Time and Work Questions

Multiple choice
  1. 11

  2. 15.5

  3. 18

  4. 66/5

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Total work = LCM(24, 15, 12) = 120 units. A does 5 units/day, B does 8 units/day, C does 10 units/day. B and C together do 18 units/day for 3 days = 54 units. Remaining work = 120 - 54 = 66 units. A alone needs 66/5 = 13.2 days = 66/5 days.

Multiple choice
  1. Only A

  2. Both B and C

  3. A, B and C

  4. Only C

  5. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let Naimish's 1 day work = 1/30. Let Pramod's 1 day work = 1/Y. Naimish worked X days and Pramod completed remaining work. Payment is proportional to work done. Pramod got Rs.1080 out of Rs.1800, so Pramod did 1080/1800 = 3/5 of work. Therefore Naimish did 2/5 of work in X days. X/30 = 2/5 gives X = 12. Pramod completed 3/5 of work alone, so time taken = (3/5)Y. Total work equation: X/30 + (3/5)Y/Y = 1. With X=12: 12/30 + 3/5 = 1, which holds. This works for any Y. Testing options: A (12,36), B (12,30), C (12,25) all satisfy X=12. D (16,25) gives X=16 which doesn't satisfy X/30 = 2/5.

Multiple choice
  1. 6 days

  2. 8 days

  3. 5 days

  4. 4 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let Y's efficiency = 1 unit. X is 40% more efficient (1.4 units) and Z is 40% less efficient (0.6 units). Combined efficiency = 3 units. Total work = 3 × 21 = 63 units. Y + Z work at 1.6 units for 35 days, completing 56 units. Remaining work = 7 units. X at 1.4 units takes 7/1.4 = 5 days. Options A, B, and D are miscalculations.

Multiple choice
  1. 24 days

  2. 18 days

  3. 36 days

  4. 30 days

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let A and B's actual work rates be 'a' and 'b' jobs per day respectively. Working together: a + b = 1/(15/2) = 2/15. With increased efficiency: 2a + 3b = 1/(10/3) = 3/10. From the first equation: 2a + 2b = 4/15. Subtracting from the second: (2a + 3b) - (2a + 2b) = 3/10 - 4/15, giving b = 9/30 - 8/30 = 1/30. So B alone would take 1/(1/30) = 30 days. Option D is correct. Options A, B, and C don't satisfy the given conditions.

Multiple choice
  1. 6

  2. 12

  3. 9

  4. 8

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let one man's work per day be 'm' and one woman's work per day be 'w'. Total work = T. First phase: 4(4m + 10w) = T/3, so 4m + 10w = T/12. Second phase: 2(6m + 12w) = 2T/9, so 6m + 12w = T/9. Solving: From first eq, 12m + 30w = T/3. From second eq, 18m + 36w = T/3. Equating: 12m + 30w = 18m + 36w, so -6m = 6w, or m = -w. This seems wrong. Let me recalculate. Actually: 4 days of (4m+10w) = T/3, so (4m+10w) = T/12. And 2 days of (6m+12w) = 2T/9, so (6m+12w) = T/9. From first: 12m + 30w = T/3. From second: 18m + 36w = T/3. Subtracting: 6m - 6w = 0, so m = w. Then T = 12(4m + 10m) = 12(14m) = 168m, or T = 9(6m + 12m) = 9(18m) = 162m. Hmm, inconsistency. Let me use the second eq: T = 9(6m + 12w) = 54m + 108w. From first eq: 4m + 10w = T/12 = (54m + 108w)/12 = 4.5m + 9w. So 4m + 10w = 4.5m + 9w, giving w = 0.5m. Then T = 54m + 108(0.5m) = 54m + 54m = 108m. Work done so far = T/3 + 2T/9 = 3T/9 + 2T/9 = 5T/9. Remaining = 4T/9 = 4(108m)/9 = 48m. Current team: 6m + 12w = 6m + 12(0.5m) = 6m + 6m = 12m per day. In 3 days: 3 × 12m = 36m. Need 48m - 36m = 12m more. Adding x women: new rate = 12m + xw = 12m + 0.5xm. In 3 days: 3(12m + 0.5xm) = 36m + 1.5xm = 48m. So 1.5xm = 12m, x = 8. Option D is correct.

Multiple choice
  1. 4

  2. 9

  3. 5

  4. 3

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let there be x women and x children. Normally, total work hours = 6x + 4x = 10x. With 50% increase, total work = 15x hours. Children can work max 6 hrs/day (increase of 2x hours). So women must do 15x - 6x = 9x hours. Each woman's increase = 9x - 6x = 3x hours, which is 3 hours per woman.

Multiple choice
  1. 45

  2. 60

  3. 54

  4. 30

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Use work rates: A+B together complete 1/20 of work per day. A alone does 1/30 per day. So B's rate = 1/20 - 1/30 = 3/60 - 2/60 = 1/60 per day. Therefore B alone needs 60 days. Option A (45) and C (54) are common errors from incorrect arithmetic, while D (30) is A's time.

Multiple choice
  1. 32

  2. 40

  3. 48

  4. 36

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Aman and Pramod together: 1/16 per day. Pramod alone: 1/24 per day. Aman's rate = 1/16 - 1/24 = 3/48 - 2/48 = 1/48 per day. So Aman needs 48 days alone. Options A (32) and D (36) are arithmetic errors, while B (40) doesn't match the calculation.

Multiple choice
  1. 480

  2. 520

  3. 760

  4. 800

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

A's work rate = 1/12 per day, B's rate = 1/16 per day. In 6 days, A+B complete 6(1/12 + 1/16) = 6(7/48) = 7/8 of the work. So C does 1/8 of the work in 6 days. Payment is divided by work contribution: C's share = (1/8) × 6400 = Rs 800.

Multiple choice
  1. 10

  2. 12

  3. 15

  4. 30

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Aman is 4 times more efficient than Sangram, so Aman's efficiency: Sangram's efficiency = 4:1. This means if Sangram takes 4x days, Aman takes x days. Given: 4x - x = 45, so 3x = 45, x = 15. Aman takes 15 days, Sangram takes 60 days. Together, their combined rate = 1/15 + 1/60 = 5/60 = 1/12. Working together, they complete the work in 12 days.

Multiple choice
  1. 11

  2. 8

  3. 23

  4. 21

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let total work = LCM(24,32,48) = 96 units. P+Q = 96/24 = 4 units/day. Q+R = 96/32 = 3 units/day. R+P = 96/48 = 2 units/day. Adding: 2(P+Q+R) = 9, so P+Q+R = 4.5 units/day. Time = 96/4.5 = 21.33 days. Option D (21) is the closest approximation.

Multiple choice
  1. 11

  2. 8

  3. 16

  4. 21

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

A's work rate = 1/20 per day. B's work rate = 1/25 per day. Combined rate = 1/20 + 1/25 = 9/100 per day. In 5 days together, they complete 5 × 9/100 = 45/100 = 9/20 of the work. Remaining work = 11/20. A alone needs (11/20) ÷ (1/20) = 11 more days to finish.