Time and Work Questions

Multiple choice
  1. 12 days

  2. 15 days

  3. 16 days

  4. 18 days

  5. 20 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A does the work in 24 days, so A's rate is 1/24 per day. The work is finished in 24 - 6 = 18 days. In 18 days, A does 18/24 = 3/4 of the work. B must have done the remaining 1/4 of the work in the first 4 days. B's rate is (1/4) / 4 = 1/16, so B takes 16 days.

Multiple choice
  1. $300
  2. $450
  3. $500
  4. $600
  5. $800
Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

A's work rate is 1/20, B's is 1/30. Let C's rate be 1/x. Total work = 1. The ratio of their shares is proportional to their work rates. Solving the system based on the total 900 and the difference between B and C leads to A receiving 450.

Multiple choice
  1. 9

  2. 13

  3. 12

  4. 15

  5. 16

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Total work = sum of 1+2+3+...+25 = (25 * 26) / 2 = 325 person-days. If 25 people work regularly, time = 325 / 25 = 13 days.

Multiple choice
  1. 10 days

  2. 24 days

  3. 25 days

  4. Cannot be determined

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let A, B, C be the work rates. A + B = 1/20 and B + C = 1/30. We want A + C. Subtracting the equations gives A - C = 1/20 - 1/30 = 1/60. We cannot determine A + C without knowing the individual rates or another relation.

Multiple choice
  1. 10 days

  2. 11 days

  3. 12 days

  4. 15 days

  5. 18 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Together rate = 1/8. In 3 days, they do 3/8 of work. Remaining = 5/8. Smith does 5/8 in 15 days, so Smith's rate = (5/8)/15 = 1/24. Bob's rate = 1/8 - 1/24 = 3/24 - 1/24 = 2/24 = 1/12. Bob takes 12 days.

Multiple choice
  1. 36 days

  2. 18 days

  3. 12 days

  4. 10 days

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let B be the work done by a boy per day and G be the work done by a girl per day. We have 2B + 5G = 1/3 and 6B + 6G = 1/2. Multiplying the first equation by 3 gives 6B + 15G = 1. Subtracting the second equation (6B + 6G = 1/2) from this gives 9G = 1/2, so G = 1/18. One girl takes 18 days.

Multiple choice
  1. 45

  2. 48

  3. 40

  4. 42

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Work = Men * Days * Hours. 1 man = 2 boys. 12 men + 18 boys = 24 boys + 18 boys = 42 boys. Work1 = 42 * 60 * 7.5 = 18900 boy-hours. Work2 = 2 * Work1 = 37800 boy-hours. 21 men + x boys = 42 boys + x boys = (42+x) boys. Work2 = (42+x) * 50 * 9 = 37800. 42+x = 37800 / 450 = 84. x = 42.

Multiple choice
  1. 20

  2. 15

  3. 12

  4. 10

  5. None of these

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

30 men = 10 days, so 1 man = 300 man-days. 12 women = 10 days, so 1 woman = 120 woman-days. 15 men = 15/300 = 1/20 of work per day. 6 women = 6/120 = 1/20 of work per day. Combined rate = 1/20 + 1/20 = 2/20 = 1/10. Time = 10 days.

Multiple choice
  1. 5

  2. 6

  3. 8

  4. 10

  5. 12

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let x be the days worked at normal efficiency. Total work = 10 * 40 = 400 man-days. After x days, 10x work is done. Remaining work = 400 - 10x. Efficiency increases by 25%, so new rate is 12.5 men. They finish in (40 - x - 6) = 34 - x days. Equation: 10x + 12.5(34 - x) = 400. 10x + 425 - 12.5x = 400. 2.5x = 25, so x = 10.