Project Management Quiz

Test your knowledge of project management fundamentals including scope, scheduling, team development, performance reporting, variance analysis, and project closing processes.

11 Questions Published

Questions

Question 1 Multiple Choice (Single Answer)

What should be done by the project manager to ensure that all work in the project is included?

  1. Create a contingency plan
  2. Create a risk management plan
  3. Create a WBS
  4. Create a scope statement
Question 2 Multiple Choice (Single Answer)

What kind of a relationship is implied when completion of a successor is dependent on initiation of its predecessor?

  1. FS
  2. FF
  3. SS
  4. SF
Question 3 Multiple Choice (Single Answer)

What should a project manager do or follow to ensure clear boundaries for project completion?

  1. Scope verification
  2. Completing a scope statement
  3. Risk management plan
  4. scope definition
Question 4 Multiple Choice (Single Answer)

Which of the following provides the foundation for team development?

  1. Motivation
  2. Organizational development
  3. Conflict management
  4. Individual development
Question 5 Multiple Choice (Single Answer)

Which of the following is NOT an input to project plan execution?

  1. Work authorization system
  2. Project plan
  3. Corrective action
  4. Preventive action
Question 6 Multiple Choice (Single Answer)

A project manager would find team development the most difficult in which form of organization?

  1. Weak Matrix organization
  2. Balanced Matrix organization
  3. Projectized organization
  4. Tight Matrix organization
Question 7 Multiple Choice (Single Answer)

Once the project is complete, the complete set of project records should be put in which of the following?

  1. Project archives
  2. Database
  3. Storage room
  4. Project report
Question 8 Multiple Choice (Single Answer)

Which of the following is a common format for performance reporting?

  1. Pareto diagrams
  2. Bar charts
  3. Responsibility assignment matrices
  4. Control charts
Question 9 Multiple Choice (Single Answer)

f the cost variance is positive and the schedule variance is also positive, then it indicates that …

  1. Project is under budget and behind schedule
  2. Project is over budget and behind schedule
  3. Project is under budget and ahead of schedule
  4. Project is over budget and ahead of schedule
Question 10 Multiple Choice (Single Answer)

Which one of the following is the last step of project closing?

  1. Client appreciates your product
  2. Client has accepted the product
  3. Lessons learned are documented
  4. Archives are complete
Question 11 Multiple Choice (Single Answer)

Who should be involved in the creation of lessons learned, at closure of project? (choose the BEST answer)

  1. Project office
  2. Management of the performing organization
  3. Project team
  4. Stakeholders