Quantitative Aptitude
Time and Work
2,195 Questions
Time and Work Questions
-
75
-
70
-
78
-
72
-
None of these
E
Correct answer
Explanation
Let M be the number of men. Work = M × 45 man-days. With (M-8) men, time = 50 days. So (M-8) × 50 = M × 45, giving 50M - 400 = 45M, so 5M = 400, M = 80. Since 80 is not among A-D, E is correct.
B
Correct answer
Explanation
Let 1 man's work = m, 1 boy's work = b per day. 6m + 5b = 1/6, 3m + 4b = 1/10. Solving: 18m + 15b = 1, 18m + 24b = 1.8. Subtracting: 9b = 0.8, b = 0.8/9, m = (1/6 - 5b)/6 = 1/36 - 5b/6. 9m + 6b = 1/3 = 3 days.
C
Correct answer
Explanation
Work = men × days × hours. For first case: 200m wall needs 40 × 12 × 8 = 3840 man-hours. So 1m needs 3840/200 = 19.2 man-hours. For 300m wall: needs 300 × 19.2 = 5760 man-hours. With 30 men working 6 hours: days = 5760/(30 × 6) = 5760/180 = 32 days.
-
4
-
8
-
6
-
Cannot be determined
-
None of these
B
Correct answer
Explanation
2 men's 1 day work = 1/6, so 1 man's 1 day work = 1/12. 2 women's 1 day work = 1/9, so 1 woman's 1 day work = 1/18. 3 children's 1 day work = 1/8, so 1 child's 1 day work = 1/24. Work done by 3 women + 4 children in 1 day = 3/18 + 4/24 = 1/6 + 1/6 = 1/3. Remaining work = 2/3. To finish 2/3 work in 1 day, men needed = (2/3)/(1/12) = 8. The key is finding individual work rates first.
-
5 days
-
3 days
-
10 days
-
15 days
B
Correct answer
Explanation
A's 1 day work = 1/5, B's 1 day work = 1/10, C's 1 day work = 1/30. Together in 1 day = 1/5 + 1/10 + 1/30 = (6+3+1)/30 = 10/30 = 1/3. So they complete the work together in 3 days. Add individual efficiencies, then invert to get total time.
B
Correct answer
Explanation
16 men × 12 days = 192 man-days of work. In 4 days, 16 men complete 16×4 = 64 man-days. Remaining work = 192-64 = 128 man-days. To finish in 4 days: 128/4 = 32 men needed. Additional men = 32-16 = 16. Use the man-days formula: men × days = constant work.
-
12 days
-
5 days
-
2 days
-
24 days
-
None of these
A
Correct answer
Explanation
Let total work = LCM(3, 8) = 24 units. Combined rate of A, B, C = 24/3 = 8 units/day. Rate of A alone = 24/8 = 3 units/day (same as B). Combined rate of A and B = 3 + 3 = 6 units/day. Therefore, C's rate = 8 - 6 = 2 units/day. Time for C alone = 24/2 = 12 days. The distractor 24 days comes from incorrectly adding rates instead of subtracting.
-
27 days
-
25 days
-
20 days
-
24 days
-
30 days
A
Correct answer
Explanation
This is an inverse proportion problem. Total work = 15 × 25 × 9 = 3375 person-hours. For 25 persons working 5 hours daily: days = 3375 ÷ (25 × 5) = 3375 ÷ 125 = 27 days. As number of persons increases, days decrease (inverse proportion), and as hours decrease, days increase (inverse proportion).
-
10 days
-
30 days
-
15 days
-
5 days
B
Correct answer
Explanation
Let total work = LCM(15, 12, 20) = 60 units. (A+B) = 60/15 = 4 units/day, (B+C) = 60/12 = 5 units/day, (C+A) = 60/20 = 3 units/day. Adding: 2(A+B+C) = 12, so A+B+C = 6 units/day. Individual rates: A = 6-5 = 1, B = 6-3 = 3, C = 6-4 = 2 units/day. Working alternately A→B→C: Cycle of 3 days = 1+3+2 = 6 units. 10 cycles (30 days) = 60 units, so work completes in exactly 30 days.
D
Correct answer
Explanation
Total work = 33 × 30 = 990 man-days. On day 1: 44 men work, completing 44 man-days. On day 2: 43 men work, completing 43 man-days. This forms an arithmetic series: 44 + 43 + 42 + ... + (44-n+1). We need sum = 990. The sum from 44 to 1 is 44×45/2 = 990 man-days. This takes 44 days (from 44 men down to 1 man).
-
6 days
-
24 days
-
4 days
-
3 days
-
None of these
C
Correct answer
Explanation
4 men = 6 women in work capacity. 1 man = 1.5 women. 4 men + 12 women = 6 + 12 = 18 women. Original: 6 women take 12 days. 18 women (3× efficiency) take 12/3 = 4 days. Option C is correct.
-
24 days
-
25 days
-
30 days
-
32 days
-
None of these
A
Correct answer
Explanation
A's work rate = 1/60 per day. In 15 days, A completes 15/60 = 1/4 of work. Remaining work = 3/4. B does 3/4 work in 30 days, so B's rate = (3/4)/30 = 1/40 per day. Combined rate = 1/60 + 1/40 = 5/120 = 1/24 per day. Together they take 24 days. Option A is correct.
-
75 men
-
100 men
-
65 men
-
46 men
A
Correct answer
Explanation
In 24 days, 25 men complete 1/3 of the work. So 25 men × 24 days = 600 man-days for 1/3 work, meaning total work = 1800 man-days. Remaining work = 1200 man-days. Time remaining = 40 - 24 - 4 = 12 days (4 days earlier than scheduled). Men needed = 1200/12 = 100 men. Extra men = 100 - 25 = 75 men. This follows the chain rule: men × days is proportional to work.
-
36
-
60
-
56
-
65
-
None of these
C
Correct answer
Explanation
This is a Time & Work problem using the formula: M1 × H1 × D1 = M2 × H2 × D2. Given: 16 × 9 × 28 = M2 × 6 × 12. Solving: 4032 = M2 × 72, so M2 = 4032/72 = 56 men.
B
Correct answer
Explanation
Let m be man's work per day, b be boy's work per day. From given: 2m + 4b = 1/10 and 4m + 5b = 1/6. Solving gives m = 1/70, b = 1/140. So a man does twice the work of a boy. If man's wage is Rs 40, boy's wage should be Rs 20 (since wages are proportional to output). Ratio = 40:20 = 5:2. Common mistake is not solving the equations correctly.