Multiple choice

Which of the following, when calculated at a given point in time means that the project is behind the schedule?

  1. Negative schedule variance

  2. Schedule variance

  3. Planned value

  4. Actual cost

  5. Schedule performance index

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

This when calculated at a given point in time means the project is behind schedule.