f the cost variance is positive and the schedule variance is also positive, then it indicates that …

  1. Project is under budget and behind schedule

  2. Project is over budget and behind schedule

  3. Project is under budget and ahead of schedule

  4. Project is over budget and ahead of schedule


Correct Option: A