  • It takes 7 men 12 days to complete a job. They worked for...
Multiple choice

It takes 7 men 12 days to complete a job. They worked for 5 days. After 5 days, 2 men left the job. In how many days will 5 men complete the job?

  1. 12 days

  2. 14 days

  3. 9 days

  4. 10 days

  5. None of these

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

They will take 7/12 × 84 /5 = 9.8 = 10 days (approximately) to complete the job.

Keep practicing — related questions

  • Tony has a box of apples. How many apples are in the box, 1. if he gave the apples to 7 friends equally? Th...
  • Which three are methods of the Object class? 1. notify(); 2. notifyAll(); 3. isInterrupted(); 4. synchroniz...
  • Which among the following are glucogenic intermediates? 1. Pyruvate 2. α-ketoglutarate 3. Succinyl-CoA 4. F...
  • Directions: Complete the following number series. 7, 8, 13, 5, 18, - 1, 22, - 10, 25, ?
  • Iron is an extremely important transition metal in biology. It helps in performing many different biologica...
  • Which of the following statements is/are true? A. The dihedral angle between the H-atoms in staggered confo...
  • Which of the following bacteria are examples of free-living nitrogen fixers? 1. Rhizobium 2. Beijerinckia 3...
  • Which of the following enzymes are examples of hydorlases? 1. Lactate dehydrogenase 2. Alanine deaminase 3....
Play the full quiz 🎤 Practise this topic out loud

Practice this chapter

  • Time and Work (2195 questions)
Advertisement
© Aliensbrain | all rights reserved
  • About
  • Contact
  • Terms and Condition
  • Privacy Policy