Time and Work Questions

Multiple choice
  1. 1000

  2. 1200

  3. 12000

  4. 14400

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Saurabh's work rate: 1/36 per day. Tarun's work rate: 1/48 per day. Combined (Saurabh + Tarun + Pawan) rate: 1/12 per day. Pawan's rate = 1/12 - (1/36 + 1/48) = 1/12 - 7/144 = 12/144 - 7/144 = 5/144. Ratio of work rates: Saurabh : Tarun : Pawan = 4/144 : 3/144 : 5/144 = 4:3:5. Total parts = 12, Pawan's share = 5/12 of ₹28,800 = ₹12,000.

Multiple choice
  1. 6

  2. 4

  3. 12

  4. 8

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let Naimish, Arun, and Deepak take n, a, and d days respectively. Given n = 2a and n = 3d, so their one-day work is 1/n, 1/a, 1/d. Working together: (1/n + 1/a + 1/d) = 1/2. Since n = 3d, Arun takes 1.5d days. Combined rate: 1/(3d) + 1/(1.5d) + 1/d = 1/(3d) + 2/(3d) + 1/d = 2/d. Therefore 2/d = 1/2, giving d = 4 days for Deepak alone.

Multiple choice
  1. 14 days / दिन

  2. 21 days / दिन

  3. 28 days / दिन

  4. 18 days / दिन

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let B's time be 2x, so A's time is x. A's rate = 1/x, B's rate = 1/(2x). C's time = A + B together = x + 2x over their combined rate. Combined rate of A and B = 1/x + 1/(2x) = 3/(2x), so C's time = 1 ÷ (3/(2x)) = 2x/3. C's rate = 1/(2x/3) = 3/(2x). Together: 1/x + 1/(2x) + 3/(2x) = 3/x = 1/7, so x = 21. A alone takes 21 days.

Multiple choice
  1. 44 days / दिन

  2. 55 days / दिनों

  3. 60 days / दिनों

  4. 33 days / दिनों

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Ram's efficiency = 4 × Shyam's. If Shyam does x work/day, Ram does 4x work/day. Together: 5x work/day. Work completed in 11 days: 11(5x) = 55x = total work. Shyam alone: 55x/x = 55 days. If Ram worked alone: 55x/(4x) = 13.75 days. 44 days would be if Ram was 5 times efficient, 33 days if equal efficiency.

Multiple choice
  1. 32

  2. 36

  3. 30

  4. 40

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let m be the original number of men. Work = m × 60 man-days. With (m+8) men: (m+8) × 50 = m × 60. Solving: 50m + 400 = 60m, so 10m = 400, giving m = 40 men. Verification: 40 × 60 = 2400 man-days, and 48 × 50 = 2400 man-days. Both calculations match.

Multiple choice
  1. 50

  2. 48

  3. 56

  4. 64

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Work done in 64 days by 120 men = 120 × 64 = 7680 man-days, which equals 2/3 of total work. Total work = 7680 × 3/2 = 11520 man-days. Remaining work = 11520 - 7680 = 3840 man-days. Remaining time = 124 - 64 = 60 days. Men needed = 3840/60 = 64. Men discharged = 120 - 64 = 56.

Multiple choice
  1. 75

  2. 45

  3. CND/ निर्धारित नही किया जा सकता है

  4. 115

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Number of women = 90 × (2/3) = 60, children = 90 × (1/3) = 30. Let wages be 5x, 3x, 2x. Total = 90(5x) + 60(3x) + 30(2x) = 690x = 10350, so x = 15. Woman's wage = 3x = 45.

Multiple choice
  1. 5

  2. 6

  3. 7

  4. 10

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

A + B do 1/3 work per day. After 2 days, 1/3 work remains, done by A alone in 2 days, so A's rate = 1/6 per day. B's rate = (1/3 - 1/6) = 1/6, so B alone takes 6 days.

Multiple choice
  1. 5 days/ दिन

  2. 3 days/ दिन

  3. 4 days/ दिन

  4. 4.5 days/ दिन

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let 1 man's 1 day work = m, 1 woman's 1 day work = w. From given: 6m + 5w = 1/6 (work per day), and 3m + 4w = 1/10. Solving: Multiply second eq by 2: 6m + 8w = 1/5. Subtract from first: -3w = 1/6 - 1/5 = -1/30, so w = 1/90. Then 6m = 1/6 - 5/90 = 15/90 - 5/90 = 10/90, so m = 1/54. For 9 men + 15 women: daily work = 9/54 + 15/90 = 1/6 + 1/6 = 1/3. Days needed = 1/(1/3) = 3. Answer B is correct.

Multiple choice
  1. 15 days/दिन

  2. 10 days/दिन

  3. 18 days/दिन

  4. 20 days/दिन

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let total work = LCM(30,15,10) = 30 units. Combined rates: A+B = 1 unit/day, B+C = 2 units/day, C+A = 3 units/day. Adding all three: 2(A+B+C) = 6, so A+B+C = 3 units/day. Time together = 30/3 = 10 days.

Multiple choice
  1. Rs.105

  2. Rs.150

  3. Rs.25

  4. Rs.185

  5. Rs.125

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Setting up the equations: (2m + w) × 14 = (2m + 4w) × 8, where m and w represent one day's work by a man and woman respectively. Solving gives 12m = 18w, or m/w = 3/2. Since wages should be proportional to efficiency and a man earns Rs.225, a woman should earn 225 × (2/3) = Rs.150 per day.

Multiple choice
  1. 20

  2. 30

  3. 36

  4. 40

  5. None of these

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Setting up the equations: 5(3m + 7w) = 4(4m + 6w) = 1. Solving gives 11w = m. Substituting back: 5(40w) = 1, so w = 1/200 of the job per day. For 10 women: 10w = 10/200 = 1/20 of the job per day. Therefore, 10 women take 20 days.

Multiple choice
  1. 3

  2. 4

  3. 5

  4. 8

  5. 9

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

When 'OR' is used in work-time problems, it means the work rates are equal. Here, 2 Men and 5 Women both complete the work in 16 days, so they have equal rates. Therefore, 2 Men + 5 Women working together equals 4 Men working. If 2 Men take 16 days, then 4 Men (double the workforce) take half the time: 16/2 = 8 days.

Multiple choice
  1. 5

  2. 15

  3. 28

  4. 6

  5. 16

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Calculate individual rates: 8 men do in 12 days, so 1 man's rate = 1/(8×12) = 1/96 work per day. 4 women do in 48 days, so 1 woman's rate = 1/(4×48) = 1/192 work per day. 10 children do in 24 days, so 1 child's rate = 1/(10×24) = 1/240 work per day. Combined rate of 10M + 4W + 10C = 10/96 + 4/192 + 10/240 = 10/96 + 2/96 + 4/96 = 16/96 = 1/6. Therefore, they complete the work in 6 days.