Multiple choice

‘A’ can do a piece of work in 20 days and ‘B’ can do the same work in 12 days. Find the number of days in which they can complete the whole work if they work on alternate days and the work is started by ‘A’?

  1. $\(\frac{23}{89}\) days$
  2. $\(\frac{76}{5}\) days$
  3. $\(\frac{66}{7}\) days$
  4. $17 days$
Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

A's work per day = 1/20, B's = 1/12. They work alternately starting with A. In 2 days, work done = 1/20 + 1/12 = 8/60 = 2/15. After 14 complete cycles (28 days), work = 28/15 ≈ 1.87 > 1, so fewer cycles needed. After 7 cycles (14 days), work = 14/15. Remaining 1/15 done by A in (1/15)/(1/20) = 4/5 days. Total = 14 + 4/5 = 76/5 days.