Multiple choice

Which of the following compares the planned amount of work with what has actually been completed, to determine if the cost, schedule, and work accomplished are progressing in accordance with the plan?

  1. Actual Cost

  2. Planned Value

  3. Earned Value Analysis

  4. Cost Variance

  5. Accomplishments

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

It compares the planned amount of work with what has actually been completed, to determine if the cost, schedule, and work accomplished are progressing in accordance with the plan.