Time and Work Questions

Multiple choice
  1. $25.8$
  2. $26.3$
  3. $25.5$
  4. $25.1$
  5. $None of these$
Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Raman's rate = 1/45 work per day. Anju's rate = 1/75 work per day. Combined rate = 1/45 + 1/75 = (5 + 3)/225 = 8/225 per day. In 12 days together, they complete 12 × 8/225 = 96/225 = 32/75 of work. Remaining work = 1 - 32/75 = 43/75. Raman alone does (43/75) × 45 = 43 × 3/5 = 129/5 = 25.8 days. Option A matches.

Multiple choice
  1. 4 days

  2. 2 days

  3. 8 days

  4. 12 days

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let S, D, E, G be days for each person. Given: E = S-4, G = D/4. Combined rate: 1/S + 1/D + 1/E + 1/G = 1. After G drops, S+D+E work 1 day, then S+D work 2 more days: 3/S + 3/D + 1/E = 1. Solving with E=S-4 gives S=8, E=4 days. Claimed answer A is correct.

Multiple choice
  1. 110 days

  2. 88 days

  3. 84 days

  4. 90 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let A, B, C be daily work rates. Given A = B + C, A + B = 1/36, C = 1/60. Substituting: B + 1/60 + B = 1/36, so 2B = 1/36 - 1/60 = (5-3)/180 = 2/180, thus B = 1/180. Therefore A = 1/180 + 1/60 = 4/180 = 1/90. A and C together in 10 days complete 10*(1/90 + 1/60) = 10*(2/180 + 3/180) = 10*(5/180) = 25/90 = 5/6 of the work. Remaining 1/6 is done by B alone at rate 1/180, taking (1/6)/(1/180) = 30 days. Total days for B alone to complete remaining work = 110 days.

Multiple choice
  1. 6

  2. 8

  3. 9

  4. 12

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

A's work rate: 1/20 work per day. B completes 20% in 6 days, so B's rate = 0.2/6 = 1/30 work per day. Combined rate: 1/20 + 1/30 = 5/60 = 1/12 work per day. For 50% of work: (1/2) ÷ (1/12) = 6 days. Together they complete half the work in exactly 6 days.

Multiple choice
  1. 60

  2. 54

  3. 6

  4. 27

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Work rates: A = 1/20, B = 1/30, C = 1/60 per day. Combined for 1 day: 1/20 + 1/30 + 1/60 = 3/60 + 2/60 + 1/60 = 6/60 = 1/10. Work done = 1/10, remaining = 9/10. C's rate = 1/60, so C needs (9/10) ÷ (1/60) = 9/10 × 60 = 54 days. Option 60 ignores the first day's work, 6 is the error of taking 1/10 directly, 27 is a miscalculation.

Multiple choice
  1. 30

  2. 35

  3. 48

  4. 36

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Total work = 45 men × 12 hours/day × 16 days = 8640 man-hours. For 30 men working 8 hours/day: days needed = 8640 ÷ (30 × 8) = 8640 ÷ 240 = 36 days. This uses the formula M1D1H1 = M2D2H2 for work problems. The key inverse relationship is that fewer men and fewer hours per day both require more days.

Multiple choice
  1. 13 days

  2. 25 days

  3. 14 days

  4. 11 days

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

In 2 days, work done = 1/17 + 1/51 = 4/51. In 24 days, work = 24/2 × 4/51 = 48/51. Day 25: Sai does 1/17 ≈ 0.059, so total = 48/51 + 1/17 = 51/51 = 1. Work completes on day 25. Day 13 gives only 26/51 (half done), and 14 days gives 28/51, still incomplete.

Multiple choice
  1. 18

  2. 27

  3. 13.5

  4. 27.5

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A's 1 day work = 1/27, B's 1 day work = 1/45. Let total days = d. A works for (d-9) days, B works for d days. (d-9)/27 + d/45 = 1. Multiply by 135: 5(d-9) + 3d = 135, so 8d - 45 = 135, 8d = 180, d = 22.5. A works for 22.5 - 9 = 13.5 days.

Multiple choice
  1. 14 days

  2. 16 days

  3. 15 days

  4. 18 days

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let R, K, M be the fraction of work each person completes in one day. We have: R+K = 1/20, K+M = 1/30, M+R = 1/24. Adding all three: 2(R+K+M) = 1/20 + 1/30 + 1/24 = 6/120 + 4/120 + 5/120 = 15/120 = 1/8. Therefore, R+K+M = 1/16, meaning all three together complete 1/16 of the wall per day, so the work is finished in 16 days.

Multiple choice
  1. Quantity I > Quantity II

  2. Quantity I ≥ Quantity II

  3. Quantity I < Quantity II

  4. Quantity I ≤ Quantity II

  5. Quantity I = Quantity II or relation can't be established

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let Q's efficiency = 1 unit/day. P's efficiency = 1.4 units/day (40% more). Together: 2.4 units/day = 1/70 work, so total work = 70 × 2.4 = 168 units. P alone: 168/1.4 = 120 days. Q alone: 168/1 = 168 days. Quantity I: P at 25% efficiency = 0.35 units/day. For 1/8 work = 21 units, time = 21/0.35 = 60 days. Quantity II: Q at 20% efficiency = 0.2 units/day. For 10% work = 16.8 units, time = 16.8/0.2 = 84 days. Since 60 < 84, Quantity I < Quantity II. Key is computing total work first, then adjusting efficiency.

Multiple choice
  1. 45

  2. 48

  3. 35

  4. 40

  5. None of these

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

5 women's work = 56 days, so total work = 5 × 56 = 280 woman-days. 10 men's work = 56 days, so total work = 10 × 56 = 560 man-days. Therefore 1 woman = 560/280 = 2 men. 5 women + 4 men = 5(2) + 4 = 14 men. Time = 560/14 = 40 days. Option D is correct.

Multiple choice
  1. 12

  2. 16

  3. 19

  4. 22

  5. None of the above

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let total work = 1 unit. A+P+X's combined rate = 1/22 per day. P+X complete 7/11 work in 28 days, so their rate = 7/(11×28) = 1/44 per day. Therefore A's rate = 1/22 - 1/44 = 1/44 per day. A worked for n days, completing n/44 work. The remaining 7/11 work was done by P+X. So n/44 + 7/11 = 1, giving n/44 = 4/11, hence n = 16 days.