Multiple choice

Which is the total of the costs incurred in accomplishing work on the activity in a given period?

  1. Earned value

  2. Accomplishments

  3. Cost performance index

  4. Cost variance

  5. Actual cost

Reveal answer Fill a bubble to check yourself
E Correct answer
Explanation

It is the total of the costs incurred in accomplishing work on the activity in a given period.