Time and Work Questions

Multiple choice
  1. 73 days

  2. 76 days

  3. 75 days

  4. 72 days

  5. None of these

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Rohan's rate = 1/36 work per day. Combined rate (Rohan + Mohan) = 1/24 work per day. Mohan's rate = (1/24) - (1/36) = (3 - 2)/72 = 1/72 work per day. So Mohan alone takes 72 days to complete the work. Option D is correct.

Multiple choice
  1. 14

  2. 17

  3. 16

  4. 18

  5. 11

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

Using the work formula: M1 × D1 × H1 = M2 × D2 × H2. Given: 24 men × 12 days × 8 hours = 2304 man-hours. For 36 men working 6 hours per day: 36 × 6 × D2 = 2304, so D2 = 2304 / 216 = 10.67 days. However, this doesn't match 11. Let me recalculate: 24 × 12 × 8 = 2304. 36 × 6 × D = 2304, so D = 2304/(36×6) = 2304/216 = 10.67. The answer should be approximately 11 days (rounding up since you can't have a fraction of a day in practice).

Multiple choice
  1. 30

  2. 32

  3. 34

  4. 36

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Total work = 24 men × 8 hours/day × 10 days = 1920 man-hours. Required: complete in 6 days at 10 hours/day. Men needed = 1920 ÷ (6 × 10) = 1920 ÷ 60 = 32 men. Option A (30): would give 1800 man-hours, insufficient. Option C (34): would give 2040 man-hours, more than needed. Option D (36): would give 2160 man-hours.

Multiple choice
  1. 8 days

  2. 9 days

  3. 12 days

  4. 16 days

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

16 men in 8 days means 1 man does 1/(16×8) = 1/128 work per day. 20 women in 16 days means 1 woman does 1/(20×16) = 1/320 work per day. 12 men + 10 women for 6 days complete: 12/128×6 + 10/320×6 = 9/16 + 3/16 = 12/16 = 3/4 of work. Remaining 1/4 work by 10 women: (1/4)/(10/320) = 8 days.

Multiple choice
  1. 10 days

  2. 12 days

  3. 15 days

  4. 16 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

B and C together do 2 days of work: B's rate = 1/20, C's rate = 1/30, combined = 1/12 per day. In 2 days they complete 2/12 = 1/6 of work. Remaining = 5/6. A's rate = 1/18, so time for 5/6 = (5/6) × 18 = 15 days.

Multiple choice
  1. 8

  2. 3

  3. 5

  4. 10

  5. None of these

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

45 men × 16 days = 720 man-days of total work. After 6 days, work done = 45 × 6 = 270 man-days. Remaining work = 720 - 270 = 450 man-days. Now 30 more men join, so 75 men work. Days needed = 450/75 = 6 days. Total days = 6 + 6 = 12 days. Options are 8, 3, 5, 10, 'None of these' - so 'None of these' (E) is correct.

Multiple choice
  1. 18 days

  2. 20 days

  3. 24 days

  4. 28 days

  5. 30 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let total work be LCM(36,52,72)=468 units. A's rate=13, B's rate=9, C's rate=6.5 units/day. If total time is x days, A worked x-8 days, B worked x-12 days, C worked x days. 13(x-8)+9(x-12)+6.5x=468. Solving: 28.5x-232=468, x=24. C worked all 24 days.

Multiple choice
  1. 2.5 days

  2. 3 days

  3. 3.33 days

  4. 4 days

  5. 4.25 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

P's rate: (2/3)/6 = 1/9 per day. Q's rate: (1/3)/8 = 1/24 per day. R's rate: (3/4)/12 = 1/16 per day. Combined work in 4 days: 4(1/9 + 1/24 + 1/16) = 4(1/9 + 7/48) = 4(55/144) = 55/36. Remaining work: 1 - 55/36 = -19/36 (this is negative, indicating an error in my calculation). Let me recalculate: 1/9 = 16/144, 1/24 = 6/144, 1/16 = 9/144. Combined = 31/144 per day. In 4 days: 124/144 = 31/36 done. Remaining: 5/36. Q's time for 5/36 = (5/36)/(1/24) = 5/36 × 24 = 10/3 = 3.33 days.

Multiple choice
  1. 5 hours

  2. 6 hours

  3. 8 hours

  4. 10 hours

  5. 12 hours

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Work = Examiners × Days × Hours. Let W = work for original books. 4 × 8 × 5 = 160 examiner-hours. New work is twice: 2W = 320 examiner-hours. With 2 examiners for 20 days: 2 × 20 × h = 320, so 40h = 320, h = 8 hours. Option C is correct.