P and Q together can do a work in 18 days. If P is 50% more efficient than Q, then in what time can Q do the work?
Reveal answer
Fill a bubble to check yourself
P and Q together can do a work in 18 days. If P is 50% more efficient than Q, then in what time can Q do the work?
45 days
36 days
32 days
27 days
None of the above
Let Q's efficiency be 1 unit/day. P's efficiency is 1.5 units/day. Combined efficiency = 2.5 units/day. Total work = 2.5 * 18 = 45 units. Time for Q = 45 / 1 = 45 days.
Since P is 50 percent more efficient than Q, the ratio of their efficiencies is 3 to 2. This means their combined efficiency is 5 units per day, so their total work is 18 days multiplied by 5 units, which equals 90 units. Working alone at an efficiency of 2 units per day, Q requires 90 units divided by 2 units per day, resulting in 45 days.