Time and Work Questions

Multiple choice
  1. 20

  2. 30

  3. 18

  4. 24

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

In 4 days, A does 4/50, B does 4/75, C does 4/20 = 1/5. Total done = 4/50 + 4/75 + 4/20 = 12/150 + 8/150 + 30/150 = 50/150 = 1/3. Work remaining = 2/3. A+B's combined rate = 1/50 + 1/75 = 5/150 = 1/30. Time needed = (2/3) / (1/30) = 20 days.

Multiple choice
  1. 924

  2. 693

  3. 231

  4. 462

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

P completes work in 12 days, so rate = 1/12 per day. Q completes in 16 days, so rate = 1/16 per day. Together with R, they complete in 6 days. Combined rate = 1/6 per day. R's rate = 1/6 - 1/12 - 1/16 = (8 - 4 - 3)/48 = 1/48 per day. Earnings of Rs. 3696 are divided in ratio of their rates: (1/12) : (1/16) : (1/48) = 4 : 3 : 1. R's share = 3696 × 1/8 = 462.

Multiple choice
  1. 60

  2. 90

  3. 72

  4. 120

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let P, Q, R be work rates per day. P + Q = 1/40, Q + R = 1/36, P + Q + R = 1/24. Subtracting first from third: R = 1/24 - 1/40 = 1/60. Then Q = 1/36 - 1/60 = 1/90. So Q alone takes 90 days. Options A, C, D are common miscalculations from incorrect subtraction.

Multiple choice
  1. 20

  2. 30

  3. 18

  4. 24

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

X, Y, Z complete work in 50, 75, 20 days respectively. Their combined rate = 1/50 + 1/75 + 1/20 = 3/150 + 2/150 + 7.5/150 = 12.5/150 per day. In 4 days, they complete 50/150 = 1/3 of work. Remaining work = 2/3. X + Y rate = 1/50 + 1/75 = 5/150 per day. Time for remaining work = (2/3) / (5/150) = 100/5 = 20 days. Options B, C, D are calculation errors.

Multiple choice
  1. 24

  2. 9

  3. 21

  4. 18

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

A does 25% (1/4) work in 8 days, so A's rate = 1/32 per day. B does 1/8 work in 12 days, so B's rate = 1/96 per day. Combined rate = 1/32 + 1/96 = 4/96 = 1/24 per day. For full work: 24 days. For 75% (3/4) of work: 3/4 × 24 = 18 days. Options A, B, C are incorrect conversions between percentages and fractions.

Multiple choice
  1. 102

  2. 81

  3. 87

  4. 75

  5. None of these इनमे से कोई नही

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Total efficiency = 7+5+8 = 20 units/day. Total work = 20×42 = 840 units. B+C efficiency = 13 units/day. In 21 days, B+C complete 21×13 = 273 units. Remaining = 840-273 = 567 units. A does 567/7 = 81 days alone. Total time = 21 + 81 = 102 days.

Multiple choice
  1. 10 days

  2. 16 days

  3. 24 days

  4. 12 days

  5. None of these इनमें से कोई नहीं

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A's rate = 1/12. A+B+C rate = 1/6. B's efficiency = 0.5 × A, so B's rate = 0.5/12 = 1/24. C's rate = (1/6) - (1/12 + 1/24) = (4/24 - 2/24 - 1/24) = 1/24. So C alone takes 24 days. Option C is correct.

Multiple choice
  1. 18

  2. 16

  3. 20

  4. 16.5

  5. 24

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Men: 36 men × 24 days × 8 hours = 6912 man-hours. One man-hour = Work/6912. Women: 48 women × 20 days × 10 hours = 9600 man-hours. One woman-hour = Work/9600. Combined work in one 12-hour day: (14 men × 12 × Work/6912) + (25 women × 12 × Work/9600) = (168/6912 + 300/9600) × Work = (0.0243 + 0.03125) × Work = 0.05556 × Work. Days needed = Work/(0.05556 × Work) = 18 days.

Multiple choice
  1. 135 days 135 दिन

  2. 142 days 142 दिन

  3. 126 days 126 दिन

  4. 110 days 110 दिन

  5. None of these इनमे से कोई नहीं

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let one male's one day work = m and one female's one day work = f. From first condition: 8m + 6f = 1/5. From second condition: 5m + 6f = 1/7. Subtract second equation from first: 3m = 1/5 - 1/7 = 2/35, so m = 2/105. Substitute in second equation: 5(2/105) + 6f = 1/7, so 10/105 + 6f = 1/7, giving 6f = 15/105 - 10/105 = 5/105 = 1/21. Therefore f = 1/126. One female alone will take 126 days to complete the work.

Multiple choice
  1. Only 1

  2. Only 2

  3. Both 1 and 2

  4. Neither 1 or 2

  5. None of these

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Neither statement provides information about men's work rate or any conversion between men, women, and children. Without knowing how men's work compares to women or children, or any relationship between these groups, we cannot determine how long 14 men would take.

Multiple choice
  1. Only 1

  2. Only 2

  3. Both 1 and 2

  4. either 1 or 2

  5. Neither 1 or 2

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Statement 1 alone is insufficient because we don't know how many women are working with the 6 men. Statement 2 alone is sufficient: if 8 men complete the work in 16 days, then 6 men will take (8×16)÷6 = 64/3 days using the inverse proportion between workers and time.

Multiple choice
  1. 40 days

  2. 48 days

  3. 36 days

  4. 72 days

  5. None of these इनमें से कोई नहीं

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let efficiencies be 3x, 4x, 5x. Combined efficiency = 12x. Combined work = 12x × 20 = 240x. C is fastest (5x), so C alone needs 240x ÷ 5x = 48 days. The 'faster person' refers to the most efficient worker, C.

Multiple choice
  1. 120

  2. 72

  3. 150

  4. 140

  5. None of these इनमे से कोई नही

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

A's rate: (1/4 work) in 6 days, so full work in 24 days. Rate = 1/24 per day. B's rate: (1/6 work) in 8 days, so full work in 48 days. Rate = 1/48 per day. Combined rate = 1/24 + 1/48 = 3/48 = 1/16 per day. They finish in 16 days. A's contribution = 16 days × (1/24) = 16/24 = 2/3 of work. A's share = (2/3) × 360 = Rs 240. Since 240 is not among options A-D, 'None of these' (E) is correct.