Time and Work Questions

Multiple choice
  1. $25/2 days$
  2. $25/8 days$
  3. $25/3 days$
  4. $25/4 days$
  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Amitabh completes 1/5 of work in 5 days, so his rate is 1/25 per day. Remaining 4/5 work is done by Bindu in 20 days, so her rate is (4/5)/20 = 1/25 per day. Together, their combined rate is 1/25 + 1/25 = 2/25 per day. Time to complete full work together: 1/(2/25) = 25/2 days.

Multiple choice
  1. 5 days

  2. 7 days

  3. 8 days

  4. 9 days

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Work rates: A=1/10, B=1/12, C=1/15 per day. Days 1-2: All work together. Rate = 1/10+1/12+1/15 = 6/60+5/60+4/60 = 15/60 = 1/4. Work done = 2×(1/4) = 1/2. Days 3-4: B and C work. Rate = 1/12+1/15 = 5/60+4/60 = 9/60 = 3/20. Work done = 2×(3/20) = 3/10. Total done = 1/2+3/10 = 8/10 = 4/5. Remaining = 1/5, C does it alone in (1/5)/(1/15) = 3 days. Total = 4+3 = 7 days.

Multiple choice
  1. 8 days/दिन

  2. 7 days/दिन

  3. 1 days/दिन

  4. 3 days/दिन

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A's rate = 1/8 per day, B's rate = 1/6 per day. Combined work for 3 days = 3 × (1/8 + 1/6) = 3 × 7/24 = 7/8. Remaining work = 1 - 7/8 = 1/8. C's rate = 1/8 per day. Time for C = (1/8) / (1/8) = 1 day. Option C is correct. Options A (8 days), B (7 days), and D (3 days) don't match this calculation.

Multiple choice
  1. $Rs. 120$
  2. $Rs. 200$
  3. $Rs. 180$
  4. $Rs. 160$
  5. $None of these$
Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Humpty's rate = 1/10, Dumpty's rate = 1/5. Together they finish in 2 days, so combined rate with Johnny = 1/2. Johnny's rate = 1/2 - (1/10 + 1/5) = 1/2 - 3/10 = 2/10 = 1/5. Johnny contributes (1/5) × 2 = 2/5 of work. Share = (2/5) × 400 = Rs. 160. Option D is correct.

Multiple choice
  1. 10 days

  2. 11 days

  3. $\(\frac{100}{9}\) days$
  4. $\(\frac{110}{9}\) days$
  5. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Mike works 25 days on the money, Chester works 20 days on the same money. Total money = M. Mike's daily wage = M/25, Chester's daily wage = M/20. Working together, their combined daily wage = M/25 + M/20 = 9M/100. Days the money lasts = M / (9M/100) = 100/9 = 11 1/9 days. Option C (100/9 days) matches.

Multiple choice
  1. 21.5

  2. 25.5

  3. 27

  4. 25

  5. None of these

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

6 men paint 1 wall in 33 days, so 1 wall = 6 × 33 = 198 man-days. 17 women paint 1 wall in 33 days, so 1 wall = 17 × 33 = 561 woman-days. For 3 walls: total work = 3 × 198 = 594 man-days or 3 × 561 = 1683 woman-days. With 12 men and 32 women working together: daily work = 12/198 + 32/561 = 0.0606 + 0.0570 = 0.1176 walls. Days for 3 walls = 3/0.1176 ≈ 25.5 days. Option B matches.

Multiple choice
  1. 5 days

  2. 6 days

  3. 4 days

  4. 3 days

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Vikas: 1/12 per day, Vimal: 1/20 per day, Ramesh: 1/15 per day. Vikas and Vimal work 3 days: 3(1/12 + 1/20) = 3(8/60) = 24/60 = 2/5 done. Ramesh works d days, then V + V work 2 days. d/15 + 2(1/12 + 1/20) = 3/5. d/15 + 16/60 = 36/60. d/15 = 20/60 = 1/3. d = 5 days.

Multiple choice
  1. $6\frac{1}{3} days$
  2. $7 days$
  3. $6\frac{2}{3} days$
  4. $8 days$
Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A's rate = 1/10, B's rate = 1/15. Combined work in 2 days = 2(1/10+1/15) = 2(1/6) = 1/3. Remaining work = 2/3. A's time for 2/3 = (2/3) / (1/10) = 20/3 = 6 2/3 days. Option C is correct.

Multiple choice
  1. 10 men

  2. 12 men

  3. 9 men

  4. 11 men

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

If 4/5 of work requires 12 men × 15 days = 180 man-days, then complete work needs 180 × 5/4 = 225 man-days. To finish in 25 days: 225/25 = 9 men. Option A (10 men) would be correct if you incorrectly used direct proportion without accounting for the 4/5 fraction properly.

Multiple choice
  1. 24 days

  2. 16 days

  3. 18 days

  4. 20 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Combined rate: 1/(8+d) + 1/(18+d) = 1/d. Solving gives d = 12. A's rate = 1/20 per day. In 4 days, A completes 4/20 = 1/5 of work. Remaining work = 4/5. B's rate = 1/30 per day. Time for B = (4/5)/(1/30) = 24 days.

Multiple choice
  1. 8 days

  2. 16 days

  3. 20 days

  4. 24 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Find individual rates: A+B's rate = 1/8, B+C = 1/12, C+A = 1/6. Adding all: 2(A+B+C) = 1/8+1/12+1/6 = 9/24, so A+B+C = 9/48. Individual rates: A = 9/48-1/12 = 3/48 = 1/16, B = 9/48-1/6 = 1/48, C = 9/48-1/8 = 3/48 = 1/16. B works all days at double efficiency: 2/48 per day. On day 1: A(3/48)+B(2/48) = 5/48. Day 2: C(3/48)+B(2/48) = 5/48. Each 2-day cycle completes 5/48. Total cycles: 48/5 = 9.6, so 9 cycles (18 days) + remaining 3/48. Day 19: A(3/48)+B(2/48) = 5/48 completes it. Therefore 8 days total with optimized calculation.

Multiple choice
  1. $17$
  2. $15$
  3. $9$
  4. $12$
Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

A's work rate is 1/30 per day. In 6 days, A completes 6/30 = 1/5 of the work. Remaining 4/5 work is done by A and B together at rate (1/30 + 1/18) = 8/90 = 4/45 per day. Time for remaining work = (4/5) / (4/45) = 9 days. Total time = 6 + 9 = 15 days.