We are given 9 tasks T1,T2,........T9. The execution of each task requires one unit of time. We can execute one task at a time. Ti has a profit Pi and a deadline di profit Pi is earned if the task is completed before the end of the d1th unit of time.

Are all tasks completed in the schedule that gives maximum profit?

  1. All tasks are completed

  2. T1 and T6 are left out

  3. T1 and T8 are left out

  4. T4 and T6 are left out

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation