Time and Work Questions

Multiple choice
  1. 4 days

  2. 3 days

  3. 2 days

  4. 1 day

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

A child finishes in 20 days, so 1 child's rate is 1/20. 5 children take 4 days, so 4 men take 8 days (double time), meaning 1 man's rate is 1/32. Since 1 man is twice as fast as a woman, 1 woman's rate is 1/64. Total rate for 12 men, 10 children, 8 women = 12/32 + 10/20 + 8/64 = 3/8 + 1/2 + 1/8 = 1. The job takes 1/1 = 1 day.

Multiple choice
  1. 3

  2. 4

  3. 6

  4. 8

  5. 10

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

A+B = 1/6, B+C = 1/12, A+C = 1/3. Summing these: 2(A+B+C) = 1/6 + 1/12 + 4/12 = 7/12. A+B+C = 7/24. C = (A+B+C) - (A+B) = 7/24 - 4/24 = 3/24 = 1/8. So C takes 8 days.

Multiple choice
  1. 7 : 13

  2. 13 : 7

  3. 7 : 12

  4. 12 : 7

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

1/A + 1/B = 1/40, 1/B + 1/C = 1/50, 1/A + 1/C = 1/60. Adding these: 2(1/A + 1/B + 1/C) = 1/40 + 1/50 + 1/60 = (15+12+10)/600 = 37/600. So 1/A + 1/B + 1/C = 37/1200. 1/C = 37/1200 - 1/40 = 7/1200. 1/A = 37/1200 - 1/50 = 13/1200. Ratio A:C = 1200/13 : 1200/7 = 7:13.

Multiple choice
  1. 26 days

  2. 24 days

  3. 23 days

  4. 22 days.

  5. 20 days

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Vibhu does 1/24 per day, Kashish does 1/48 per day. Together they do 3/48 = 1/16 per day. Let total days be x. Kashish works for x days, Vibhu works for x-12 days. (x-12)/24 + x/48 = 1. Multiply by 48: 2(x-12) + x = 48. 2x - 24 + x = 48. 3x = 72. x = 24.

Multiple choice
  1. 88 days

  2. 90 days

  3. 96 days

  4. 98 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A+B = 1/80, B+C = 1/120. Let B's rate be b. A = 1/80 - b, C = 1/120 - b. Day 1: A+B = 1/80. Day 2: B+C = 1/120. Day 3: A+B = 1/80. Day 4: B+C = 1/120. In 2 days, work done = 1/80 + 1/120 = 5/240 = 1/48. Total work = 1. Days = 1 / (1/96) = 96 days.

Multiple choice
  1. 4 days

  2. 3 days

  3. 2 days

  4. 1 day

  5. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A's rate = 1/14, B's rate = 1/21. Together = 1/14 + 1/21 = 3/42 + 2/42 = 5/42. In 7 days, they do 7 * 5/42 = 5/6 of the work. Remaining = 1/6. C's rate = 1/2 * A's rate = 1/28. B+C rate = 1/21 + 1/28 = 4/84 + 3/84 = 7/84 = 1/12. Time to finish 1/6 work = (1/6) / (1/12) = 2 days.

Multiple choice
  1. 12 days

  2. 40 days

  3. 6 days

  4. 9 days

  5. 16 days

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let B be the work of a boy per day and G be the work of a girl per day. 8B + 12G = 1/8 and 6B + 14G = 1/10. Solving this system: multiply first by 3 and second by 4: 24B + 36G = 3/8 and 24B + 56G = 4/10. Subtracting gives 20G = 4/10 - 3/8 = 16/40 - 15/40 = 1/40. Thus, 20 girls complete the work in 40 days.

Multiple choice
  1. 20

  2. 17

  3. 19

  4. 14

  5. None of these

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

In the first 11 days, 21 members completed 1/6 of the work. To find the total number of members (M) needed to complete the remaining 5/6 of the work in the remaining 33 days, we use the work formula: (21 * 11) / (1/6) = (M * 33) / (5/6). Solving this gives M = 35 members, which means 35 - 21 = 14 extra members are required.