Time and Work Questions

Multiple choice
  1. 15

  2. 22

  3. 18

  4. Data inadequate

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

12 men in 4 days means total work = 48 man-days. So 1 man does 1/48 of work per day. 6 men work for 2 days, completing 6 × 2 × (1/48) = 12/48 = 1/4 of work. Remaining 3/4 work must be done in 3 days. 15 women complete full work in 4 days, so 1 woman does 1/60 per day. In 3 days, 15 women do 15 × 3 × (1/60) = 45/60 = 3/4 of work. Exactly what's needed.

Multiple choice
  1. The question cannot be answered even with the help of both the statements together.

  2. The question can be answered with the help of statement II alone.

  3. The question can be answered with the help of statement I alone.

  4. The question can be answered with the help of both statements together.

  5. The question can be answered with either statement I or statement II.

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

A completes work in 18 days, so A's rate = 1/18 per day. After 9 days, A completes 9/18 = 1/2 of work. Remaining = 1/2. Statement I: B works faster than A (insufficient). Statement II: A:B work ratio = 2:3, so B's rate = (3/2)×(1/18) = 1/12 per day. Combined rate = 1/18 + 1/12 = 5/36 per day. Time for half work = (1/2)/(5/36) = 18/5 = 3.6 days. Statement II alone is sufficient.

Multiple choice
  1. 250

  2. 320

  3. 280

  4. 350

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

A, B, C can complete work in 10, 12, 15 days respectively. Their work per day ratios are 1/10 : 1/12 : 1/15 = 6:5:4 (LCM method). Total parts = 6+5+4 = 15. B's share = (5/15) × 750 = 250. Wages are distributed in proportion to work contribution.

Multiple choice
  1. 78

  2. 76

  3. 72

  4. 84

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let A+B, B+C, C+A work rates be 1/20, 1/30, 1/40 respectively per day. Adding all: 2(A+B+C) = 1/20+1/30+1/40 = 13/120. So A+B+C = 13/240 per day. C alone = (13/240) - (1/20) = 13/240-12/240 = 1/240 per day. For 30% work: 0.3×240 = 72 days.

Multiple choice
  1. 30 days

  2. 32 days

  3. 36 days

  4. 46 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Total work = 80 × 30 = 2400 man-days. Work completed in first 10 days with 80 men = 800 man-days. Work in next 10 days (11-20) with 70 men = 700 man-days. Work in next 10 days (21-30) with 60 men = 600 man-days. After 30 days, total work done = 2100 man-days. Remaining work = 300 man-days with 50 men, which takes 300/50 = 6 days. Total time = 30 + 6 = 36 days.

Multiple choice
  1. 20 days

  2. 25 days

  3. 30 days

  4. 34 days

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let total work = 1 unit. A and B together complete in 40 days, so their combined rate = 1/40 per day. In first 10 days, they complete 10 × (1/40) = 1/4 work. Remaining = 3/4. Now their rate doubles to 1/20 per day. Time for remaining = (3/4) ÷ (1/20) = 15 days. Total = 10 + 15 = 25 days.

Multiple choice
  1. 9

  2. 9.5

  3. 9.375

  4. 10

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

If Pranesh completes the work in 15 days, his rate is 1/15 work per day. Avinash is 60% more efficient, so his rate is (1/15) × 1.60 = 1.6/15. The time Avinash needs is the reciprocal: 15/1.6 = 9.375 days. This is calculated by dividing Pranesh's time by (1 + efficiency percentage as decimal). Option C is correct.

Multiple choice
  1. 35 days

  2. 32 days

  3. 45 days

  4. 40 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

If Mohit is 5 times as efficient as Rohit, he takes 1/5 the time to complete the same work. Let Rohit take R days. Then R - R/5 = 28, giving 4R/5 = 28, so R = 35 days. Rohit alone completes the work in 35 days. Option A is correct.

Multiple choice
  1. 10

  2. 14

  3. 15

  4. 9

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A completes 1/20 of the work daily. B completes 1/30 daily, and C completes 1/60 daily. On every third day, all three work together, completing 1/20 + 1/30 + 1/60 = 6/60 = 1/10 of the work. The 3-day cycle completes 1/20 + 1/20 + 1/10 = 1/5 of the work. In 15 days (5 cycles), they complete 5 × (1/5) = 1, meaning the entire work is finished. The other options don't align with this cyclical pattern.

Multiple choice
  1. 11

  2. 14

  3. 15

  4. 13

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let m and w be work done by 1 man and 1 woman per day. From given: 4m + 5w = 1/15 and 9m + 6w = 1/10. Solving gives w = 2m. For 4 men and x women to finish in 7 days: 4m + x(2m) = 1/7. Substituting m = 1/210 gives x = 13 women.

Multiple choice
  1. Only I and III

  2. All three together are sufficient

  3. All three together are not sufficient

  4. I or (II and III) are sufficient

  5. II or (I and III) are sufficient

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

Rashmi worked for 4 days when 25% work was done. So remaining work = 75%. Statement I: Rashmi + Sweta complete in 80/9 days, so combined rate = 9/80 per day. Statement III: Sweta's efficiency is 20% less than Rashmi, so Sweta's rate = 0.8 × Rashmi's rate. If Rashmi's rate = r, then r + 0.8r = 9/80, so 1.8r = 9/80, r = 1/16 per day. For 75% work at rate 1/16: days = (3/4)/(1/16) = 12 days. Statements II and III are sufficient. Alternatively: I+III gives Rashmi's rate = 1/16, and we know 4 days were worked. We need to know how much work is left (from II) to calculate remaining days. So 'II or (I and III)' are sufficient. Claimed answer E is correct.

Multiple choice
  1. Quantity I > Quantity II

  2. Quantity I < Quantity II

  3. Quantity I ≥ Quantity II

  4. Quantity I ≤ Quantity II

  5. Quantity I = Quantity II or No relationship can be established

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

Mahesh: 60 days. Kavya+Sarita: 15 days. Mahesh+Sarita (alternate days): 40 days. Let Kavya take k days, Sarita take s days. Kavya+Sarita combined rate: 1/15. Mahesh's rate: 1/60. When working alternate days, in 40 days they complete 40*(1/60 + 1/s)/2 = 40/120 + 20/s. This equals 1. So 1/3 + 20/s = 1, giving s = 30. So Sarita takes 30 days. Then Kavya takes 1/(1/15 - 1/30) = 30 days. Both take 30 days, so Kavya = Sarita, meaning Quantity I = Quantity II.

Multiple choice
  1. 14 days

  2. 12 days

  3. 15 days

  4. 10 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let X's efficiency = 5k, Y's efficiency = 4k. Combined efficiency = 9k. Together they complete work in 10 days, so total work = 90k. Y works alone for 5 days, completing 20k. Remaining work = 70k. X alone does 5k per day, so time needed = 70k/5k = 14 days. Option A is correct.

Multiple choice
  1. 10

  2. 12

  3. 15

  4. 20

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Combined work rate of A, B, C = 1/12 work per day. A and B complete 7/12 work in 14 days, so their rate = (7/12)/14 = 1/24 per day. Therefore, C's rate = (1/12 - 1/24) = 1/24 per day. C completed 5/12 work alone, so time = (5/12)/(1/24) = 10 days.