Alien head

Project Management Quiz

Description: Project Management Quiz
Number of Questions: 11
Created by:
Tags: project-management
Attempted 0/11 Correct 0 Score 0

What should be done by the project manager to ensure that all work in the project is included?

  1. Create a contingency plan

  2. Create a risk management plan

  3. Create a WBS

  4. Create a scope statement


Correct Option: C

What kind of a relationship is implied when completion of a successor is dependent on initiation of its predecessor?

  1. FS

  2. FF

  3. SS

  4. SF


Correct Option: D

What should a project manager do or follow to ensure clear boundaries for project completion?

  1. Scope verification

  2. Completing a scope statement

  3. Risk management plan

  4. scope definition


Correct Option: B

Which of the following provides the foundation for team development?

  1. Motivation

  2. Organizational development

  3. Conflict management

  4. Individual development


Correct Option: D

Which of the following is NOT an input to project plan execution?

  1. Work authorization system

  2. Project plan

  3. Corrective action

  4. Preventive action


Correct Option: A

A project manager would find team development the most difficult in which form of organization?

  1. Weak Matrix organization

  2. Balanced Matrix organization

  3. Projectized organization

  4. Tight Matrix organization


Correct Option: A

Once the project is complete, the complete set of project records should be put in which of the following?

  1. Project archives

  2. Database

  3. Storage room

  4. Project report


Correct Option: A

Which of the following is a common format for performance reporting?

  1. Pareto diagrams

  2. Bar charts

  3. Responsibility assignment matrices

  4. Control charts


Correct Option: B

f the cost variance is positive and the schedule variance is also positive, then it indicates that …

  1. Project is under budget and behind schedule

  2. Project is over budget and behind schedule

  3. Project is under budget and ahead of schedule

  4. Project is over budget and ahead of schedule


Correct Option: A

Which one of the following is the last step of project closing?

  1. Client appreciates your product

  2. Client has accepted the product

  3. Lessons learned are documented

  4. Archives are complete


Correct Option: D

Who should be involved in the creation of lessons learned, at closure of project? (choose the BEST answer)

  1. Project office

  2. Management of the performing organization

  3. Project team

  4. Stakeholders


Correct Option: D
+ View questions