Time and Work Questions

Multiple choice
  1. 1: 2

  2. 3: 1

  3. 1: 4

  4. 5: 1

  5. 2: 1

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let work capacity of 1 man = M and 1 boy = B per day. From first condition: 12M + 16B = 1/6 (work per day). From second: 16M + 30B = 1/4. Solving these simultaneous equations: Multiply first by 12 and second by 6 to get 144M + 192B = 2 and 96M + 180B = 1.5. Subtracting gives 48M + 12B = 0.5, so 4M + B = 1/24, which means B = 1/24 - 4M. Substituting back gives M:B = 3:1.

Multiple choice
  1. 24

  2. 40

  3. 60

  4. 72

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let P, Q, R be daily work rates. P+Q = 1/30, Q+R = 1/20. Work equation: 5P + 15Q + 18R = 1. Substitute P = 1/30 - Q and R = 1/20 - Q. This gives 5(1/30 - Q) + 15Q + 18(1/20 - Q) = 1. Solving: 1/6 - 5Q + 15Q + 9/10 - 18Q = 1, which simplifies to -8Q = -1/15, so Q = 1/120. Therefore R = 1/20 - 1/120 = 5/120 = 1/24. R alone takes 24 days.

Multiple choice
  1. 10 hours

  2. 8 hours

  3. 7 hours

  4. 6 hours

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Work = 4 examiners × 10 days × 5 hours = 200 examiner-hours. For twice the work (400 units) by 2 examiners in 20 days: 400 = 2 × 20 × h. So h = 400 / 40 = 10 hours per day (option A). This uses inverse proportion: fewer examiners means more hours needed.

Multiple choice
  1. 15 days

  2. 18 days

  3. 24 days

  4. 22 days

  5. 20 days

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

Let 1 man's 1 day work = m and 1 woman's 1 day work = w. From given: 10(4m+6w)=1 and 6(6m+12w)=1. Solving gives m=1/100 and w=1/200. Total work = 100(4/100+6/200) = 1. Work done by 2m+3w in 1 day = 2/100+3/200 = 7/200. Days needed = 1/(7/200) = 200/7 ≈ 28.57. This doesn't match option E (20 days). Solving differently: from eqns, 4m+6w=1/10 and 6m+12w=1/6, giving m=2w. Then 2m+3w = 7w. Total work = 10(4m+6w) = 10(8w+6w) = 140w. Days = 140w/7w = 20. Option E matches.

Multiple choice
  1. Rs. 21600

  2. Rs. 31600

  3. Rs. 32400

  4. Rs. 21400

  5. none of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let total work = 1 unit. A can complete in 10 days, so A's rate = 1/10 per day. A works for 3+3=6 days total, completing 6/10 = 3/5 of work. B works for 3+3=6 days, completing 2/5 of work. So B's rate = (2/5)/6 = 1/15 per day, meaning B alone would take 15 days. Earnings are split in ratio of work done: A:B = 3/5:2/5 = 3:2. B's share = (2/5) × 54000 = Rs. 21600, which matches option A.

Multiple choice
  1. 36 Days

  2. 18 Days

  3. 48 Days

  4. 24 Days

  5. none of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Father's rate: 1/88 per day. Two daughters together: 1/88 per day, so one daughter = 1/176 per day. Three sons together: 1/88 per day, so one son = 1/264 per day. Working together: Father + daughter + son = 1/88 + 1/176 + 1/264 = (3+1.5+1)/264 = 5.5/264 = 1/48. So they complete the work in 48 days, which matches option C.

Multiple choice
  1. 80 days

  2. 120 days

  3. 100 days

  4. 60 days

  5. None of these

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

When we add the work rates of all three pairs (A+B, B+C, C+A), we get 2(A+B+C) = 1/72 + 1/120 + 1/90 = 12/360 = 1/30. Therefore A+B+C's combined rate is 1/60 work per day, meaning they complete the work in 60 days.

Multiple choice
  1. 7.5

  2. 13

  3. 11

  4. 9

  5. None of these इनमे से कोई नहीं

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Riya's work rate: 1/5 per day. Combined rate: 1/3 per day. Son's rate = 1/3 - 1/5 = 2/15 per day. Time for son alone = 15/2 = 7.5 days.

Multiple choice
  1. 15 days 15 दिन

  2. 18 days 18 दिन

  3. 24 days 24 दिन

  4. 20 days 20 दिन

  5. 16 days 16 दिन

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

16 men × 40 = 640 man-days. Converting: 20 women = 16 men, so 1 woman = 0.8 man. 32 boys = 16 men, so 1 boy = 0.5 man. Combined team: 8 men + 30(0.8) + 16(0.5) = 8 + 24 + 8 = 40 men equivalent. Days needed = 640/40 = 16 days. Option A would require 42.7 man-equivalents, Option B would require 35.6.

Multiple choice
  1. 30 days

  2. 24 days

  3. 18 days

  4. 12 days

  5. None of these इनमें से कोई नहीं

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A completes in 36 days, so A's rate = 1/36. B is 20% more efficient: rate = 1.2/36 = 1/30 (B completes in 30 days). C is 20% less efficient: rate = 0.8/36 = 1/45 (C completes in 45 days). Combined rate of B and C = 1/30 + 1/45 = 3/90 + 2/90 = 5/90 = 1/18. Option C (18 days) is correct.

Multiple choice
  1. 30 days 30 दिन

  2. 24 days 24 दिन

  3. 26 days 26 दिन

  4. 28 days 28 दिन

  5. None of these इनमें से कोई नहीं

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

x + y together do work in 8 days, so their combined rate = 1/8 work per day. x alone takes 12 days, so x's rate = 1/12 work per day. y's rate = combined rate - x's rate = 1/8 - 1/12 = (3-2)/24 = 1/24. So y alone takes 24 days.

Multiple choice
  1. 4(7/15) days 4(7/15) दिन

  2. 5(5/23) days 5(5/23) दिन

  3. 5(5/23) days 6(3/19) दिन

  4. 4(13/25) days 4(13/25) दिन

  5. None of these इनमें से कोई नहीं

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

A's rate = 1/15, B's rate = 1/12. C completes 3/4 work in 18 days, so full work in 24 days (18 × 4/3), rate = 1/24. Combined rate = 1/15 + 1/12 + 1/24 = 8/120 + 10/120 + 5/120 = 23/120. Time = 120/23 = 5(5/23) days.

Multiple choice
  1. 24 days 24 दिन

  2. 48 days 48 दिन

  3. 36 days 36 दिन

  4. 12 days 12 दिन

  5. 60 days 60 दिन

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let total work = 12 units (LCM of 12). Combined rate = 1 unit/day. Given: A + C = 2B and A + B = 3C. Solving: from A + B = 3C, we get A = 3C - B. Substitute in A + C = 2B: (3C - B) + C = 2B, so 4C = 3B, B = (4/3)C. Then A = 3C - (4/3)C = (5/3)C. Sum of rates: (5/3)C + (4/3)C + C = 1, so (12/3)C = 1, C = 1/4. C alone takes 12/(1/4) = 48 days.

Multiple choice
  1. 5 days

  2. 6 days

  3. 8 days

  4. 10 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Work = 100 men × 40 days = 4000 man-days. Work done in first 35 days by 100 men = 3500 man-days. Remaining work = 500 man-days, done by 200 men in 2.5 days. Without extra men, 500 man-days would take 500/100 = 5 more days. Total = 35 + 5 = 40 days, so delay = 45 - 40 = 5 days.