Quantitative Aptitude
Time and Work
2,195 Questions
Time and Work Questions
-
6 days
-
12 days
-
14 days
-
Can’t be determined
-
None of these
D
Correct answer
Explanation
We know: 10 men + 5 women complete the work in 12 days. Also: 8 children complete the same work in 16 days. We need to find: 3 men + 2 women + 2 children's rate. However, we have no information about the relative efficiency of men vs women vs children. Without knowing how a man's work compares to a woman's or a child's, we cannot combine these rates. The data is insufficient.
-
Rs.25
-
Rs. 20
-
Rs. 45
-
Rs. 65
A
Correct answer
Explanation
First man's rate: 1/6 work per day. Second man's rate: 1/8 work per day. Together with boy, they finish in 3 days, so combined rate is 1/3 per day. Boy's rate = 1/3 - (1/6 + 1/8) = 1/3 - 7/24 = 1/24. Boy does 3 × (1/24) = 1/8 of work. His share = (1/8) × Rs. 200 = Rs. 25. Options B (Rs. 20), C (Rs. 45), and D (Rs. 65) are incorrect.
-
2 days
-
5 days
-
6 days
-
10 days
A
Correct answer
Explanation
12 men's rate = 1/10 work/day, so 1 man = 1/120. 20 women's rate = 1/12, so 1 woman = 1/240. 8 men + 4 women work for 9 days: (8/120 + 4/240) × 9 = (0.067 + 0.017) × 9 = 0.75 work done. Remaining = 0.25. New team: 8 men + 14 women = 8/120 + 14/240 = 0.067 + 0.058 = 0.125/day. Days needed = 0.25/0.125 = 2 days.
D
Correct answer
Explanation
Let original men = M. Work = M × 18 man-days. When 6 men leave, M - 6 men take 20 days: (M-6) × 20 = M × 18. Solving: 20M - 120 = 18M, so 2M = 120, giving M = 60 men originally. This uses the inverse relationship between men and time for constant work.
D
Correct answer
Explanation
Let original men = M. Work = M × 40 man-days. With 45 more men: (M + 45) × 25 = M × 40. Solving: 25M + 1125 = 40M, so 15M = 1125, giving M = 75 men originally. This follows from the inverse proportionality - more men means fewer days needed.
-
44 days
-
50 days
-
65 days
-
55 days
-
58 days
D
Correct answer
Explanation
If Ram is 4 times as efficient as Shyam, then Ram does 4 units of work per day while Shyam does 1 unit per day. Together, they do 5 units per day and complete the work in 11 days, so total work = 5 × 11 = 55 units. Shyam alone would take 55 units ÷ 1 unit/day = 55 days. This is option D.
-
15 days
-
27 days
-
30 days
-
36 days
-
None of these
B
Correct answer
Explanation
Total work = 24 men × 18 days = 432 man-days. For 16 men: days = 432/16 = 27 days. This is inverse variation: fewer men means more days. Option B (27 days) is correct.
C
Correct answer
Explanation
Let A, B, C's 1-day work be a, b, c. From the given: a+b=1/8, b+c=1/12, a+b+c=1/6. Subtract third from first: c = 1/6 - 1/8 = 1/24. Subtract third from second: a = 1/6 - 1/12 = 1/12. Therefore, A+C together do 1/12 + 1/24 = 1/8 work per day, taking 8 days to complete.
-
10 days
-
12 days
-
18 days
-
16 days
-
8 days
D
Correct answer
Explanation
16 men × 16 days = 256 man-days. 20 women × 16 days = 320 woman-days. So 16 man-days = 20 woman-days, or 4 men = 5 women. Work needed = 256 man-days. 8 men + 10 women = 8 men + 8 men = 16 men (since 10 women = 8 men). Days = 256/16 = 16 days.
-
12 days
-
14 days
-
8 days
-
15 days
-
None of these
E
Correct answer
Explanation
Let total time = T days. X works for (T-4) days at 1/24 per day, Y works for T days at 1/32 per day. Equation: (T-4)/24 + T/32 = 1. Solving: 4(T-4) + 3T = 96, giving 7T - 16 = 96, so T = 16 days. The answer should be 16 days, but since this isn't among options A-D, 'None of these' is indeed correct.
-
6 days
-
4 days
-
5 days
-
8 days
-
None of these
D
Correct answer
Explanation
36 men complete work in 16 days, so total work = 576 man-days. After 4 days, work done = 144 man-days, remaining = 432 man-days. New team: 30 men + 48 women (where 2 women = 1 man, so 48 women = 24 man-equivalent) = 54 man-equivalent. Days needed = 432/54 = 8 days exactly. The claimed answer D (8 days) is correct.
-
350 Rs.
-
450 Rs.
-
269 Rs.
-
369 Rs.
-
None of these
C
Correct answer
Explanation
A's rate = 1/10 per day, B's rate = 1/15 per day. Together in 5 days they complete 5(1/10+1/15) = 5(1/6) = 5/6 of work. Remaining 1/6 done by C in 24 days, so C's rate = 1/144 per day. Total rate of all three = 1/10+1/15+1/144. C's share of wage = (C's rate)/(combined rate) × 1614 = 1614/24 = 67.25. However, looking at the options, 269 Rs equals 4 × 67.25, suggesting C's work share is 1/6 of total, so wage = (1/6)/(1) × 1614 = 269. Answer C is correct.
-
10 boys
-
8 boys
-
9 boys
-
6 boys
B
Correct answer
Explanation
Using inverse proportion: if 4 boys complete work in 12 days, then 4 × 12 = 48 boy-days are needed. To finish in 6 days, divide 48 by 6 = 8 boys. This is a standard work-rate problem where more workers reduce time proportionally.
-
30 days
-
32 days
-
36 days
-
25 days
-
None of these
B
Correct answer
Explanation
8 men complete work in 40 days, so total work = 8 × 40 = 320 man-days. With 10 men (8 + 2), days needed = 320/10 = 32 days. More workers means fewer days - inverse proportion.
-
$\(\frac{23}{89}\) days$
-
$\(\frac{76}{5}\) days$
-
$\(\frac{66}{7}\) days$
-
$17 days$
B
Correct answer
Explanation
A's work per day = 1/20, B's = 1/12. They work alternately starting with A. In 2 days, work done = 1/20 + 1/12 = 8/60 = 2/15. After 14 complete cycles (28 days), work = 28/15 ≈ 1.87 > 1, so fewer cycles needed. After 7 cycles (14 days), work = 14/15. Remaining 1/15 done by A in (1/15)/(1/20) = 4/5 days. Total = 14 + 4/5 = 76/5 days.