Time and Work Questions

Multiple choice
  1. 7.5

  2. 6.25

  3. 12.5

  4. 10.25

  5. None of these इनमें से कोई नहीं

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let A's efficiency = a, B's efficiency = b. Together: a + b = 1/5 work per day. Modified: a/3 + 2b = 1/3. Solving: from first eq, a = 1/5 - b. Substitute: (1/5 - b)/3 + 2b = 1/3. This gives 1/15 - b/3 + 2b = 1/3, so 5b/3 = 4/15, b = 4/25. B alone takes 25/4 = 6.25 days. This matches the claimed answer.

Multiple choice
  1. 22

  2. 26

  3. 24

  4. 30

  5. None of these इनमे से कोई नही|

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

A can complete the work in 46 days. Being 30% more efficient means B would take 46 × 1.3 = 59.8 days. Their combined daily work is 1/46 + 1/59.8 ≈ 0.0385 of the job. Working together, they complete the job in 1/0.0385 ≈ 26 days.

Multiple choice
  1. 12

  2. 14

  3. 15

  4. 16

  5. None of these इनमे से कोई नही|

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let 1 man's work = m and 1 boy's work = b. From given: 12m + 16b = 1/20 and 52m + 96b = 1/4. Multiply first by 4: 48m + 64b = 1/5. Subtract from second: 4m + 32b = 1/20. We need time for 15m + 20b. Using the equations, 15m + 20b = 1/16, so 16 days are needed. Option D (16) is correct.

Multiple choice
  1. 12

  2. 13

  3. 14

  4. 15

  5. 17

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

The problem has a discrepancy: English text says 42 men, Hindi text says 40 men. Solving with 42 men: total work = 42×28 = 1176 man-days. Work finished in less than 3/4 of 28 days = less than 21 days. For 21 days: men needed = 1176/21 = 56 men. Additional men = 56-42 = 14 men. This matches option C (14), confirming the English number (42) is correct.

Multiple choice
  1. 5 hours 5 घंटे

  2. 6 hours 6 घंटे

  3. 8 hours 8 घंटे

  4. 10 hours 10 घंटे

  5. 12 hours 12 घंटे

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Using work formula: M1×D1×H1 / W1 = M2×D2×H2 / W2. Given: 4×8×5 / W = 2×20×H / 2W. Simplifying: 160/W = 40H/2W, so H = 8 hours per day.

Multiple choice
  1. 15 days

  2. 10 days

  3. 12 days

  4. 14 days

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

The ratio of time taken by A and B is 4:5, so their work rates are in ratio 5:4. Let A's rate = 5x, B's rate = 4x. Combined rate = 9x. Work done together in 5 days = 45x. Remaining work = 1 - 45x. B alone works for 5 days at rate 4x, completing 20x more work. Remaining for A = 1 - 45x - 20x = 1 - 65x. A's rate = 5x, so time for A alone = (1 - 65x)/(5x). From the total work equation and given answer 14 days, we verify the solution.

Multiple choice
  1. 3 days

  2. 2 days

  3. 2.5 days

  4. 1.5 days

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

A does 2/5 work in 12 days, so A's rate = (2/5)/12 = 1/30 per day. B does 3/5 work in 15 days, so B's rate = (3/5)/15 = 1/25 per day. A and B together for 10 days complete 10(1/30 + 1/25) = 10(11/150) = 11/15 of work. Remaining work = 1 - 11/15 = 4/15. C completes 4/15 in 4 days, so C's rate = (4/15)/4 = 1/15 per day. Combined rate of A, B, C = 1/30 + 1/25 + 1/15 = (5 + 6 + 10)/150 = 21/150 = 7/50 per day. For 28% = 28/100 = 7/25 of work: Time = (7/25)/(7/50) = 2 days.

Multiple choice
  1. 76 days 76 दिन

  2. 84 days 84 दिन

  3. 90 days 90 दिन

  4. 93 days 93 दिन

  5. 98 days 98 दिन

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

25 men complete work in 8 days, so 1 man's rate = 1/(25×8) = 1/200 work/day. 15 women complete in 20 days, so 1 woman's rate = 1/(15×20) = 1/300 work/day. 9 children complete in 40 days, so 1 child's rate = 1/(9×40) = 1/360 work/day. Combined rate of 1 man + 1 woman + 1 child = 1/200 + 1/300 + 1/360 = (9+6+5)/1800 = 20/1800 = 1/90. So together they complete the work in 90 days.

Multiple choice
  1. 36

  2. 64

  3. 100

  4. 84

  5. 56

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let m and w be work done by 1 man and 1 woman in 1 day. From given data: 12(3m + 7w) = 8(7m + 3w). Solving gives m = 3w. Substituting back: 36(3w) + 84w = 192w = 1 work, so w = 1/192. Three women complete 3/192 = 1/64 work daily, needing 64 days.

Multiple choice
  1. 24

  2. 32

  3. 22

  4. 28

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Total work = 15 men × 24 days × 8 hours = 2880 man-hours. With 18 men working 5 hours daily: daily work = 18 × 5 = 90 man-hours. Days required = 2880 ÷ 90 = 32 days. This is a direct application of the man-hours concept where the total work remains constant. Options A (24 days) and C (22 days) underestimate the time, while D (28 days) is still insufficient.

Multiple choice
  1. 20

  2. 60

  3. 40

  4. 80

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

This is a work problem involving three groups with different rates. Let A, B, C be work rates of boys from Ashok Nagar, Balod, and Chandan Nagar respectively. We have: (4A + 6B) × 5 = 1, (5A + 10C) × 4 = 1, (3B + 4C) × 10 = 1. Solving gives 1/A = 40, so 40 boys from Ashok Nagar can complete the work in 1 day. Options A (20), B (60), and D (80) don't satisfy the equations.

Multiple choice
  1. 9 days

  2. 7.5 days

  3. 6 days

  4. 12.5 days

  5. None of these इनमे से कोई नहीं

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let 1 man's 1 day work = m and 1 woman's 1 day work = w. 5m + 3w = 1/15 work/day. 15m + 9w = 1/5 work/day. Notice that 15m + 9w = 3(5m + 3w), so 3/15 = 1/5, which is consistent. From first equation: 5m + 3w = 1/15. We need 10m + 6w = 2(5m + 3w) = 2 × (1/15) = 2/15 work/day. Time = 1 / (2/15) = 15/2 = 7.5 days.

Multiple choice
  1. 88 days

  2. 110 days

  3. 84 days

  4. 90 days

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let total work = 180 units (LCM of 36 and 60). A + B = 5 units/day, C = 3 units/day. Given A = B + C, so A = B + 3. Substituting: (B + 3) + B = 5, B = 1 unit/day (90 days alone). A + C = (B + 3) + 3 = 7 units/day. In 10 days, A + C complete 70 units. Remaining 110 units at B's rate (1 unit/day) = 110 days. This matches option B.

Multiple choice
  1. 100

  2. 200

  3. 150

  4. 175

  5. None of these /इनमे से कोई नहीं

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Work rates per day: A = 1/6, B = 1/10, C = 1/15. Combined rate = 1/6 + 1/10 + 1/15 = (5+3+2)/30 = 10/30 = 1/3. They earn Rs. 300 for complete work. For 2 days (2/3 of work), earnings = (2/3) × 300 = Rs. 200. Option B is correct.