Time and Work Questions

Multiple choice
  1. 33 days

  2. 26 days

  3. 13 days

  4. 30 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

A's work rate is 1/30 per day. B's work rate is 1/40 per day. In 3 days together, they complete 3(1/30 + 1/40) = 3(7/120) = 7/40 of the work. Remaining work is 1 - 7/40 = 33/40. B alone needs (33/40) ÷ (1/40) = 33 days to finish the remaining work. Option A is correct.

Multiple choice
  1. 8

  2. 10

  3. 15

  4. 20

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

20 boys complete 1/4 of the work in 25 days, so the work rate is (1/4) / (20 × 25) = 1/2000 per boy-day. The remaining 3/4 of the work must be completed in 50 days. Let x be the additional boys needed: (20 + x) × 50 × (1/2000) = 3/4. Solving gives 20 + x = 30, so x = 10 more boys are required.

Multiple choice
  1. 45

  2. 52

  3. 60

  4. 36

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Combined rate of A and B is 1/40 work per day. In 8 days, they complete 8/40 = 1/5 of work, leaving 4/5. B finishes this 4/5 in 36 days, so B's rate is (4/5)/36 = 1/45 per day. Therefore, B alone can complete the work in 45 days. The other options don't satisfy the work equation.

Multiple choice
  1. 17

  2. 19

  3. 18

  4. 20

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

A is 1.5 times efficient as B, so A's work: B's work = 3:2. Let A take x days, B takes x+8 days. Work ratio gives (x+8)/x = 3/2, so 2x+16 = 3x, x = 16. A takes 16 days, B takes 24 days. Total work = LCM(16,24) = 48 units. A/day = 3, B/day = 2. Working alternately starting with A for 10 days (5 cycles): work = 5×(3+2) = 25 units. Remaining 23 units: day 11 (A) does 3, day 12 (B) does 2, day 13 (A) does 3, day 14 (B) does 2, day 15 (A) does 3, day 16 (B) does 2, day 17 (A) does 3, day 18 (B) does 2, day 19 (A) does remaining 3. Total 19 days.

Multiple choice
  1. 7.5 days

  2. 11.5 days

  3. 12 days

  4. 15 days

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Mohan's rate is 1/25 per day. In 5 days he completes 5/25 = 1/5 of work. Remaining 4/5 is done by Bhim in 30 days, so Bhim's rate is (4/5)/30 = 2/75 per day. If Bhim works 15 days first, he completes 30/75 = 2/5. Remaining 3/5 at Mohan's rate (1/25) takes (3/5)/(1/25) = 15 days. Option D is correct.

Multiple choice
  1. 120

  2. 72

  3. 150

  4. 140

  5. None of these

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

A completes 1/24 of the work daily while B handles 1/48 per day. Working together, their combined rate is 1/16 per day. A's contribution ratio is (1/24)/(1/16) = 2/3, earning Rs 240 from the Rs 360 total, which is not listed in options A-D.

Multiple choice
  1. 600/17

  2. 600/23

  3. 1200/23

  4. 1200/17

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Given rates: A+B = 1/20, B+C = 1/25, C+A = 1/15 work per day. Adding all three equations: 2(A+B+C) = 1/20 + 1/25 + 1/15 = (15 + 12 + 20)/300 = 47/300. Therefore A+B+C = 47/600. To find A alone: A = (A+B+C) - (B+C) = 47/600 - 1/25 = 47/600 - 24/600 = 23/600 work per day. Thus A alone takes 600/23 days to complete the work. This is a standard combined work problem requiring algebraic manipulation of rates.

Multiple choice
  1. 7.1

  2. 7.2

  3. 6.4

  4. 5.8

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let P+Q = 8, so (P+Q)'s work = 1/8 per day. Q+R = 16, so (Q+R)'s work = 1/16 per day. R+P = 8, so (R+P)'s work = 1/8 per day. Adding all three equations: 2(P+Q+R) = 1/8 + 1/16 + 1/8 = 5/16, so P+Q+R = 5/32. Time for all three = 32/5 = 6.4 days.

Multiple choice
  1. 78

  2. 90

  3. 96

  4. 114

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Combined work rate of X, Y, Z is 1/18. X's rate is 1/36, Y's rate is 1/60. Z's rate = 1/18 - 1/36 - 1/60 = 10/180 - 5/180 - 3/180 = 2/180 = 1/90. Therefore, Z alone takes 90 days to complete the work.

Multiple choice
  1. $Rs.760$
  2. $Rs.620$
  3. $Rs.680$
  4. $Rs.540$
Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Work rates: A completes in 15 days (rate 1/15), B in 30 days (rate 1/30), C in 75 days (rate 1/75). Taking LCM of 150 as work units: A does 10 units/day, B does 5 units/day, C does 2 units/day. Total 17 units/day means work finishes in 150/17 days. Payment is divided in ratio 10:5:2, so A gets Rs. 950, C gets Rs. 190. Difference is Rs. 760.

Multiple choice
  1. 1080 Rs.

  2. 3500 Rs.

  3. 3780 Rs.

  4. 7000 Rs.

  5. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A does 20% work in 8 days → A's 1 day work = 20%/8 = 2.5%. B does 30% in 12 days → B's 1 day work = 30%/12 = 2.5%. C does 40% in 18 days → C's 1 day work = 40%/18 ≈ 2.22%. B and C work ratio is 2.5:2.22. B-C wage difference = Rs 12 for 1 day. A's wage for 35 days = (A's work/B's work) × (B's wage - C's wage) × 35 = (2.5/2.5) × 12 × 35 = Rs 3780.

Multiple choice
  1. 11

  2. 28

  3. 33

  4. 18

  5. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Given: A+B=30 days, B+C=24 days, C+A=20 days. Combined rate (A+B+C)/2 = (1/30+1/24+1/20)/2 = (4+5+6)/120 × 1/2 = 15/240 = 1/16, so all three complete work in 16 days together. In 5 days they complete 5/16 of work. Remaining 11/16 done by A alone at rate (1/16 - 1/24) = (3-2)/48 = 1/48. Time = (11/16)/(1/48) = 11×3 = 33 days. Option C is correct.

Multiple choice
  1. 9

  2. 10

  3. 12

  4. 15

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let d be the number of days for 40 men. Work = 40d man-days. With 30 men: 30(d + 6) = 40d, so 30d + 180 = 40d, giving d = 18 days. Total work = 40 × 18 = 720 man-days. With 60 men: days = 720/60 = 12 days. Alternatively, 60 men is 1.5 times 40 men, so time is 18/1.5 = 12 days.