Quantitative Aptitude
Time and Work
2,195 Questions
Time and Work Questions
C
Correct answer
Explanation
Total work = 4 men * 7 hours * 8 days = 224 man-hours. New setup: x men * 8 hours * 4 days = 32x. 32x = 224, so x = 7.
-
4 days
-
3 days
-
2 days
-
1 day
D
Correct answer
Explanation
A child finishes in 20 days, so 1 child's rate is 1/20. 5 children take 4 days, so 4 men take 8 days (double time), meaning 1 man's rate is 1/32. Since 1 man is twice as fast as a woman, 1 woman's rate is 1/64. Total rate for 12 men, 10 children, 8 women = 12/32 + 10/20 + 8/64 = 3/8 + 1/2 + 1/8 = 1. The job takes 1/1 = 1 day.
-
32
-
34
-
36
-
40
-
None of these
A
Correct answer
Explanation
Let original men be M. Work = M * 20. New men = M - 12. Work = (M - 12) * 32. 20M = 32M - 384. 12M = 384. M = 32.
-
45 days
-
22 days
-
37 days
-
30 days
-
43 days
A
Correct answer
Explanation
Niranjan = 2 * Bhola. Together, they do 3 units of work per day. 15 days * 3 units/day = 45 units total. Bhola does 1 unit/day. Time for Bhola = 45 / 1 = 45 days.
B
Correct answer
Explanation
Let x be the number of persons. Work = 10x. With x+8 persons, time is 8 days. Work = 8(x+8). 10x = 8x + 64, so 2x = 64, x = 32.
-
12 days
-
15 days
-
17 days
-
18 days
-
20 days
B
Correct answer
Explanation
Bikesh takes 24 days. Atul is 60% more efficient, meaning his efficiency is 1.6 times Bikesh's. Time taken by Atul = 24 / 1.6 = 15 days.
D
Correct answer
Explanation
A+B = 1/6, B+C = 1/12, A+C = 1/3. Summing these: 2(A+B+C) = 1/6 + 1/12 + 4/12 = 7/12. A+B+C = 7/24. C = (A+B+C) - (A+B) = 7/24 - 4/24 = 3/24 = 1/8. So C takes 8 days.
-
7 : 13
-
13 : 7
-
7 : 12
-
12 : 7
-
None of these
A
Correct answer
Explanation
1/A + 1/B = 1/40, 1/B + 1/C = 1/50, 1/A + 1/C = 1/60. Adding these: 2(1/A + 1/B + 1/C) = 1/40 + 1/50 + 1/60 = (15+12+10)/600 = 37/600. So 1/A + 1/B + 1/C = 37/1200. 1/C = 37/1200 - 1/40 = 7/1200. 1/A = 37/1200 - 1/50 = 13/1200. Ratio A:C = 1200/13 : 1200/7 = 7:13.
-
26 days
-
24 days
-
23 days
-
22 days.
-
20 days
B
Correct answer
Explanation
Vibhu does 1/24 per day, Kashish does 1/48 per day. Together they do 3/48 = 1/16 per day. Let total days be x. Kashish works for x days, Vibhu works for x-12 days. (x-12)/24 + x/48 = 1. Multiply by 48: 2(x-12) + x = 48. 2x - 24 + x = 48. 3x = 72. x = 24.
-
88 days
-
90 days
-
96 days
-
98 days
C
Correct answer
Explanation
A+B = 1/80, B+C = 1/120. Let B's rate be b. A = 1/80 - b, C = 1/120 - b. Day 1: A+B = 1/80. Day 2: B+C = 1/120. Day 3: A+B = 1/80. Day 4: B+C = 1/120. In 2 days, work done = 1/80 + 1/120 = 5/240 = 1/48. Total work = 1. Days = 1 / (1/96) = 96 days.
-
4 days
-
3 days
-
2 days
-
1 day
-
None of these
C
Correct answer
Explanation
A's rate = 1/14, B's rate = 1/21. Together = 1/14 + 1/21 = 3/42 + 2/42 = 5/42. In 7 days, they do 7 * 5/42 = 5/6 of the work. Remaining = 1/6. C's rate = 1/2 * A's rate = 1/28. B+C rate = 1/21 + 1/28 = 4/84 + 3/84 = 7/84 = 1/12. Time to finish 1/6 work = (1/6) / (1/12) = 2 days.
-
12 days
-
40 days
-
6 days
-
9 days
-
16 days
B
Correct answer
Explanation
Let B be the work of a boy per day and G be the work of a girl per day. 8B + 12G = 1/8 and 6B + 14G = 1/10. Solving this system: multiply first by 3 and second by 4: 24B + 36G = 3/8 and 24B + 56G = 4/10. Subtracting gives 20G = 4/10 - 3/8 = 16/40 - 15/40 = 1/40. Thus, 20 girls complete the work in 40 days.
-
20
-
17
-
19
-
14
-
None of these
D
Correct answer
Explanation
In the first 11 days, 21 members completed 1/6 of the work. To find the total number of members (M) needed to complete the remaining 5/6 of the work in the remaining 33 days, we use the work formula: (21 * 11) / (1/6) = (M * 33) / (5/6). Solving this gives M = 35 members, which means 35 - 21 = 14 extra members are required.
-
8 days
-
4 days
-
12 days
-
24 days
-
5 days
A
Correct answer
Explanation
P's efficiency is 1 unit/day. Q is 50% more efficient, so Q's efficiency is 1.5 units/day. The total work is 12 days * 1 unit/day = 12 units. Time for Q = 12 units / 1.5 units/day = 8 days.