Time and Work Questions

Multiple choice
  1. Both statements A and C

  2. Only statement B

  3. Either statement A or C

  4. Both statements A and B

  5. Any one of them

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

A: John = 1/12. B: John + Mary = 1/4. C: Mary + Ben = 1/5. From A and B, Mary = 1/4 - 1/12 = 2/12 = 1/6. From C, Ben = 1/5 - 1/6 = 1/30. Total rate = 1/12 + 1/6 + 1/30 = (5+10+2)/60 = 17/60. Time = 60/17 days. A and C are sufficient.

Multiple choice
  1. 9

  2. 6

  3. 8

  4. 7

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let M, W, B be the work done by a man, woman, and boy in one day. Given W=3M and B=0.5M, the group (3M+4W+6B) = (3M + 12M + 3M) = 18M. Total work = 18M * 6 days = 108M. To complete 108M in 4 days, the daily work needed is 27M. Since one woman does 3M, the number of women needed is 27M / 3M = 9.

Multiple choice
  1. 40

  2. 20

  3. 35

  4. 50

  5. 60

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let S be the work of a supervisor and W be the work of a worker per day. From the problem, 8(4S + 6W) = 10(3S + 7W), which simplifies to 32S + 48W = 30S + 70W, or 2S = 22W, meaning S = 11W. Substituting back, the total work is 8(4(11W) + 6W) = 8(50W) = 400W. If 10 workers do the job, they take 400W / 10W = 40 days.

Multiple choice
  1. 10

  2. 11

  3. 12

  4. 15

  5. 18

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Ron and Sam do 1/8 of the work per day. In 3 days, they do 3/8 of the work. Remaining work = 5/8. Sam does 5/8 of the work in 15 days, so Sam's rate is (5/8)/15 = 1/24 per day. Ron's rate = (1/8) - (1/24) = 3/24 - 1/24 = 2/24 = 1/12. Ron takes 12 days to finish the work alone.

Multiple choice
  1. 3

  2. 2

  3. 4

  4. 5

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Work = 8 * 6 = 48 female-hours. Male work = 4 * 6 = 24 male-hours. Assuming 1 male = 1 female, 48 units / 24 units = 2. The male finishes in 24 hours, so 48/24 = 2 females are needed.

Multiple choice
  1. 2 2 5 days

  2. 3 1 5 days

  3. 3 2 5 days

  4. 4 5 days

  5. None of these

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

C takes 28 days, so C's efficiency is 1/28 of the work per day. B's efficiency is twice C's, so 2/28 = 1/14. A's efficiency equals B's, so 1/14. Total work is 1. After 4 days, C and B have done 4 * (1/28 + 1/14) = 4 * (3/28) = 3/7. Remaining work is 4/7. A, B, and C together do 1/14 + 1/14 + 1/28 = 5/28 per day. Time taken = (4/7) / (5/28) = (4/7) * (28/5) = 16/5 = 3.2 days.

Multiple choice
  1. 12 days

  2. 20 days

  3. 10 days

  4. 4 days

  5. 8 days

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let Sachin take S days. Piyush takes 5S days. Kadil is 6 times as efficient as Piyush, so Kadil takes (5S)/6 days. Together: 1/S + 1/(5S) + 6/(5S) = 1/2. (5+1+6)/(5S) = 1/2. 12/(5S) = 1/2. 5S = 24, S = 4.8. Piyush = 5 * 4.8 = 24 days. Kadil = 24/6 = 4 days. Difference = 24 - 4 = 20 days.

Multiple choice
  1. 8

  2. 16

  3. 32

  4. 10

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Total work = 16 * 12 = 192 man-days. Work done in 4 days = 16 * 4 = 64 man-days. Remaining work = 192 - 64 = 128 man-days. Remaining time = 4 days. Men needed = 128 / 4 = 32. Original men = 16. New men joined = 32 - 16 = 16.

Multiple choice
  1. 15

  2. 19

  3. 12

  4. 21

  5. None of these

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let x be the original number of men. The total work is 15x. With (x-6) men, the work takes 21 days, so 21(x-6) = 15x. Solving this: 21x - 126 = 15x, which gives 6x = 126, so x = 21.