Multiple choice

What is the ratio between earned value and actual cost called?

  1. Planned value

  2. Schedule variance

  3. Cost performance index

  4. Cost variance

  5. Actual cost

Reveal answer Fill a bubble to check yourself
C Correct answer
Explanation

It is the ratio between earned value and actual cost.

Keep practicing — related questions

  • Which must correspond to whatever was budgeted for the planned value and the earned value?
  • Which is the total of the costs incurred in accomplishing work on the activity in a given period?
  • Which of the following compares the planned amount of work with what has actually been completed, to determ...
  • Which of the following represents the value of the work actually completed?
  • Which portion of the approved cost estimates premeditated to be spent on the given activity during a given ...
  • Which of the following, when calculated at a given point in time means that the project is behind the sched...
  • _______ ratio is also known as overall profitability ratio or return on capital employed.
  • A shopkeeper earns a profit of 20% on selling a book at 5% discount on printed price. Find the ratio of the...
Play the full quiz 🎤 Practise this topic out loud
Advertisement
© Aliensbrain | all rights reserved
  • About
  • Contact
  • Terms and Condition
  • Privacy Policy