A and B can complete a piece of work in 8 days, B and C can do it in 12 days, C and A can do it in 6 days. If B works for all the days. A starts the work and then next day the work is done by C and this process continues then in how many days the work will be completed if B does the work with double efficiency?
Reveal answer
Fill a bubble to check yourself