Which of the following represents the value of the work actually completed?

  1. Planned value

  2. Cost variance

  3. Schedule variance

  4. Earned value

  5. Accomplishment

Reveal answer Fill a bubble to check yourself
D Correct answer
Explanation

It represents the value of the work actually completed.

Keep practicing — related questions

  • Which of the following compares the planned amount of work with what has actually been completed, to determ...
  • Which is the total of the costs incurred in accomplishing work on the activity in a given period?
  • Which must correspond to whatever was budgeted for the planned value and the earned value?
  • Which of the following, when calculated at a given point in time, means that the project is ______________.
  • Which of the following, when calculated at a given point in time means that the project is behind the sched...
  • What is the ratio between earned value and planned value called?
  • Which of the following is an industry standard method of measuring a project progress at any given point in...
  • Which of the following is an industry standard method of measuring a project progress at any given point in...
Play the full quiz 🎤 Practise this topic out loud
Advertisement
© Aliensbrain | all rights reserved
  • About
  • Contact
  • Terms and Condition
  • Privacy Policy