Quantitative Aptitude
Time and Work
2,195 Questions
Time and Work Questions
-
2 days/दिन
-
3 days/दिन
-
4 days/दिन
-
10 days/दिन
D
Correct answer
Explanation
Let one man's work per day be m units. Since a woman takes twice the time, she does m/2 units per day. Total work = (4m + 7(m/2)) * 8 = (4m + 3.5m) * 8 = 60m units. With 5 men and 2 women, daily work = 5m + 2(m/2) = 6m. Days needed = 60m/6m = 10 days.
D
Correct answer
Explanation
If A does work in 27 days, A's 1 day work = 1/27. B is 50% more efficient, so B's 1 day work = 1.5 × (1/27) = 1/18. Therefore B completes the work in 18 days. Option B (15) is a trap — 50% less time would be 13.5 days, not 50% more efficient.
B
Correct answer
Explanation
The work rate of 4 men equals 6 women, so 1 man = 1.5 women. Original work requires 336 man-hours (4 × 12 × 7). For twice the work (672 man-hours), 10 men + 3 women (equivalent to 12 men) working 8 hours/day complete it in 672 ÷ (12 × 8) = 7 days.
-
7 days / दिन
-
21 days / दिन
-
14 days / दिन
-
28 days / दिन
D
Correct answer
Explanation
If boy's 1 day work = 1 unit, then woman's work = 2 units (twice as fast), and man's work = 4 units (twice woman). Together they do 4 + 2 + 1 = 7 units/day. For 4 days, total work = 28 units. Boy alone needs 28/1 = 28 days.
-
2 : 1 : 4
-
1 : 2 : 4
-
2 : 4 : 1
-
4 : 2 : 1
B
Correct answer
Explanation
A completes half work in 1 day, so A's efficiency = 0.5 work/day. B completes full work in 1 day, so B's efficiency = 1 work/day. B does half of C's work in 1 day, meaning B's work = 1/2 of C's work in 1 day, so C's efficiency = 2 work/day. Ratio A:B:C = 0.5:1:2 = 1:2:4.
-
26 days/दिन
-
21 days/दिन
-
32 days/दिन
-
42 days/दिन
D
Correct answer
Explanation
Let B's 1 day work = 1 unit. Then A's work = 2 units (twice as good). Together they do 3 units/day and finish in 14 days, so total work = 42 units. B alone needs 42/1 = 42 days.
-
21 days/दिन
-
24 days/दिन
-
26 days/दिन
-
33 days/दिन
B
Correct answer
Explanation
From given: 1 man's 1 day work = 1/44. Since 2 women = 1 man, 1 woman's work = 1/(44×2) = 1/88. Since 3 boys = 1 man, 1 boy's work = 1/(44×3) = 1/132. Combined work of 1 man + 1 woman + 1 boy = 1/44 + 1/88 + 1/132 = (3+1.5+1)/132 = 5.5/132 = 1/24. Therefore they complete the work in 24 days.
-
6 days/दिन
-
9 days/दिन
-
10 days/दिन
-
13 days/दिन
A
Correct answer
Explanation
A's work rate = 1/9 per day. B's work rate = 1/10 per day. C's work rate = 1/15 per day. B and C work together for 2 days: work done = 2(1/10 + 1/15) = 2(3/30 + 2/30) = 2(5/30) = 1/3. Remaining work = 1 - 1/3 = 2/3. A completes 2/3 of work at rate 1/9, so time = (2/3)/(1/9) = (2/3)×9 = 6 days.
B
Correct answer
Explanation
This is inverse proportion: more men means fewer days. Total work = 26 × 17 = 442 man-days. To finish in 13 days: 442 ÷ 13 = 34 men needed. Additional men = 34 - 26 = 8. Option B is correct.
-
4 days
-
5 days
-
10 days
-
15 days
-
None of these
A
Correct answer
Explanation
Let 1 day's work for 1 man = m and 1 woman = w. From given: 2m + 3w = 1/8 and 3m + 2w = 1/7. Solving: multiply first by 3: 6m + 9w = 3/8. Multiply second by 2: 6m + 4w = 2/7. Subtract: 5w = 3/8 - 2/7 = (21-16)/56 = 5/56, so w = 1/56. Then m = 1/1568. For 5M + 4W: 5(1/1568) + 4(1/56) = 5/1568 + 4/56 = 5/1568 + 112/1568 = 117/1568 = 1/4. Therefore, work completes in 4 days.
B
Correct answer
Explanation
Let n be the initial number of men. Each day, 10 men leave, so on day i, n - 10(i-1) men work. Total work = n × 8 (since n men complete work in 8 days). The work equation: n + (n-10) + (n-20) + ... + (n-110) = 8n (12 terms, last term n-110). Sum = 12n - 10(0+1+...+11) = 12n - 10 × 66 = 12n - 660. So 12n - 660 = 8n, giving 4n = 660, so n = 165.
-
4 days/दिन
-
10 days/दिन
-
12 days/दिन
-
15 days/दिन
A
Correct answer
Explanation
3 men complete the work in 12 days, so 1 man does 1/36 of the work per day. Since 3 men = 5 women, 6 men = 10 women. Combined: 6 men + 5 women = 10 women + 5 women = 15 women. If 5 women take 12 days, 15 women take 12 × 5/15 = 4 days. Option A is correct.
D
Correct answer
Explanation
A does 3 times the work of B, so if B's rate = r, A's rate = 3r. Combined rate = 4r. Together: 4r × 12 = 1 work, so r = 1/48. A's rate = 3/48 = 1/16. A alone: 16 days.
-
12 days
-
15 days
-
10 days
-
8 days
-
6 days
D
Correct answer
Explanation
Total work = 24 × 24 = 576 man-hours. If 72 men work: 576 ÷ 72 = 8 hours. The question asks for hours, but options are labeled 'days'. However, given the standard interpretation of such problems, option D (8 days/hours) is the intended answer assuming the unit is consistent.
A
Correct answer
Explanation
Work done in 40 days = 1/3 by 180 men. Work remaining = 2/3 in 60 days. Men needed for 2/3 work in 60 days = (180 × 3 × 40)/(2 × 60) = 180 men. Extra men needed = 180 - 180 = 0. Wait - this doesn't match. Let me recalculate: (180 men × 40 days)/(1/3 work) = (x men × 60 days)/(2/3 work). Solving: 180 × 40 × 2/3 = x × 60 × 1/3. This gives x = 240. Extra = 240 - 180 = 60. Answer A is correct.