Quantitative Aptitude

Time, Work, and Projects

198 Questions

Time and work questions test the ability to calculate the time required to complete tasks involving individual or combined worker efficiency. These problems frequently appear in competitive exams to assess logical calculation skills. Topics include pipes, cisterns, group efficiency, and hourly work rates.

Combined work efficiencyMen and days calculationsWorker efficiency ratiosWorking hours per dayLeaving and joining workers

Time, Work, and Projects Questions

Multiple choice
  1. 10:00 a.m. – 12 noon

  2. 12 noon – 2:00 p.m.

  3. 1:00 p.m. – 3:00 p.m.

  4. 2:00 p.m. – 4:00 p.m.

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Clearly, the computers would be used the most when all the three groups are working simultaneously and this happens during the period of 12 noon to 2:00 p.m.

Multiple choice
  1. 4 p.m.

  2. 5 p.m.

  3. 6 p.m.

  4. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

The monkey climbs 30 feet and slips back 20 feet each hour, gaining 10 feet net per hour. After 7 hours (from 8 a.m. to 3 p.m.), he reaches 70 feet. At the beginning of the 8th hour (starts at 3 p.m.), he climbs 30 feet from 70 to 100 feet. At the beginning of the 9th hour (starts at 4 p.m.), he climbs from 100 to 130 feet, touching the 120-foot flag at 6 p.m. (after 10 hours from 8 a.m., which is 6 p.m.).

Multiple choice
  1. 4 p.m.

  2. 5 p.m.

  3. 6 p.m.

  4. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Net climb per hour = 30 - 20 = 10 ft. After 9 hours (8am to 5pm), monkey reaches 90 ft. At 5pm, starts at 90 ft, climbs 30 ft to reach 120 ft exactly. No slip back occurs because goal is reached during the climb.

Multiple choice
  1. 6 days

  2. 14 days

  3. 5 days

  4. 10 days

  5. 8 days

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

It is correct answer.

Let alone time of Suman be x .

Then alone time of Rahul = x/3 and that of Varun be x/4.

Suman's one day work + Rahul's one day work + Varun's one day work = Combined one day work                     

   (1/x) + (1/(x/3)) + (1/(x/4)) = 1                                                  x = 8

Multiple choice
  1. 30 days

  2. 10 days

  3. 15 days

  4. 1/10 days


Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

( A + B ) 's  1 day work  = 1 / 6( B + C ) 's 1 day work = 2 / 15       ( 7 1/2 = 15 /2 ) ( C + A )'s 1 day work = 1/ 10By adding

( A+ B ) + ( B + C ) + ( C + A ) 's 1 day work = 1/ 6 + 2/15 + 1/10  (A + B + B + C + C + A) 's 1 day work = 1/ 6 + 2/15 + 1/10  ( 2A + 2B + 2C ) 's 1 day work = 1/6 + 2/15 + 1/10 2 ( A + B + C ) 's 1 day work = (5 + 4 + 3) /30 = 12/30 = 6 /15 (A + B + C )'s 1 day work = 6/15 x 2 = 6/30

( A + B + C ) 's 1 day work - ( C + A ) 's 1 day work =                                  6/30 - 1/10                                 = 6 - 3 /30                                = 3/30                                  = 1 /10 B1 day work is 1/10 B can complete whole work in  1 / 1/10 = 10 days

Multiple choice
  1. 28 days

  2. 14 days

  3. 4 days

  4. 21 days

  5. 8 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Work done by C in one day = 1/7 Work done by B in one day = 1/2(C) = 1/7 x 1/2 = 1/14 Work done by A in one day = 1/2(B) = 1/2 x 1/14 = 1/28 Work done by A, B and C together in one day = (4 + 2 + 1)/28 = 1/4 Work is done by A, B and C together in 4 days.

Multiple choice
  1. 35/6 days

  2. 6/35 days

  3. 6 days

  4. 60/11 days

  5. 12 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

A's 1 day's work = 1/10th part of the whole work and  B's 1 day's work = 1/14th part of the whole work. Therefore, (A + B)'s one day's work = 1/10 + 1/14 = 6/35th part of the whole work. So, both will complete the work in 35/6 days. It is the correct answer.

Multiple choice
  1. 7 days

  2. 6 days

  3. 24 days

  4. 5 days

  5. 8 days

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

 It is clear that 12 men = 16 women or 3 men = 4 women.  Therefore, 18 men + 8 women =18 * (4 / 3) women + 8 women  = 24 + 8 = 32 women 
Now, 16 women can complete the work in 12 days. So, 32 women will do it in 6 days. ((12 * 16) / 32 = 6 days).  It is the correct answer.

Multiple choice
  1. 3 days

  2. 12/5 days

  3. 32/3 days

  4. 8/3 days

  5. 2 days

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

(A + B) can do the work in (4 * 8) / (4 + 8) = 32/12 = 8/3 days

Therefore, C takes 8/3 days to complete the work. So, (B + C) takes ((8/3) * 8)/((8/3) + 8) = 64/32 = 2 days. It is the correct answer.

Multiple choice
  1. Rs. 11.25

  2. Rs. 17

  3. Rs. 12.75

  4. Rs. 11.75

  5. Rs. 21.25

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A did 1/3th of the workin 6 days. B completed 1/4th of the work in 6 days. Work completed by C in 6 days = 1 - (1/3) + (1/4) = 5/12th of the work Since A, B and C did the work in 6 days 1/3th, 1/4th, 5/12th of the work, respectively. A's share = Rs 51 * (1 / 3) = Rs. 17 B's share = Rs 51 * (1 / 4) = Rs. 12.75 C's share = Rs 51 * (5 / 12) = Rs. 21.25. So B's share is Rs 12.75. It is the correct answer.