A man completes 9/12 of a job in 21 days. At this rate, how many more days will it take him to finish the job?

  1. 7

  2. 6

  3. 9

  4. 10

  5. 12

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Work done=9/12 Balance work=1-9/12=3/12 Less work,Less days 9/12 --->21 days 3/12--->x days Then (9/12) *x=(3/12) * 21 x=(3*12*21)/(12*9) x=7 days It is the correct answer.

Keep practicing — related questions

  • It takes 7 men 12 days to complete a job. They worked for 5 days. After 5 days, 2 men left the job. In how ...
  • Directions: Complete the following number series. 12, 12, 21, 47, 112, ?
  • A system is using NRZ-I to transfer 12-Mbps data. Calculate the average signal rate (S) and minimum bandwid...
  • Directions: Choose the correct word/phrase to complete the given sentence. How ________ time does it take t...
  • What will be the output of the program? class Bitwise { public static void main(String [] args) { int x = 1...
  • In oogenesis after arrival of spermatozoa, completion of meiosis takes place by ____________.
  • Rohit opened a recurring deposit account in the bank by depositing Rs. 250 per month for 11 months. The rat...
  • Directions: Read the given text carefully and fill in the blank with the most appropriate option that would...
Play the full quiz 🎤 Practise this topic out loud

Practice this chapter

  • Time and Work (2195 questions)
Advertisement
© Aliensbrain | all rights reserved
  • About
  • Contact
  • Terms and Condition
  • Privacy Policy