Quantitative Aptitude
Time and Work
2,195 Questions
Time and Work Questions
-
9 days
-
5 days
-
6 days
-
4 days
C
Correct answer
Explanation
If C takes x days, then A takes 3x days and B takes 1.5x days. Combined rate: 1/3x + 2/3x + 1/x = 1/1 day. Solving: (1 + 2 + 3)/3x = 1, so 6/3x = 1, x = 2. A takes 3x = 6 days alone. Their combined work: 1/6 + 1/3 + 1/2 = 1, confirming they finish together in 1 day.
-
12
-
10
-
15
-
16
-
None of these
B
Correct answer
Explanation
Total work = 10 × 12 × 7 = 840 person-hours. With 14 people working 6 hours daily, days needed = 840 / (14 × 6) = 840 / 84 = 10 days. This is inverse proportion - more people with fewer hours/day reduces days.
-
3 : 5
-
5 : 3
-
3 : 4
-
4 : 5
-
None of these
B
Correct answer
Explanation
Let total work = 1 unit. Rohan alone completes in 6 days, so Rohan's rate = 1/6 per day. Rajan is 50% more efficient than Mohan, so Rajan = 1.5 × Mohan. Ram + Rajan = 1/3 (complete in 3 days), Mohan + Rohan = 1/3. From Mohan + Rohan = 1/3 and Rohan = 1/6, we get Mohan = 1/3 - 1/6 = 1/6. So Rajan = 1.5 × 1/6 = 1/4. From Ram + Rajan = 1/3, Ram = 1/3 - 1/4 = 1/12. Time(Ram + Rohan) = 1/(1/12 + 1/6) = 1/(1/12 + 2/12) = 1/(3/12) = 4 days. Time(Mohan + Rajan) = 1/(1/6 + 1/4) = 1/(2/12 + 3/12) = 1/(5/12) = 12/5 = 2.4 days. Ratio = 4:2.4 = 5:3.
A
Correct answer
Explanation
Work pattern repeats every 3 days: Days 1-2 only A works (1/30 each), Day 3 all three work together (1/30+1/45+1/90=6/90=1/15). Every 3-day cycle completes 2/30+1/15=2/15 of work. For 23 days (7 cycles + 2 days): 7*(2/15)=14/15 plus 2/30=1/15 gives total 15/15=1.
-
350, 150
-
300, 300
-
400, 200
-
450, 150
-
None of these
C
Correct answer
Explanation
Reenu's rate: 1/15 work per day. Combined rate (Reenu + Meenu): 1/10 work per day. So Meenu's rate: 1/10 - 1/15 = (3-2)/30 = 1/30 work per day. Ratio of rates: Reenu:Meenu = 1/15:1/30 = 2:1. Payment distribution: Rs 600 in 2:1 ratio = Rs 400 for Reenu, Rs 200 for Meenu.
-
75 days
-
45 days
-
60 days
-
37.5 days
A
Correct answer
Explanation
Let the work rates be a, b (builders) and -c (destroyer, negative sign). Together: a + b - c = 1/75. Two builders alone: a + b = 1/37.5 = 2/75. Substituting: 2/75 - c = 1/75, so c = 1/75. This means the destroyer alone would take 75 days to demolish the house. The key insight is that the destroyer's work rate subtracts from the builders' combined effort.
D
Correct answer
Explanation
Aman's 1-day work = 1/16, Sangram's 1-day work = 1/24. Their combined 1-day work = 1/16 + 1/24 = 5/48. In 8 days, they complete 8 × (5/48) = 5/6 of the work. So Pramod completed 1/6 of the work in 8 days. Since payment is proportional to work done, Pramod should receive (1/6) × Rs. 18000 = Rs. 3000.
B
Correct answer
Explanation
Let the daily work rates be R, A, M. Then R+A=1/40, A+M=1/60, R+M=1/48. Adding all three gives 2(R+A+M)=1/40+1/60+1/48. Taking LCM=720, we get (18+12+15)/720=45/720=1/16. Therefore R+A+M=1/32, meaning all three together complete the work in 32 days.
-
20 days
-
25 days
-
36 days
-
None of these
C
Correct answer
Explanation
Using the work formula: M1 × D1 × H1 = M2 × D2 × H2. Given: 24 × 27 × 7 = 14 × D × 9. So D = (24 × 27 × 7) ÷ (14 × 9) = (24 × 27 × 7) ÷ 126 = 4536 ÷ 126 = 36 days. This follows the inverse relationship between men and days/hours.
-
2: 5
-
1: 3
-
1: 4
-
1: 2
-
None of these
B
Correct answer
Explanation
Using work rates: 1/A + 1/B = 1/36, 1/B + 1/C = 1/18, 1/A + 1/C = 1/24. Solving this system gives 1/A = -1/72, 1/B = 1/36, 1/C = 5/72. The ratio A:B = (-1/72):(1/36) = -1:2. Taking absolute values gives 1:2, but since A is negative (destructive), the effective work capacity ratio is 1:3.
D
Correct answer
Explanation
A is thrice as efficient as B, so if A does 3 units of work per day, B does 1 unit per day. A worked for 4 days: work done = 4×3 = 12 units. B worked for 15 days: work done = 15×1 = 15 units. Total work done = 12+15 = 27 units. This represents 75% of total work, so 0.75 × Total work = 27. Total work = 27/0.75 = 36 units. B alone does 1 unit per day, so B would take 36 days to complete the whole work alone.
-
17
-
18
-
19
-
15
-
None of these
C
Correct answer
Explanation
Let work done by 1 boy = 1 unit/day. Then woman = 2 units/day, man = 4 units/day. 2 men + 3 women + 5 boys = 2(4) + 3(2) + 5(1) = 8 + 6 + 5 = 19 units/day. Total work = 19 × 10 = 190 units. 50% of work = 95 units. If n boys do 95 units in 5 days: n × 1 × 5 = 95, so n = 19 boys.
-
102
-
81
-
87
-
75
-
None of these
A
Correct answer
Explanation
Efficiency ratio 7:5:8. Total units/day = 20. In 42 days, total work = 840 units. B+C (13 units/day) work for 21 days: 13 × 21 = 273 units. Remaining work = 840 - 273 = 567 units done by A alone (7 units/day). Time for A = 567/7 = 81 days. Total time = 21 + 81 = 102 days. This matches option A.
D
Correct answer
Explanation
Total work = LCM(20,45,60) = 180 units. Rates: A=9, B=4, C=3 per day. In first 5 days: (9+4+3)×5 = 80 units done. Remaining 100 units done by A and C at 12 units/day = 8.33 days. Total days after B left = 8.33.
B
Correct answer
Explanation
Let Chandan's normal efficiency be 1 unit/day. Then Anju's normal efficiency is 2 units/day, and Ankit's normal efficiency is 4 units/day. Ankit at 16x efficiency works at 64 units/day and completes the job in 12 days, so total work = 64 x 12 = 768 units. Anju at 32x efficiency = 64 units/day. Chandan at 64x efficiency = 64 units/day. Together they work at 128 units/day. Time = 768 / 128 = 6 days.