Quantitative Aptitude
Time and Work
2,195 Questions
Time and Work Questions
-
12 days
-
15 days
-
16 days
-
18 days
-
20 days
C
Correct answer
Explanation
A does the work in 24 days, so A's rate is 1/24 per day. The work is finished in 24 - 6 = 18 days. In 18 days, A does 18/24 = 3/4 of the work. B must have done the remaining 1/4 of the work in the first 4 days. B's rate is (1/4) / 4 = 1/16, so B takes 16 days.
B
Correct answer
Explanation
A's work rate is 1/20, B's is 1/30. Let C's rate be 1/x. Total work = 1. The ratio of their shares is proportional to their work rates. Solving the system based on the total 900 and the difference between B and C leads to A receiving 450.
B
Correct answer
Explanation
Total work = sum of 1+2+3+...+25 = (25 * 26) / 2 = 325 person-days. If 25 people work regularly, time = 325 / 25 = 13 days.
-
Rs. 480
-
Rs. 240
-
Rs. 320
-
Rs. 400
-
10 days
-
24 days
-
25 days
-
Cannot be determined
D
Correct answer
Explanation
Let A, B, C be the work rates. A + B = 1/20 and B + C = 1/30. We want A + C. Subtracting the equations gives A - C = 1/20 - 1/30 = 1/60. We cannot determine A + C without knowing the individual rates or another relation.
-
10 days
-
11 days
-
12 days
-
15 days
-
18 days
C
Correct answer
Explanation
Together rate = 1/8. In 3 days, they do 3/8 of work. Remaining = 5/8. Smith does 5/8 in 15 days, so Smith's rate = (5/8)/15 = 1/24. Bob's rate = 1/8 - 1/24 = 3/24 - 1/24 = 2/24 = 1/12. Bob takes 12 days.
-
36 days
-
18 days
-
12 days
-
10 days
B
Correct answer
Explanation
Let B be the work done by a boy per day and G be the work done by a girl per day. We have 2B + 5G = 1/3 and 6B + 6G = 1/2. Multiplying the first equation by 3 gives 6B + 15G = 1. Subtracting the second equation (6B + 6G = 1/2) from this gives 9G = 1/2, so G = 1/18. One girl takes 18 days.
D
Correct answer
Explanation
Work = Men * Days * Hours. 1 man = 2 boys. 12 men + 18 boys = 24 boys + 18 boys = 42 boys. Work1 = 42 * 60 * 7.5 = 18900 boy-hours. Work2 = 2 * Work1 = 37800 boy-hours. 21 men + x boys = 42 boys + x boys = (42+x) boys. Work2 = (42+x) * 50 * 9 = 37800. 42+x = 37800 / 450 = 84. x = 42.
C
Correct answer
Explanation
Let B's efficiency be 1 unit/day, then A's is 2 units/day. Combined efficiency = 3 units/day. Total work = 12 * 3 = 36 units. B alone takes 36 / 1 = 36 days.
-
20
-
15
-
12
-
10
-
None of these
D
Correct answer
Explanation
30 men = 10 days, so 1 man = 300 man-days. 12 women = 10 days, so 1 woman = 120 woman-days. 15 men = 15/300 = 1/20 of work per day. 6 women = 6/120 = 1/20 of work per day. Combined rate = 1/20 + 1/20 = 2/20 = 1/10. Time = 10 days.
-
15 days
-
18 days
-
20 days
-
24 days
-
28 days
C
Correct answer
Explanation
Total work = 25 * 14 = 350 units. Days 1-5: 25 * 5 = 125. Days 6-10: 20 * 5 = 100. Days 11-15: 15 * 5 = 75. Days 16-20: 10 * 5 = 50. Total = 125+100+75+50 = 350. The work is finished in 20 days.
D
Correct answer
Explanation
Let x be the days worked at normal efficiency. Total work = 10 * 40 = 400 man-days. After x days, 10x work is done. Remaining work = 400 - 10x. Efficiency increases by 25%, so new rate is 12.5 men. They finish in (40 - x - 6) = 34 - x days. Equation: 10x + 12.5(34 - x) = 400. 10x + 425 - 12.5x = 400. 2.5x = 25, so x = 10.
-
Rs. 14
-
Rs. 5
-
Rs. 20
-
Rs. 7
-
None of these
-
4 days
-
6 days
-
2 days
-
3 days
D
Correct answer
Explanation
Combined rate = 1/4 + 1/12 = 3/12 + 1/12 = 4/12 = 1/3. Time = 1 / (1/3) = 3 days.
-
6 days
-
10 days
-
7 days
-
5 days
-
None of these
D
Correct answer
Explanation
If a man works 1.5 times as much as a boy, 1 man = 1.5 boys. 4 men = 6 boys. The work takes 15 days. 8 men + 6 boys = 12 boys + 6 boys = 18 boys. Using (M1*D1 = M2*D2), 6 boys * 15 days = 18 boys * D2, so D2 = 90 / 18 = 5 days.