Time and Work Questions

Multiple choice
  1. Sunday

  2. Monday

  3. Tuesday

  4. Wednesday

  5. Thursday

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A works 4h/day weekdays, 1h/day weekends. Total work 8h/day for 20 days = 160h. A's rate = 1/160 per hour. B's rate = 1/240 per hour. Combined rate = 1/160 + 1/240 = 5/480 = 1/96 per hour. They work 4h/day weekdays and 1h/day weekends. Weekly work = 5*4 + 2*1 = 22 hours. Total work needed = 96 hours. 4 weeks = 88 hours. Remaining 8 hours finished on Tuesday.

Multiple choice
  1. 8 days

  2. 6 days

  3. 15 days

  4. 16 days

  5. 20 days

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

A+B = 1/8, B+C = 1/12, C = 1/24. B = 1/12 - 1/24 = 1/24. A = 2 * B = 2/24 = 1/12. A+B+C = 1/12 + 1/24 + 1/24 = 2/24 + 1/24 + 1/24 = 4/24 = 1/6. Time = 6 days.

Multiple choice
  1. 6 days

  2. 8 days

  3. 5 days

  4. 12 days

  5. 16 5 days

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let a woman's work rate be w. Then a man's rate is 2w. Four women do the pit in 60 days, so the total work is 4w * 60 = 240w. Eight women and six men have a combined rate of 8w + 6(2w) = 20w. The time taken is 240w / 20w = 12 days.

Multiple choice
  1. 16 days

  2. 15.5 days

  3. 17 days

  4. 16.5 days

  5. 17 1 7 days

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Ram's rate = 1/10, Karan = 1/20, Vineet = 1/40. In 3 days, they do 1/10 + 1/20 + 1/40 = 7/40. In 6 cycles (18 days), they do 42/40 (too much). In 5 cycles (15 days), they do 35/40. Remaining work = 5/40 = 1/8. Day 16: Ram does 1/10. Remaining = 1/8 - 1/10 = 1/40. Day 17: Karan does 1/20. He finishes the 1/40 in half a day. Total = 16.5 days.

Multiple choice
  1. Only A is sufficient

  2. Only B is sufficient

  3. Only C is sufficient

  4. Either A or C is sufficient

  5. Either B or C is sufficient

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Statement A gives the work rate of 1 man and 1 boy. Statement C gives the work rate of 6 men. Both allow calculating the individual rates of men and boys, which is sufficient to determine the remaining work time. Statement B is just a description of the remaining work.

Multiple choice
  1. 11

  2. 12

  3. 13.5

  4. 14.5

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let R and G be daily work rates. R+G = 1/16. In 7 days, they do 7/16 work. Remaining work = 9/16. After 7 days, R's rate becomes 0.7R. They finish in 10 more days (17-7). So, 10(0.7R + G) = 9/16. 7R + 10G = 9/16. Solving the system: R+G=1/16 => 7R+7G=7/16. Subtracting gives 3G = 2/16, so G = 2/48 = 1/24. Remaining work 9/16 divided by G (1/24) = (9/16) * 24 = 216/16 = 13.5 days.

Multiple choice
  1. 13

  2. 14

  3. 12

  4. 18

  5. 15

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

A does 1/10 of the work per day, and B does 1/20. In a 2-day cycle, they complete 1/10 + 1/20 = 3/20 of the work. After 6 cycles (12 days), 18/20 of the work is done; on day 13, A completes the remaining 2/20 (1/10) of the work.

Multiple choice
  1. 40

  2. 48

  3. 50

  4. 60

  5. 72

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

A+B complete work in 24 days. A gets 50% more than B, so A's efficiency is 1.5 times B's. A = 1.5B. (1.5B + B) * 24 = Total Work. 2.5B * 24 = 60B. B alone takes 60 days.

Multiple choice
  1. 17 days

  2. 17.5 days

  3. 22.5 days

  4. 19.5 days

  5. 20 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Sonu's rate = 1/15, Monu's rate = 1/18. Let Saif's rate be 1/x. Together they do 1/6 of the work per day. 1/15 + 1/18 + 1/x = 1/6. (6+5)/90 + 1/x = 1/6. 11/90 + 1/x = 15/90. 1/x = 4/90 = 2/45. x = 22.5 days.

Multiple choice
  1. 5

  2. 6

  3. 7

  4. 8

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let total days be T. A works 2 days (2/10), B works (T-3) days (T-3)/12, C works T days (T/15). 2/10 + (T-3)/12 + T/15 = 1. Multiply by 60: 12 + 5(T-3) + 4T = 60. 12 + 5T - 15 + 4T = 60. 9T - 3 = 60. 9T = 63. T = 7.