Time and Work Questions

Multiple choice
  1. 1/10

  2. 1/5

  3. 1/6

  4. 2/15

  5. 1/8

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

P's rate = 1/10, Q's = 1/12, R's = 1/15. Combined rate = (6+5+4)/60 = 15/60 = 1/4. Work in 2 days = 2 * 1/4 = 1/2. P+Q rate = 1/10 + 1/12 = 11/60. Work in 2 days = 2 * 11/60 = 11/30. Total work done = 1/2 + 11/30 = 15/30 + 11/30 = 26/30 = 13/15. Remaining = 1 - 13/15 = 2/15.

Multiple choice
  1. 6 days

  2. 8 days

  3. 12 days

  4. 9 days

  5. 11 days

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let total days be x. P worked 3 days (3/12 work). Q worked (x-3) days. R worked x days. Equation: 3/12 + (x-3)/16 + x/24 = 1. Multiplying by 48: 12 + 3(x-3) + 2x = 48, so 12 + 3x - 9 + 2x = 48, 5x = 45, x = 9.

Multiple choice
  1. 20

  2. 24

  3. 30

  4. 45

  5. 50

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

A and B work for 10 days: 10 * (1/20 + 1/30) = 10 * (5/60) = 5/6. Remaining work = 1/6. B and C finish this in 1 day more than estimated. Estimated time for A+B = 1 / (1/20 + 1/30) = 12 days. They worked 10, so 2 days left. C and B finish in 2+1 = 3 days. 3 * (1/30 + 1/C) = 1/6. 1/30 + 1/C = 1/18. 1/C = 1/18 - 1/30 = (5-3)/90 = 2/90 = 1/45. C = 45 days.

Multiple choice
  1. 6 8 13 days

  2. 8 4 13 days

  3. 9 days

  4. 9 3 13 days

  5. None of these

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

If B takes t days, A takes t/1.6 days. Their time difference is 9, so t/1.6 = 15 and t = 24. Their combined rate is 1/15 + 1/24 = 13/120, so the joint time is 120/13 = 9 3/13 days.

Multiple choice
  1. 20

  2. 30

  3. 40

  4. 60

  5. 45

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Total work = 20 * 30 * 4 = 2400 man-hours. Work done = 30 * 20 * 3 = 1800 man-hours. Remaining work = 600 man-hours. One man working 10 hours a day takes 600 / 10 = 60 days.

Multiple choice
  1. 4

  2. 6

  3. 8

  4. 10

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

16 women * 12 days = 192 woman-days. 12 men * 8 days = 96 man-days. 1 man = 2 women. 16 men start, after 3 days they do 16*3=48 man-units. Remaining = 96-48=48 man-units = 96 woman-units. New group: 6 men + 4 women = 12+4=16 women. 96/16 = 6 days.