Time and Work Questions

Multiple choice
  1. 4

  2. 8

  3. 6

  4. 10

Reveal answer Fill a bubble to check yourself
B Correct answer
Multiple choice
  1. 20 days

  2. 30 days

  3. 40 days

  4. 60 days

  5. 80 days

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Total work = 20 * 30 * 4 = 2400 man-hours. Work done = 30 * 20 * 3 = 1800 man-hours. Remaining work = 600 man-hours. One man working 10 hours a day takes 600 / 10 = 60 days.

Multiple choice
  1. 125

  2. 120

  3. 100

  4. 80

  5. Cannot be determined

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let M, E, H, D be men, efficiency, hours, and days. Work = M*E*H*D. New work = (1.25M)(1.25E)(1.25H)(D-61). Since work is constant: M*E*H*D = 1.25^3 * M*E*H(D-61). D = 1.953125 * (D-61). D = 1.953125D - 119.14. 0.953125D = 119.14, D = 125.

Multiple choice
  1. 6 hours

  2. 8 hours

  3. 10 hours

  4. 12 hours

  5. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Initial work is 20 men * 50 days * 5 hours = 5000 man-hours. After 15 days, 20 * 15 * 5 = 1500 man-hours are done, leaving 3500 man-hours. With 10 men remaining, they must work 3500 / (10 * 35 days) = 10 hours per day.

Multiple choice
  1. 9 1 11 days

  2. 9 8 9 days

  3. 10 2 11 days

  4. 12 days

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let the efficiency of A be 6 units/day, which means B's efficiency is 3 units/day and C's efficiency is 2 units/day. Since B and C together (5 units/day) take 20 days to complete the work, the total work is 5 * 20 = 100 units. Working together, all three have a combined efficiency of 6 + 3 + 2 = 11 units/day, so they will complete the work in 100/11 = 9 1/11 days.

Multiple choice
  1. 4 days

  2. 5 days

  3. 6 days

  4. 8 days

  5. 9 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Total work = 60 units (LCM of 10, 15, 20). A's rate = 6/day, B's rate = 4/day, C's rate = 3/day. A+B work 6 days at 6 hours/day (equivalent to 36 hours). Work done = (6+4) * (36/8) = 45 units. Remaining work = 15 units. C works 10 hours/day, rate = 3 * (10/8) = 3.75 units/day. Days for C = 15 / 3.75 = 4.