aliensbrain
  • Home
  • Study
  • Quizzes
  • 🎤AI Practicefree
  • Notebooks
  • Community
  • Sign in
  • Software Engineering
  • What is the ratio between earned value and actual cost ca...
Multiple choice

What is the ratio between earned value and actual cost called?

  1. Cost performance index

  2. Cost variance

  3. Actual cost

  4. Planned value

  5. Accomplishments

Reveal answer Fill a bubble to check yourself
A Correct answer
Explanation

It is the ratio between earned value and actual cost.

Keep practicing — related questions

  • What is the ratio between earned value and actual cost called?
  • What is the ratio between earned value and planned value called?
  • Which is the total of the costs incurred in accomplishing work on the activity in a given period?
  • Which of the following compares the planned amount of work with what has actually been completed, to determ...
  • Which must correspond to whatever was budgeted for the planned value and the earned value?
  • Which of the following represents the value of the work actually completed?
  • _______ ratio is also known as overall profitability ratio or return on capital employed.
  • Which portion of the approved cost estimates premeditated to be spent on the given activity during a given ...
Play the full quiz 🎤 Practise this topic out loud
Advertisement
© Aliensbrain | all rights reserved
  • About
  • Contact
  • Terms and Condition
  • Privacy Policy