Time and Work Questions

Multiple choice
  1. 4 days/दिन

  2. 5 days/दिन

  3. 3 days/दिन

  4. 2 days/दिन

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

From the given information, 3 men's work = 6 women's work, so 1 man = 2 women. The total work is 3 × 16 = 48 man-days. Converting 8 men and 8 women to men: 8 men + 4 men = 12 men total. Days needed = 48/12 = 4 days. The key is converting women to equivalent men using the rate relationship.

Multiple choice
  1. 46 days

  2. 52 days

  3. 64 days

  4. 68 days

  5. 72 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

If Prakash is thrice as efficient as Neeraj, let Neeraj's efficiency = 1 unit/day, then Prakash's = 3 units/day. Combined efficiency = 4 units/day. Total work = 4 × 16 = 64 units. Neeraj alone = 64/1 = 64 days. The distractors 52, 68, and 72 days come from incorrect ratio setups or calculation errors.

Multiple choice
  1. 25

  2. 20

  3. 15

  4. 10

  5. 30

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Total work = 20×30 = 600 man-days. First 10 days: 20 men complete 200 units. Next 10 days: 10 men complete 100 units. Remaining 20 days: work = 600-300 = 300 units, requiring 300/20 = 15 men. Since only 10 men remain, need 15-10 = 5 more men - but this gives 15 men for 20 days = 300 units. Actually, check: 10 men for 20 days = 200 units, but need 300. So need 300/20 = 15 men total, meaning 15-10 = 5 more men needed. Wait, options suggest 20 more men - rechecking: After 20 days, 300 work done, 300 remains. With 20 days left, need 300/20 = 15 men. Have 10, need 5 more. But answer claims 20 more men (total 25) - let's verify: 25×20 = 500, but only 300 needed. There's a calculation mismatch.

Multiple choice
  1. P

  2. Q

  3. R

  4. S

  5. Cannot be determined

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Calculate each person's rate: P does 1/4 work in 10 days, so full work in 40 days. Q does 40% (2/5) work in 15 days, so full work in 15 × 5/2 = 37.5 days. R does 1/3 work in 13 days, so full work in 39 days. S does 1/6 work in 7 days, so full work in 42 days. Q completes work fastest (37.5 days), so Q is the answer.

Multiple choice
  1. 50 days / दिन

  2. 45 days / दिन

  3. 60 days / दिन

  4. 54 days / दिन

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let the man's efficiency be 3x and woman's efficiency be 2x. Combined efficiency = 5x work/day. They complete work in 20 days, so total work = 20 × 5x = 100x units. Woman alone at 2x efficiency would take 100x/2x = 50 days. Option B (45 days) would require different efficiency ratios. Option C (60 days) assumes equal efficiency. Option D (54 days) is a miscalculation.

Multiple choice
  1. 30 days / दिन

  2. 27 days / दिन

  3. 20 days / दिन

  4. 25 days / दिन

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let B take x days alone. Then A takes (x-10) days alone. Their combined rate: 1/(x-10) + 1/x = 1/12. Solving: (x + x - 10)/[x(x-10)] = 1/12, so (2x-10)×12 = x(x-10). This gives 24x - 120 = x² - 10x, or x² - 34x + 120 = 0. Solving: x = [34 ± √(1156 - 480)]/2 = [34 ± √676]/2 = [34 ± 26]/2. So x = 30 or x = 4. Since A takes (x-10) days, x cannot be 4. Thus x = 30 days.

Multiple choice
  1. 65 days/दिन

  2. 75 days/दिन

  3. 85 days/दिन

  4. 102 days/दिन

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let man's efficiency = 14k, woman's = 11k. Together: 25k work/day. In 33 days, work = 33 × 25k = 825k. Woman alone: 825k/(11k) = 75 days. Check: Together rate = 1/33, woman rate = 11/25 of together = 11/(25×33) = 11/825 = 1/75.

Multiple choice
  1. 12

  2. 24

  3. 36

  4. 48

  5. 60

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

This is an inverse proportion problem - more children means fewer days. Total work = 30 × 16 = 480 child-days. To complete in 20 days, children needed = 480/20 = 24. Option A (12) would give 12×20 = 240 child-days, half the required work. Option C (36) would give 36×20 = 720 child-days, exceeding the requirement.

Multiple choice
  1. 6 days/ दिन

  2. 8 days/ दिन

  3. 10 days/ दिन

  4. 11 days/ दिन

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Ram and Shyam together complete 60% in 4 days, so 100% would take them 4 × (100/60) = 20/3 days together. Let Ram take R days alone, Shyam take S days alone. Their combined rate: 1/R + 1/S = 3/20. Shyam completes remaining 40% alone in 8 days, so 100% takes S = 8 × (100/40) = 20 days. Therefore: 1/R = 3/20 - 1/20 = 2/20 = 1/10, so R = 10 days.

Multiple choice
  1. Only I

  2. Only II

  3. Any two

  4. All I, II and III

  5. None of these

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let m = 1 man's work/day, w = 1 woman's work/day. From I: 6(6m+5w)=1, so 36m+30w=1. From II: 10(3m+4w)=1, so 30m+40w=1. Solving gives m=1/54, w=1/90. For 9 men and 15 women: daily work = 9/54 + 15/90 = 1/6 + 1/6 = 1/3. Time needed = 3 days. Similarly, II and III together also work (I and III give same equation). Any two statements are sufficient.

Multiple choice
  1. 4 days

  2. 5 days

  3. 6 days

  4. 8 days

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A+B rate = 1/12, B+C = 1/15, C+A = 1/20. Adding: 2(A+B+C) = 1/12+1/15+1/20 = 1/5, so A+B+C = 1/10 (all three take 10 days together). In 6 days, they complete 6/10 = 3/5 work. Remaining 2/5 work at B+C rate (1/15) takes (2/5)/(1/15) = 6 days.

Multiple choice
  1. 20 days/दिन

  2. 8 days/दिन

  3. 16 days/दिन

  4. 24 days/दिन

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

A's rate = 1/24, B's = 1/32, C's = 1/64. Total work = 1. Let total days = D. A works 6 days, B works (D-6) days (leaves 6 days before completion), C works D days. Equation: 6(1/24) + (D-6)(1/32) + D(1/64) = 1. Solving: D = 20 days. Option A is correct.

Multiple choice
  1. 53

  2. 52

  3. 50

  4. 55

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Work done in 12 days by 250 workers = 2/7. Work remaining = 5/7 to be done in 25 days. Required workers: (250 × 12)/(2/7) = (W × 25)/(5/7). Solving: W = 300. Additional workers = 300 - 250 = 50. Option C is correct.