Time and Work Questions

Multiple choice
  1. Any two

  2. I and either II or III

  3. Any one

  4. All I, II and III

  5. None of these

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Statement I: Combined rate of Reetesh + Rahul. Statement III: Reetesh's individual rate. From I and III, Rahul's rate can be found. Statement II confirms this but is not needed - once we have individual rates, Rahul's time alone can be calculated. So I and III are sufficient. I and II together also work: from combined rate (I) and the work pattern (II), Rahul's contribution can be derived. Thus I + either II or III works.

Multiple choice
  1. 30 days

  2. 35 days

  3. 40 days

  4. 45 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

A's work in (3/4)t time = (1/2) of B's work in t time → A's rate : B's rate = (1/2)/(3/4) = 2/3. Together in 18 days: (2/3 + 1) × B's work = 18 days → (5/3)B = 18 → B = 18 × 3/5 = 54/5 = 10.8 days for full work. This is wrong; recalculate: If B's rate = 1 work per x days, A's rate = (1/2)/(3/4x) = 2/3x. Combined: 1/x + 2/3x = 18 days → 5/3x = 18 → x = 30 days. B takes 30 days alone.

Multiple choice
  1. Rs.180

  2. Rs. 200

  3. Rs. 225

  4. Rs. 250

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

First, calculate each person's daily work capacity: Person 1 = 1/8, Person 2 = 1/12, Person 3 = 1/16. In 3 days, they complete 3×(1/8 + 1/12 + 1/16) = 3×(13/48) = 39/48 of the work. The fourth person contributed 1 - 39/48 = 9/48 = 3/16 of the total work. Therefore, the fourth person gets (3/16)×1200 = Rs. 225.

Multiple choice
  1. Only I and II

  2. Only II and III

  3. Only I and III

  4. Any two of the three

  5. None of these

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

Let individual rates be R, S, Ss (Ram, Shyam, Suresh). From statements: R+S=1/18, Ss+R=1/15, S+Ss=1/12 (where all rates are per day). We need combined rate R+S+Ss. Adding all three equations: 2(R+S+Ss) = 1/18 + 1/15 + 1/12. So R+S+Ss = (1/2) × (1/18 + 1/15 + 1/12). But the answer is E (None of these), suggesting the statements together are insufficient or don't give a unique answer.

Multiple choice
  1. 4 days

  2. 8 days

  3. 16 days

  4. 32 days

  5. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let A, B, C be work rates. A+B = 1/18, B+C = 1/24, A+C = 1/36. Add all: 2(A+B+C) = 1/18 + 1/24 + 1/36 = 4/72 + 3/72 + 2/72 = 9/72 = 1/8. So A+B+C = 1/16. Together they complete the work in 16 days. Option C (16 days) is correct.

Multiple choice
  1. 16

  2. 8

  3. 12

  4. 10

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

If A is thrice as efficient as B, then A's work rate is 3x B's rate. Let B take x days, so A takes x-8 days. Since work = rate × time, and work done is the same: 3(x-8) = x, giving x = 12 days. Alternatively, use the formula: if A is k times efficient and takes d days less, then B takes kd/(k-1) = 3×8/2 = 12 days.

Multiple choice
  1. 36

  2. 24

  3. 18

  4. 16

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

6 men in 12 days means 1 man does 1/72 of work per day. 8 women in 18 days means 1 woman does 1/144 of work per day. 18 children in 10 days means 1 child does 1/180 of work per day. Work done by 4 men + 12 women + 20 children in 2 days = 2×(4/72 + 12/144 + 20/180) = 2×(1/18 + 1/12 + 1/9) = 2×(2/36 + 3/36 + 4/36) = 2×(9/36) = 1/2. Remaining work = 1/2. If men complete this in 1 day, we need m men such that m/72 = 1/2, so m = 36 men are required.

Multiple choice
  1. 12 days

  2. 15 days

  3. 8 days

  4. 10 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

8 men in 5 days means total work = 8 × 5 = 40 man-days. So 1 man does 1/40 of work per day. 16 women in 5 days means total work = 16 × 5 = 80 woman-days. So 1 woman does 1/80 of work per day. 2 men + 6 women = 2(1/40) + 6(1/80) = 1/20 + 3/40 = 5/40 = 1/8 of work per day. Days needed = 1 / (1/8) = 8 days. Option C is correct.

Multiple choice
  1. 4 days

  2. 8 days

  3. 6 days

  4. 10 days

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

If A does thrice as much work as B, then A's work rate is 3 times B's. Let B's rate = 1 unit/day, so A's rate = 3 units/day. Combined rate = 4 units/day. If they complete work in 3 days, total work = 4 × 3 = 12 units. A alone would take 12/3 = 4 days. This is a work-rate problem where efficiency ratios determine individual times.