Time and Work Questions

Multiple choice
  1. 15 days

  2. 45 days

  3. 30 days

  4. 10 days

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Peeyush does 1/3 of the job in 30 days, so he does the whole job in 90 days. Sanjiv does the remaining 2/3 of the job in 60 days, so he does the whole job in 90 days. Together, their rate is 1/90 + 1/90 = 2/90 = 1/45, meaning they take 45 days.

Multiple choice
  1. 5 17 18

  2. 5 13 18

  3. 5 3 5

  4. 4 17 18

Reveal answer Fill a bubble to check yourself
A Correct answer
Multiple choice
  1. 10/3 days

  2. 4 days

  3. 5 days

  4. Cannot be determined

  5. 10 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Total work is c*e = f*g. The condition (e-4)(c+5) = ce and (g-4)(f+5) = fg leads to equations that allow solving for the work rate. Given the constraints, the combined rate calculation results in 10/3 days.

Multiple choice
  1. 30 days

  2. 45 days

  3. 15 days

  4. 60 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Praful does 1/2 of the job in 30 days, so he takes 60 days to complete the whole job. Sarabjit completes the remaining 1/2 in 10 days, so he takes 20 days to complete the whole job. Their combined daily rate is 1/60 + 1/20 = 1/60 + 3/60 = 4/60 = 1/15, meaning they take 15 days together.

Multiple choice
  1. 13 days

  2. 24 days

  3. 26 days

  4. 12 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let Bansi take x days. Akhilesh takes x - 39 days. Efficiency ratio A:B = 2:1, so time ratio A:B = 1:2. Thus, x = 2(x - 39) => x = 2x - 78 => x = 78. Akhilesh takes 39 days, Bansi takes 78 days. Together: (39 * 78) / (39 + 78) = 3042 / 117 = 26 days.