
84 trees
-
67 trees
-
82 trees
-
37 trees
-
2 trees
A
Correct answer
Explanation
50 men working for 8 hrs cut 70 trees.
or 1 man working for 1 hr cuts 70/(50 * 8) trees.
Thus, 40 men working for 12 hrs will cut (70 * 40 * 12)/(50 * 8) trees = 84 trees.
It is the correct answer.
-
Rs. 11.25
-
Rs. 17
-
Rs. 12.75
-
Rs. 11.75
-
Rs. 21.25
C
Correct answer
Explanation
A did 1/3th of the workin 6 days.
B completed 1/4th of the work in 6 days.
Work completed by C in 6 days = 1 - (1/3) + (1/4) = 5/12th of the work
Since A, B and C did the work in 6 days 1/3th, 1/4th, 5/12th of the work, respectively.
A's share = Rs 51 * (1 / 3) = Rs. 17
B's share = Rs 51 * (1 / 4) = Rs. 12.75
C's share = Rs 51 * (5 / 12) = Rs. 21.25.
So B's share is Rs 12.75.
It is the correct answer.
A
Correct answer
Explanation
Total work = 15 × 21 × 8 = 2520 man-hours. Since 3 women = 2 men, 21 women = 14 men. Let required days = d. Then 14 × d × 6 = 2520, giving 84d = 2520, so d = 30 days. Convert women's capacity to equivalent men using the given ratio.
B
Correct answer
Explanation
5 men = 8 women, so 1 man = 8/5 woman. 3 men + 5 women = 3(8/5) + 5 = 49/5 woman-equivalent. Work done = 10 × 49/5 = 98 woman-days. To finish in 14 days: 98/14 = 7 women.
-
22½days
-
22 days
-
23 days
-
24½ days
A
Correct answer
Explanation
Let B take x days. A takes x-60 days. A works 3 times as fast, so x/(x-60) = 3. Solving: x = 3x - 180 → 2x = 180 → x = 90 (B's days), A = 30 days. Together: 1/30 + 1/90 = 4/90, so time = 90/4 = 22.5 days.
-
3 days
-
8/9 days
-
4 days
-
can't say
B
Correct answer
Explanation
A takes 8 days, so A's rate = 1/8 work per day. B works 3 times faster, so B's rate = 3/8 work per day. C works 5 times faster, so C's rate = 5/8 work per day. Combined rate = (1+3+5)/8 = 9/8 work per day. Time together = 1 ÷ (9/8) = 8/9 days.
C
Correct answer
Explanation
A company contracts to paint 3 houses.
Mr.Brown paints in 6 days = 1 house
Mr.Brown paints in 1days =1/6 house
Mr.Brown paints in 8days =8/6 =4/3 house
work left = 3-4/3 = 5/3 house
Mr.Black paints in 8 days = 1 house
Mr..Black paints in 1days =1/8 house
Mr..Black paints in 6days =6/8= 3/4 house
work left = 5/3 - 3/4 = 11/12=
.Blue paints in 12 days = 1 house
.Blue paints in 1 day = 1/12 house
Mr. blue will finish 11/12 huse in = (11/12)/12=11 days
-
110 men
-
130 men
-
100 men
-
none of these
-
8 hrs
-
7 1/2 hrs
-
7 hrs
-
9 hrs
-
31 days
-
30 days
-
33 days
-
40 days
-
None of these
C
Correct answer
Explanation
Work done by A in 10 days = 10/80 = 1/8
Remaining work = (1-(1/8)) = 7/8
Now, work will be done by B in 49 days.
Whole work will be done by B in (49 * 8/7) = 56 days
Therefore, A's one day's work = 1/80 B’s one day's work = 1/56(A + B)'s one day's work = 1/80 + 1/56 = 17/560 = 33 days
Hence, both will finish the work in 33 days.
-
Rs. 512
-
Rs. 768
-
Rs. 675
-
Rs. 800
-
None of these
A
Correct answer
Explanation
Daily wages are in the ratio 4 : 5 : 4.
Working days of A, B, C = 8, 9 and 12
Wages will be in the ratio 32 : 45 : 48.
Share of A = 32/(24 + 45 + 48) × 2000 = Rs. 512
-
1/2th part, 1/18 hr
-
1/3th part, 1/36 hr
-
1/4th part, 1/9 hr
-
1/7th part, 1/27 hr
-
None of these
A
Correct answer
Explanation
1/2 + 1/3 + 1/6 = 1 also (1/18 + 2/3 + 1/6) h = 8/9 hr. This is correct.
-
30/13
-
30/11
-
11/13
-
31/13
-
None of the above
B
Correct answer
Explanation
Work done by X in 5 days = 5*1/10 = 1/2
Balance work to be done = 1 - 1/2 = 1/2
(X + Y) 's one day's work = 1/10 + 1/12 = 11/60
Number of days Y worked = 1/2 * 60/11 = 30/11
So, option (2) is correct.