Time and Work Questions

Multiple choice
  1. 18 days/दिन

  2. 20 days/दिन

  3. 25 days/दिन

  4. 90 days/दिन

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Let A alone take x days. Then B and C each take 5x days (since they take 5 times A's time). Combined rate: 1/x + 1/(5x) + 1/(5x) = 1/x + 2/(5x) = 7/(5x). Time together = 5x/7 = 15 days. Solving: x = 21 days. However, this doesn't match the options. Let's re-interpret: if B and C together take 5 times A (i.e., their combined time is 5x), then A's rate + combined rate of B&C = 1/x + 1/(5x) = 6/(5x) = 1/15, giving x = 18 days. Option D (90 days) would be correct if only B or only C worked, not all three together.

Multiple choice
  1. 9

  2. 7

  3. 6

  4. 5

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

6 women do work in 3 days, so 1 woman takes 18 days. 3 women + 18 children take 2 days. Work rate: 3/18 + 18/(child's rate) = 1/2. So 1/6 + 18/c = 1/2, giving 18/c = 1/3, so c = 54. One child takes 54 days. 9 children together take 54/9 = 6 days. Option C is correct. Options A, B, D are incorrect calculations.

Multiple choice
  1. 25 days/दिन

  2. 30 days/दिन

  3. 24 days/दिन

  4. 20 days/दिन

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

A's rate = 1/20, B's rate = 1/30. Combined rate = 5/60 = 1/12. In 7 days, they complete 7/12 of the work. Remaining = 5/12. C completes 5/12 in 10 days, so C's rate = 5/120 = 1/24. Therefore, C alone completes full work in 24 days.

Multiple choice
  1. Rs. 1350

  2. Rs. 2150

  3. Rs. 1950

  4. Rs. 1750

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Weekly earning Rs. 8400/7 = Rs. 1200/day for 48 person-hours (6×8). For 54 person-hours (9×6): earning = 1200 × 54/48 = Rs. 1350/day.

Multiple choice
  1. 48

  2. 36

  3. 28

  4. 32

  5. 40

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

B completed 60% of work alone, so A did 40%. B worked for entire duration, A worked for 12 days less. If B takes b days alone, his rate is 1/b. A completed 40% in 12 days, so A takes 30 days. Given B takes 12 more days than A, b = 36.

Multiple choice
  1. ₹ 2200

  2. ₹ 4400

  3. ₹ 6600

  4. ₹ 8800

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

Let A's time = 3t, then B's time = 2t (A does half work in 2/3 of B's time). A's work in 2 days: 2/(3t), C's work: 2/40 = 1/20. Given A does thrice work of C in same time: 3×(1/20) = 2/(3t) gives t = 10/9. Work rates: A = 3/40, B = 2/45, C = 1/40. Total rate = 53/360. Ratio of work A:B:C = 3:2:1. A's share = (3/6) × 13,200 = ₹6,600.

Multiple choice
  1. 24

  2. 36

  3. 42

  4. 48

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let A, B, C take a, b, c days respectively. A = B + C combined work, so 1/a = 1/b + 1/c. A + B together: 1/a + 1/b = 1/15. C alone: 1/c = 1/40. Substituting: 1/a + 1/b = 1/15 and 1/a = 1/b + 1/40. From second: 1/a - 1/b = 1/40. Adding with first: 2/a = 1/15 + 1/40 = 11/120, so a = 240/11. Then 1/b = 1/15 - 11/240 = 5/240 = 1/48, so b = 48 days.

Multiple choice
  1. 70

  2. 85

  3. 65

  4. 75

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

Let the original number of men be x. Total work = x × 40 man-days. With 45 additional men: (x+45) × 25 = x × 40. Solving: 25x + 1125 = 40x, so 15x = 1125, giving x = 75 men.

Multiple choice
  1. 37

  2. 40

  3. 41

  4. 47

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

In 1/4 day, a man completes 1/12 of the work and a woman completes 1/16. Together they do 7/48 of the work. The remaining 41/48 must be done by boys. Each boy does 1/48 of the work in 1/4 day. So we need 41 boys. Options A, B, and D underestimate the work required.

Multiple choice
  1. 60

  2. 62

  3. 45

  4. 66

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

First calculate the total work in terms of each group's capacity: 10 children × 240 days = 2400 child-days of work; 18 men × 72 days = 1296 man-days; 15 women × 180 days = 2700 woman-days. The per-day rate for one child is 1/2400, one man is 1/1296, one woman is 1/2700. The combined rate of 9 men + 30 women + 10 children = 9/1296 + 30/2700 + 10/2400. Simplifying: 9/1296 = 1/144 ≈ 0.00694; 30/2700 = 1/90 ≈ 0.01111; 10/2400 = 1/240 ≈ 0.00417. Sum = 0.02222 work per day. Days = 1 ÷ 0.02222 = 45 days.

Multiple choice
  1. 40 days/दिनों

  2. 60 days/दिनों

  3. 75 days/दिनों

  4. 80 days/दिनों

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

Let A's rate = a, B's rate = b. Combined: a + b = 1/60. In 40 days, they complete 40/60 = 2/3 of work. Remaining work = 1/3, done by A in 20 days. So A's rate a = (1/3)/20 = 1/60. Therefore A alone takes 60 days.

Multiple choice
  1. 30 days/ दिन

  2. 35 days/ दिन

  3. 40 days/ दिन

  4. 45 days/ दिन

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

If A takes 50% more time than B, let B take x days, then A takes 1.5x days. Their rates: B = 1/x work per day, A = 1/(1.5x) = 2/(3x) work per day. Combined rate = 1/x + 2/(3x) = 5/(3x). Together they take 18 days, so 5/(3x) = 1/18, giving x = 30 days for B alone.

Multiple choice
  1. 18

  2. 15

  3. 14

  4. 16

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

A+B's combined rate: 1/12 work/day. A's rate: 1/20 work/day. So B's rate: 1/12 - 1/20 = 1/30 work/day. When B works half-days, effective rate = 1/20 + (1/2)(1/30) = 1/20 + 1/60 = 4/60 = 1/15 work/day. Time needed: 15 days. Option A (18 days) overestimates. Options C, D are incorrect.

Multiple choice
  1. 100

  2. 125

  3. 50

  4. 75

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

Work rate calculation: 200 men complete 1/4 work in 50 days. Remaining work = 3/4 in 100 days. Let M be total men needed. Work done = M × 100 days. For 3/4 work: M × 100 = 3/4 × 200 × 200 (from initial rate). This gives M = 300, so 100 additional men are needed. Alternatively: Work = 200 × 50 / 0.25 = 40000 man-days. Remaining = 30000 in 100 days, requiring 300 men.

Multiple choice
  1. 12

  2. 8

  3. 6

  4. 18

Reveal answer Fill a bubble to check yourself
B Correct answer
Explanation

If A completes work in 12 days, and B is 50% more efficient, then B's efficiency is 1.5 times A's efficiency. This means B takes 12 / 1.5 = 8 days to complete the same work.