U and V can complete a piece of work in 6 and 48 days, respectively. They contracted to complete some work for Rs. 45,000. What will be the share (in Rs.) of U?

  1. 35,000

  2. 37,000

  3. 36,000

  4. 40,000

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

U and V complete work in 6 and 48 days. Their work rates are 1/6 and 1/48. The ratio of their work is 8:1. U's share is (8/9) * 45,000 = 40,000.