Time and Work Questions

Multiple choice
  1. 12 days

  2. 6 days

  3. 3 days

  4. 24 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Pannalal does 1/3 of the job in 20 days, so he does the whole job in 60 days. Saiprasad does the remaining 2/3 of the job in 10 days, so he does the whole job in 15 days. Their combined rate is 1/60 + 1/15 = 5/60 = 1/12, meaning they finish in 12 days.

Multiple choice
  1. 2 days

  2. 3 days

  3. 4 days

  4. 5 days

  5. 6 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Milli takes 12 days, so her rate is 1/12 work/day. Jason is twice as fast, so his rate is 2/12 = 1/6 work/day. Together, their rate is 1/12 + 1/6 = 3/12 = 1/4 work/day. They finish in 4 days.

Multiple choice
  1. 40 days

  2. 30 days

  3. 16 days

  4. 24 days

  5. 20 days

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let the daily work rates of R, A, and S be r, a, and s respectively. Since R takes twice as long as A and S together, we have r = (a + s)/2, which means the total rate r + a + s = 3r = 1/10, so r = 1/30. Similarly, since A takes thrice as long as S and R together, we have a = (s + r)/3, which means r + a + s = 4a = 1/10, so a = 1/40. Solving for s gives s = 1/10 - 1/30 - 1/40 = 1/24, meaning S alone takes 24 days.

Multiple choice
  1. 160 days

  2. 150 days

  3. 130 days

  4. 175 days

  5. Na

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

1 man = 1/80 work/day. 12 men = 12/80 = 3/20 work/day. Total work = 1/4 per day. 16 women = 1/4 - 3/20 = 5/20 - 3/20 = 2/20 = 1/10 per day. 1 woman = 1/(16 * 10) = 1/160 work/day. So, 160 days.

Multiple choice
  1. 15 days

  2. 12 days

  3. 10 days

  4. 9 days

  5. None of the above

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

P's rate = 1/30, Q's rate = 1/18. P works for 6 days alone: 6/30 = 1/5 work done. Remaining = 4/5. Combined rate = 1/30 + 1/18 = (3+5)/90 = 8/90 = 4/45. Time for remaining = (4/5) / (4/45) = 9 days. Total time = 6 + 9 = 15 days.

Multiple choice
  1. 32.5 days

  2. 35 days

  3. 37.5 days

  4. 42 days

  5. None of the above

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A, B, and C together complete 1/15 of the work per day. In 6 days, they complete 6/15 = 2/5 of the work, leaving 3/5 to be finished by B and C in 15 days, meaning B and C complete 1/25 of the work per day. Subtracting (B+C)'s rate from (A+B+C)'s rate gives A's rate: 1/15 - 1/25 = (5-3)/75 = 2/75. Thus, A takes 75/2 = 37.5 days to finish the work alone.

Multiple choice
  1. Rs. 2000

  2. Rs. 6000

  3. Rs. 4000

  4. Rs. 3000

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Work rates: Mayank = 1/5, Deepak = 1/10, Pawan = 1/15. Ratio of work done = 1/5 : 1/10 : 1/15 = 6 : 3 : 2. Total parts = 6+3+2 = 11. Deepak's share = (3/11) * 11000 = 3000.

Multiple choice
  1. 18

  2. 12

  3. 10

  4. 9

  5. 7

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

A+B=1/15, B+C=1/12, C+A=1/10. 2(A+B+C) = 1/15 + 1/12 + 1/10 = (4+5+6)/60 = 15/60 = 1/4. A+B+C = 1/8. After 5 days, work done = 5/8. Remaining = 3/8. A's efficiency = (A+B+C) - (B+C) = 1/8 - 1/12 = (3-2)/24 = 1/24. Time for A = (3/8) / (1/24) = 9 days.