Covers software engineering concepts including project management metrics (earned value analysis, variance tracking), UML modeling (state charts, stereotypes, tagged values), prototyping methods (high/low fidelity, horizontal, presentation), and information systems (operational, status enquiry, data analysis)
Questions
Which of the following, when calculated at a given point in time means that the project is behind the schedule?
- Negative schedule variance
- Schedule variance
- Planned value
- Actual cost
- Schedule performance index
Which of the following is rendered as a name enclosed by guillemots and placed above the name of another element?
- Note
- Stereotype
- Documentation
- Use case diagram
- Secuence diagram
What is the ratio between earned value and actual cost called?
- Schedule variance
- Cost variance
- Actual cost
- Planned value
- Cost performance index
Which of the following systems ensures that specific tasks are planned and carried out properly within a factory or office?
- Strategic information system
- Tactical information system
- Closed system
- Abstract system
- Operational information system
Which of the following simulates the proposed product in some very rudimentary way even by pencil and paper or by slides?
- Exploratory prototyping
- Experimental prototyping
- Evolutionary prototyping
- Low fidelity prototyping
- Waterfall model
Which of the following systems includes the number of decisions in the operational management and the same at the middle management that are based on one or two aspects of a decision making situation?
- Tactical information system
- Status enquiry system
- Abstract system
- Closed system
- Probabilistic system
Which of the following represents the value of the work actually completed?
- Planned value
- Cost variance
- Schedule variance
- Earned value
- Accomplishment
Which of the following is important in modeling the behavior of an interface, class or and emphasize the event ordered behavior of an object?
- Class diagram
- Object diagram
- Sequence diagram
- State chart diagram
- Interface
Which of the following is intended to closely mimic the look, feel and the responsiveness of the system including its temporal delay characteristics?
- Experimental prototyping
- Embedded prototyping
- High fidelity prototyping
- Exploratory prototyping
- Waterfall model
Which of the following can serve a marketing purpose by illustrating to potential users, the expected system behavior?
- Embedded prototyping
- Evolutionary prototyping
- Presentation prototype
- Exploratory prototyping
- Incremental and Iterative model
Which of the following systems is based on comparative analysis and use of a formula or an algorithm?
- Strategic information system
- Tactical information system
- Deterministic system
- Probabilistic system
- Data analysis system
Which of the following when calculated at a given point in time means the project is over budget?
- Cost performance index
- Actual cost
- Cost variance
- Negative cost variance
- Milestones
In which of the following prototypings are the most of the system functions at least nominally accessible but only a few are actually operational?
- Exploratory prototyping
- Evolutionary prototyping
- Horizontal prototyping
- Embedded prototyping
- Waterfall model
Which of the following is rendered as a string enclosed by brackets and placed below the name of another element?
- Tagged value
- Note
- Documentation
- Secuence diagram
- Activity diagram
In which of the following systems are the data analyzed and reports generated that is used for the assessment of the situation for decision making?
- Information analysis system
- Closed system
- Deterministic system
- Probabilistics system
- Abstract System