Time and Work Questions

Multiple choice
  1. 9 days

  2. 5 days

  3. 6 days

  4. 4 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

If C takes x days, then A takes 3x days and B takes 1.5x days. Combined rate: 1/3x + 2/3x + 1/x = 1/1 day. Solving: (1 + 2 + 3)/3x = 1, so 6/3x = 1, x = 2. A takes 3x = 6 days alone. Their combined work: 1/6 + 1/3 + 1/2 = 1, confirming they finish together in 1 day.

Multiple choice
  1. 3 : 5

  2. 5 : 3

  3. 3 : 4

  4. 4 : 5

  5. None of these

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let total work = 1 unit. Rohan alone completes in 6 days, so Rohan's rate = 1/6 per day. Rajan is 50% more efficient than Mohan, so Rajan = 1.5 × Mohan. Ram + Rajan = 1/3 (complete in 3 days), Mohan + Rohan = 1/3. From Mohan + Rohan = 1/3 and Rohan = 1/6, we get Mohan = 1/3 - 1/6 = 1/6. So Rajan = 1.5 × 1/6 = 1/4. From Ram + Rajan = 1/3, Ram = 1/3 - 1/4 = 1/12. Time(Ram + Rohan) = 1/(1/12 + 1/6) = 1/(1/12 + 2/12) = 1/(3/12) = 4 days. Time(Mohan + Rajan) = 1/(1/6 + 1/4) = 1/(2/12 + 3/12) = 1/(5/12) = 12/5 = 2.4 days. Ratio = 4:2.4 = 5:3.

Multiple choice
  1. 23

  2. 24

  3. 30

  4. 22.5

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Work pattern repeats every 3 days: Days 1-2 only A works (1/30 each), Day 3 all three work together (1/30+1/45+1/90=6/90=1/15). Every 3-day cycle completes 2/30+1/15=2/15 of work. For 23 days (7 cycles + 2 days): 7*(2/15)=14/15 plus 2/30=1/15 gives total 15/15=1.

Multiple choice
  1. 350, 150

  2. 300, 300

  3. 400, 200

  4. 450, 150

  5. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Reenu's rate: 1/15 work per day. Combined rate (Reenu + Meenu): 1/10 work per day. So Meenu's rate: 1/10 - 1/15 = (3-2)/30 = 1/30 work per day. Ratio of rates: Reenu:Meenu = 1/15:1/30 = 2:1. Payment distribution: Rs 600 in 2:1 ratio = Rs 400 for Reenu, Rs 200 for Meenu.

Multiple choice
  1. 75 days

  2. 45 days

  3. 60 days

  4. 37.5 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let the work rates be a, b (builders) and -c (destroyer, negative sign). Together: a + b - c = 1/75. Two builders alone: a + b = 1/37.5 = 2/75. Substituting: 2/75 - c = 1/75, so c = 1/75. This means the destroyer alone would take 75 days to demolish the house. The key insight is that the destroyer's work rate subtracts from the builders' combined effort.

Multiple choice
  1. 9000

  2. 6000

  3. 4000

  4. 3000

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Aman's 1-day work = 1/16, Sangram's 1-day work = 1/24. Their combined 1-day work = 1/16 + 1/24 = 5/48. In 8 days, they complete 8 × (5/48) = 5/6 of the work. So Pramod completed 1/6 of the work in 8 days. Since payment is proportional to work done, Pramod should receive (1/6) × Rs. 18000 = Rs. 3000.

Multiple choice
  1. 28

  2. 32

  3. 24

  4. 30

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let the daily work rates be R, A, M. Then R+A=1/40, A+M=1/60, R+M=1/48. Adding all three gives 2(R+A+M)=1/40+1/60+1/48. Taking LCM=720, we get (18+12+15)/720=45/720=1/16. Therefore R+A+M=1/32, meaning all three together complete the work in 32 days.

Multiple choice
  1. 20 days

  2. 25 days

  3. 36 days

  4. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Using the work formula: M1 × D1 × H1 = M2 × D2 × H2. Given: 24 × 27 × 7 = 14 × D × 9. So D = (24 × 27 × 7) ÷ (14 × 9) = (24 × 27 × 7) ÷ 126 = 4536 ÷ 126 = 36 days. This follows the inverse relationship between men and days/hours.

Multiple choice
  1. 2: 5

  2. 1: 3

  3. 1: 4

  4. 1: 2

  5. None of these

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Using work rates: 1/A + 1/B = 1/36, 1/B + 1/C = 1/18, 1/A + 1/C = 1/24. Solving this system gives 1/A = -1/72, 1/B = 1/36, 1/C = 5/72. The ratio A:B = (-1/72):(1/36) = -1:2. Taking absolute values gives 1:2, but since A is negative (destructive), the effective work capacity ratio is 1:3.

Multiple choice
  1. 27

  2. 45

  3. 24

  4. 36

  5. 42

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

A is thrice as efficient as B, so if A does 3 units of work per day, B does 1 unit per day. A worked for 4 days: work done = 4×3 = 12 units. B worked for 15 days: work done = 15×1 = 15 units. Total work done = 12+15 = 27 units. This represents 75% of total work, so 0.75 × Total work = 27. Total work = 27/0.75 = 36 units. B alone does 1 unit per day, so B would take 36 days to complete the whole work alone.

Multiple choice
  1. 17

  2. 18

  3. 19

  4. 15

  5. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let work done by 1 boy = 1 unit/day. Then woman = 2 units/day, man = 4 units/day. 2 men + 3 women + 5 boys = 2(4) + 3(2) + 5(1) = 8 + 6 + 5 = 19 units/day. Total work = 19 × 10 = 190 units. 50% of work = 95 units. If n boys do 95 units in 5 days: n × 1 × 5 = 95, so n = 19 boys.

Multiple choice
  1. 102

  2. 81

  3. 87

  4. 75

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Efficiency ratio 7:5:8. Total units/day = 20. In 42 days, total work = 840 units. B+C (13 units/day) work for 21 days: 13 × 21 = 273 units. Remaining work = 840 - 273 = 567 units done by A alone (7 units/day). Time for A = 567/7 = 81 days. Total time = 21 + 81 = 102 days. This matches option A.

Multiple choice
  1. 12.25

  2. 10.75

  3. 9.67

  4. 8.33

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Total work = LCM(20,45,60) = 180 units. Rates: A=9, B=4, C=3 per day. In first 5 days: (9+4+3)×5 = 80 units done. Remaining 100 units done by A and C at 12 units/day = 8.33 days. Total days after B left = 8.33.

Multiple choice
  1. 8

  2. 6

  3. 5

  4. 4

  5. None of these

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let Chandan's normal efficiency be 1 unit/day. Then Anju's normal efficiency is 2 units/day, and Ankit's normal efficiency is 4 units/day. Ankit at 16x efficiency works at 64 units/day and completes the job in 12 days, so total work = 64 x 12 = 768 units. Anju at 32x efficiency = 64 units/day. Chandan at 64x efficiency = 64 units/day. Together they work at 128 units/day. Time = 768 / 128 = 6 days.