5 skilled workers can build a wall in 20days: 8 semi-skilled workers can build a wall in 25 days; 10 unskilled workers can build a wall in 30days. If a team has 2 skilled, 6 semi-skilled and 5 unskilled workers, how long will it take to build the wall?
D
Correct answer
Explanation
For skilled:
men -> days -> amount of wall
5 -> 20 -> 1
1 -> 100 -> 1
1 -> 1 -> 1/100
For semi-skilled:
men -> days -> amount of wall
8 -> 25 -> 1
1 -> 200 -> 1
1 -> 1 -> 1/200
For unskilled:
men -> days -> amount of wall
10 -> 30 -> 1
1 -> 300 -> 1
1 -> 1 -> 1/300
Amount of work 2 skilled in 1 day = 2/100
Amount of work 6 semi-skilled in 1 day = 6/200
Amount of work 5 unskilled in 1 day = 5/300
Total work in 1 day
= 2/100+6/200+5/300
= 12/600+18/600+10/600
= 1/15
So complete work will take 15 days