Quantitative Aptitude

Time, Work, and Projects

198 Questions

Time and work questions test the ability to calculate the time required to complete tasks involving individual or combined worker efficiency. These problems frequently appear in competitive exams to assess logical calculation skills. Topics include pipes, cisterns, group efficiency, and hourly work rates.

Combined work efficiencyMen and days calculationsWorker efficiency ratiosWorking hours per dayLeaving and joining workers

Time, Work, and Projects Questions

Multiple choice
  1. 3 days

  2. 8/9 days

  3. 4 days

  4. can't say

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

A takes 8 days, so A's rate = 1/8 work per day. B works 3 times faster, so B's rate = 3/8 work per day. C works 5 times faster, so C's rate = 5/8 work per day. Combined rate = (1+3+5)/8 = 9/8 work per day. Time together = 1 ÷ (9/8) = 8/9 days.

Multiple choice
  1. 7

  2. 8

  3. 11

  4. 12

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

 A company contracts to paint 3 houses. Mr.Brown paints in 6 days = 1 house Mr.Brown paints in 1days =1/6 house Mr.Brown paints in 8days =8/6 =4/3 house work left = 3-4/3 = 5/3 house Mr.Black paints in 8 days = 1 house Mr..Black paints in 1days =1/8 house Mr..Black paints in 6days =6/8= 3/4 house work left = 5/3 - 3/4 = 11/12= .Blue paints in 12 days = 1 house .Blue paints in 1 day = 1/12 house Mr. blue will finish 11/12 huse in = (11/12)/12=11 days

Multiple choice
  1. 31 days

  2. 30 days

  3. 33 days

  4. 40 days

  5. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Work done by A in 10 days = 10/80 = 1/8 Remaining work = (1-(1/8)) = 7/8 Now, work will be done by B in 49 days. Whole work will be done by B in (49 * 8/7) = 56 days Therefore, A's one day's work = 1/80 B’s one day's work = 1/56(A + B)'s one day's work = 1/80 + 1/56 = 17/560 = 33 days Hence, both will finish the work in 33 days.

Multiple choice
  1. Rs. 512

  2. Rs. 768

  3. Rs. 675

  4. Rs. 800

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Daily wages are in the ratio 4 : 5 : 4. Working days of A, B, C = 8, 9 and 12 Wages will be in the ratio 32 : 45 : 48. Share of A = 32/(24 + 45 + 48) × 2000 = Rs. 512

Multiple choice
  1. 1/2th part, 1/18 hr

  2. 1/3th part, 1/36 hr

  3. 1/4th part, 1/9 hr

  4. 1/7th part, 1/27 hr

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

1/2 + 1/3 + 1/6 = 1 also (1/18 + 2/3 + 1/6) h = 8/9 hr. This is correct.

Multiple choice
  1. 30/13

  2. 30/11

  3. 11/13

  4. 31/13

  5. None of the above

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Work done by X in 5 days = 5*1/10 = 1/2 Balance work to be done = 1 - 1/2 = 1/2 (X + Y) 's one day's work = 1/10 + 1/12 = 11/60 Number of days Y worked = 1/2 * 60/11 = 30/11 So, option (2) is correct.

Multiple choice
  1. 40 days

  2. 35 days

  3. 30 days

  4. 60 days

  5. None of these

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Pradeep and Dipali's 1 day's work = 1/10 Dipali's 1 day's work = 1/12 Therefore, Pradeep's 1 day's work = 1/10 - 1/12 = 2/120 = 1/60 Number of days required to do the work by Pradeep = 60 days Hence, this option is correct.

Multiple choice
  1. 10 days

  2. 13 days

  3. 12 days

  4. Data inadequate

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

(Work done by both in one day = 1 ÷ 7.5 = 2/15 Work done by Salim in one day = 1/20. Therefore, work done by Akram in one day = 2/15 - 1/20 = 8 - 3/60 = 5/60 = 1/12. Hence Akram alone can do the work in 12 days.)

Multiple choice
  1. 4 : 1

  2. 2 : 7

  3. 8 : 3

  4. 7 : 2

  5. None of these

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

(2 men + 3 boys can do a job in 5 days, so in one day-5 X (2 men + 3 boys) can do it in one day. Similarly, 4 X (3 men + 2 boys) can do it in one day. Therefore, 5 X (2 men + 3 boys) = 4 X (3 men + 2 boys)2 men = 7 boys. Hence, work ratio = 7 : 2)

Multiple choice
  1. 3rd

  2. 6th

  3. 9th

  4. 7th

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Work rates: A=1/7, B=1/8, C=1/6. Cycle (3 days) = 1/7 + 1/8 + 1/6 = (24+21+28)/168 = 73/168. After 6 days (2 cycles) = 146/168. Remaining = 22/168. Day 7 (Anand) does 1/7 = 24/168. Since 24/168 > 22/168, work finishes on day 7.