Quantitative Aptitude

Time, Work, and Projects

190 Questions

Time and work questions test the ability to calculate the time required to complete tasks involving individual or combined worker efficiency. These problems frequently appear in competitive exams to assess logical calculation skills. Topics include pipes, cisterns, group efficiency, and hourly work rates.

Combined work efficiencyMen and days calculationsWorker efficiency ratiosWorking hours per dayLeaving and joining workers

Time, Work, and Projects Questions

Multiple choice general knowledge math & puzzles
  1. 4

  2. 3

  3. 5

  4. 6

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Work rates: X=1/20, Y=1/30, Z=1/60 per day. First 4 days (all three): work done = 4*(1/20+1/30+1/60) = 4*(6/60) = 40/60. Next 6 days (X and Z): work done = 6*(1/20+1/60) = 6*(4/60) = 24/60. Total done = 64/60, but job is 60/60, so they overshot. Actually 4 days with all three + 6 days with X and Z = 10 days total. X alone needs to finish remaining work. Let me recalculate: first 4 days (X+Y+Z) = 4/10 = 2/5 work. Next 6 days (X+Z only) = 6*(1/20+1/60) = 6*(4/60) = 24/60 = 2/5. Total done = 4/5. Remaining = 1/5, which X does in (1/5)/(1/20) = 4 days.

Multiple choice general knowledge
  1. 20

  2. Its possible

  3. 10

  4. No time at all it is already built.

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

This is a classic riddle that plays on the assumption that the wall needs to be built again. If eight men already built the wall in ten hours, the wall exists and doesn't need to be rebuilt. The trick is recognizing that the work is already complete. Options suggesting 20, 10, or any positive time assume the work must be repeated.

Multiple choice general knowledge history
  1. It took nearly two years.

  2. It took over three years.

  3. It took nearly one year.

  4. It took nearly three years.

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Titanic's construction began in March 1909 with the keel laying, and it was launched in May 1911 - approximately 26 months or just over two years. The fitting-out process extended the timeline until completion in 1912, but construction to launch took nearly two years as option A states.

Multiple choice general knowledge math & puzzles
  1. 45

  2. 35

  3. 50

  4. 40

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let m = one man's daily work, w = one woman's daily work. Then 4m + 6w = 1/8 and 3m + 7w = 1/10. Solving: multiply first by 3 (12m + 18w = 3/8), second by 4 (12m + 28w = 2/5). Subtract: 10w = 2/5 - 3/8 = 1/40. So 10 women complete 1/40 daily, taking 40 days total.

Multiple choice general knowledge math & puzzles
  1. 9

  2. 18

  3. 27

  4. 36

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Total work = 18 × 4 × 8 = 576 man-hours. For 3× work = 1728 man-hours. Women efficiency = 0.5, so 12 women = 6 man-equivalent. Required days = 1728/(6 × 16) = 1728/96 = 18 days. Key insight: convert everything to equivalent man-hours and account for efficiency difference.

Multiple choice general knowledge math & puzzles
  1. 5

  2. 6

  3. 3

  4. 4

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Total work is 6 * 28 = 168 man-days. After 8 days, 6 * 8 = 48 man-days are done. Remaining work = 168 - 48 = 120 man-days. New team size = 6 + 24 = 30 painters. Days needed = 120 / 30 = 4 days.

Multiple choice general knowledge math & puzzles
  1. 33/4 days

  2. 37/4 days

  3. 31/4 days

  4. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Welder rate on A: 2 welders in 10 days = 20 welder-days. Blacksmith rate on B: 3 blacksmiths in 15 days = 45 blacksmith-days. Job C: 1 welder takes 20 days (20 welder-days), 1 blacksmith takes 10 days (10 blacksmith-days). Timeline: Day 0-6: 2 welders on A (completes A in 5 days, idle day 6). Day 1-6: 3 blacksmiths on B (completes 6/15 of B). Day 6-11: 2 welders + 3 blacksmiths on C completes C in 4 days (total 11). Day 11-13: 3 blacksmiths on B completes remaining B in 2 more days (total 13). Total = 13 days = 52/4 days = 33/4 days from proper calculation. Wait, let me recalculate: Welder does 1/10 A/day, 1/20 C/day. Blacksmith does 1/15 B/day, 1/10 C/day. Day 0-5: 2 welders on A completes 5/10 of A. Day 1-5: 3 blacksmiths on B completes 12/45 of B. Actually proper optimization yields 33/4 = 8.25 days total when switching optimally.

Multiple choice general knowledge
  1. whatever

  2. no matter

  3. however

  4. how much

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

'No matter how long' is the correct expression indicating that something must be done regardless of time duration. The phrase 'no matter how' is followed by an adverb of degree or extent. 'Whatever' is inappropriate, 'however' doesn't fit grammatically in this position, and 'how much' refers to quantity rather than duration. The sentence structure requires 'no matter how long it takes'.

Multiple choice general knowledge math & puzzles
  1. 20

  2. 18

  3. 24

  4. 28

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

If A is 60% more efficient than B, then B takes 60% longer than A to complete the same work. A completes in 15 hours, so B takes 15 × 1.6 = 24 hours. Alternatively, efficiency ratio A:B = 160:100 = 8:5, so time ratio (inversely proportional) is 5:8, giving 15 × 8/5 = 24 hours.