Time and work questions test the ability to calculate the time required to complete tasks involving individual or combined worker efficiency. These problems frequently appear in competitive exams to assess logical calculation skills. Topics include pipes, cisterns, group efficiency, and hourly work rates.
Combined work efficiencyMen and days calculationsWorker efficiency ratiosWorking hours per dayLeaving and joining workers
Time, Work, and Projects Questions
-
3 days
-
8/9 days
-
4 days
-
can't say
B
Correct answer
Explanation
A takes 8 days, so A's rate = 1/8 work per day. B works 3 times faster, so B's rate = 3/8 work per day. C works 5 times faster, so C's rate = 5/8 work per day. Combined rate = (1+3+5)/8 = 9/8 work per day. Time together = 1 ÷ (9/8) = 8/9 days.
C
Correct answer
Explanation
A company contracts to paint 3 houses.
Mr.Brown paints in 6 days = 1 house
Mr.Brown paints in 1days =1/6 house
Mr.Brown paints in 8days =8/6 =4/3 house
work left = 3-4/3 = 5/3 house
Mr.Black paints in 8 days = 1 house
Mr..Black paints in 1days =1/8 house
Mr..Black paints in 6days =6/8= 3/4 house
work left = 5/3 - 3/4 = 11/12=
.Blue paints in 12 days = 1 house
.Blue paints in 1 day = 1/12 house
Mr. blue will finish 11/12 huse in = (11/12)/12=11 days
-
110 men
-
130 men
-
100 men
-
none of these
-
8 hrs
-
7 1/2 hrs
-
7 hrs
-
9 hrs
-
31 days
-
30 days
-
33 days
-
40 days
-
None of these
C
Correct answer
Explanation
Work done by A in 10 days = 10/80 = 1/8
Remaining work = (1-(1/8)) = 7/8
Now, work will be done by B in 49 days.
Whole work will be done by B in (49 * 8/7) = 56 days
Therefore, A's one day's work = 1/80 B’s one day's work = 1/56(A + B)'s one day's work = 1/80 + 1/56 = 17/560 = 33 days
Hence, both will finish the work in 33 days.
-
Rs. 512
-
Rs. 768
-
Rs. 675
-
Rs. 800
-
None of these
A
Correct answer
Explanation
Daily wages are in the ratio 4 : 5 : 4.
Working days of A, B, C = 8, 9 and 12
Wages will be in the ratio 32 : 45 : 48.
Share of A = 32/(24 + 45 + 48) × 2000 = Rs. 512
-
1/2th part, 1/18 hr
-
1/3th part, 1/36 hr
-
1/4th part, 1/9 hr
-
1/7th part, 1/27 hr
-
None of these
A
Correct answer
Explanation
1/2 + 1/3 + 1/6 = 1 also (1/18 + 2/3 + 1/6) h = 8/9 hr. This is correct.
-
30/13
-
30/11
-
11/13
-
31/13
-
None of the above
B
Correct answer
Explanation
Work done by X in 5 days = 5*1/10 = 1/2
Balance work to be done = 1 - 1/2 = 1/2
(X + Y) 's one day's work = 1/10 + 1/12 = 11/60
Number of days Y worked = 1/2 * 60/11 = 30/11
So, option (2) is correct.
-
40 days
-
35 days
-
30 days
-
60 days
-
None of these
D
Correct answer
Explanation
Pradeep and Dipali's 1 day's work = 1/10
Dipali's 1 day's work = 1/12
Therefore, Pradeep's 1 day's work = 1/10 - 1/12 = 2/120 = 1/60
Number of days required to do the work by Pradeep = 60 days
Hence, this option is correct.
-
4
-
2.25
-
10
-
9
-
None of these
-
1/6 days
-
1/5 days
-
5 days
-
6 days
-
None of these
C
Correct answer
Explanation
(A + B)'s 1 day work = 11/30
A's 1 day work = 1/6
Therefore, B's 1 day work = 11/30 - 1/6 = 6/30 = 1/5
Therefore, B alone can do the same work in = 5 days
-
2.3
-
2.1
-
10/24
-
2.4
-
None of these
D
Correct answer
Explanation
A's 1 day work = 1/4
B's 1 day work = 1/6
(A + B)'s 1 day work = (1/6 + 1/4) = 10/24
Therefore, required number of days = 24/10 = 2.4
-
10 days
-
13 days
-
12 days
-
Data inadequate
C
Correct answer
Explanation
(Work done by both in one day = 1 ÷ 7.5 = 2/15 Work done by Salim in one day = 1/20. Therefore, work done by Akram in one day = 2/15 - 1/20 = 8 - 3/60 = 5/60 = 1/12. Hence Akram alone can do the work in 12 days.)
-
4 : 1
-
2 : 7
-
8 : 3
-
7 : 2
-
None of these
D
Correct answer
Explanation
(2 men + 3 boys can do a job in 5 days, so in one day-5 X (2 men + 3 boys) can do it in one day. Similarly, 4 X (3 men + 2 boys) can do it in one day. Therefore, 5 X (2 men + 3 boys) = 4 X (3 men + 2 boys)2 men = 7 boys. Hence, work ratio = 7 : 2)
D
Correct answer
Explanation
Work rates: A=1/7, B=1/8, C=1/6. Cycle (3 days) = 1/7 + 1/8 + 1/6 = (24+21+28)/168 = 73/168. After 6 days (2 cycles) = 146/168. Remaining = 22/168. Day 7 (Anand) does 1/7 = 24/168. Since 24/168 > 22/168, work finishes on day 7.