A painting job can be completed by 6 painters in 36 days. If 18 more painters join the team 8 days after starting work on the job, then how many more days are required to complete the job?
Reveal answer
Fill a bubble to check yourself
A painting job can be completed by 6 painters in 36 days. If 18 more painters join the team 8 days after starting work on the job, then how many more days are required to complete the job?