Quantitative Aptitude
Time and Work
2,195 QuestionsTime and Work Questions
A village road is to be constructed by a team of $250$ workers. After $12$ days it was found that only $2/7^{th}$ part of the work was complete. To complete the rest in another $25$ days, how many more workers should be employed?
Mark the correct alternative of the following.
If six men can do a piece of work in $6$ days, then $3$ men can do same work in?
Ten men, working for 6 days of 10 hours each, finish $ \dfrac {5}{21} $ of a piece of work. How many men working at the same rate and for the same number of hours each day, will be required to complete the remaining work in 8 days?
$35$ workers can build a house in $16$ days. How many days will $28$ workers working at the same rate take to build the same house?
Sakshi can do a piece of work in $20$ days. Tanya is $25$% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:
$A$ can do a piece of work in $10$ days and $B$ in $15$ days. How long will they take together to finish it ?
$A, B$ and $C$ can finish a job working alone in $72, 24$ and $36$ days respectively. In how many days they can finish the job if they worked together?
A can do a piece of work in $'x'$ days and $B$ can do the same work in $'x+16'$ days.If both working together can do it in $15$ days. Calculate $x$.
'$X$' completes a job in $2$ days and '$Y$' completes it in $3$ days and '$Z$' takes $4$ days to complete it. If they work together and get Rs. $3,900$ for the job, then how much amount does '$Y$' get?
Rehna works $2\cfrac { 1 }{ 2 } $ hours each day on her embroidery. She completes the work in $7$ days. How many hours did she take to complete her work?
Deepak can paint $\cfrac { 2 }{ 5 } $ of a house in one day. If he continuous working at this rate, how many days will he take to paint the whole house?
A can do a piece of work in $24$ days. If B is $60\%$ more efficient then the number of days required by B to do the twice as large as the earlier work is-
A and B can do a job in $12$ days, B and C can do it in $16$ days. After A has worked for $5$ days and B has worked for $7$ days, C can finish the rest in $13$ days. In how many days can C do the work alone?
If $12$ men complete a work in $20$ days. If only $8$ men are employed, then the time required to complete the same work is