Quantitative Aptitude
Time and Work
2,195 Questions
Time and Work Questions
-
Rs. 180
-
Rs. 200
-
Rs. 300
-
Rs. 240
B
Correct answer
Explanation
A's rate: 1/10 work per day. B's rate: 1/15 work per day. Combined (A+B+C) rate: 1/4 work per day. C's rate = 1/4 - (1/10 + 1/15) = 1/4 - 1/6 = 1/12 work per day. Payment is proportional to work done. C does (1/12 × 4) = 1/3 of total work in 4 days. C receives: 600 × 1/3 = Rs. 200. Option A would be 30% of work, Option C would be 50%, Option D would be 40%.
-
10 days / दिन
-
7 days / दिन
-
9 days / दिन
-
11 days / दिन
C
Correct answer
Explanation
5W + 8M = 1/12 work/day, 11W + 5M = 1/8 work/day. Solving gives 1W = 1/216, 1M = 1/144. Then 9W + 6M = 9/216 + 6/144 = 1/24 + 1/24 = 1/9 work/day, so 9 days needed. Set up and solve the simultaneous equations for individual work rates.
-
18 days
-
19 days
-
20 days
-
21 days
B
Correct answer
Explanation
A's work rate = 1/25 per day, B's = 1/30 per day. Combined rate = 1/25 + 1/30 = 11/150 per day. In 5 days, they complete 5 × 11/150 = 11/30 of work. Remaining = 19/30. B alone does 1/30 per day, so needs 19 days. Option B is correct.
B
Correct answer
Explanation
Let Bramhanand's time = x days. Then Aryan takes 2x days and Chandranshu takes x/3 days (since Aryan takes thrice Chandranshu's time). Combined rate: 1/(2x) + 1/x + 3/x = 1/2. Solving: (1 + 2 + 6)/2x = 1/2, giving 9/2x = 1/2, so x = 6 days.
A
Correct answer
Explanation
This is an inverse proportion problem - more men means fewer days. Total work = 16 × 12 = 192 man-days. For 24 men: 192 ÷ 24 = 8 days. The work is inversely proportional to the number of workers.
-
20
-
56
-
41
-
21
-
None of these
D
Correct answer
Explanation
Total work = 35 × 120 = 4200 man-days. Work done = 35 × 80 = 2800. Remaining = 1400 in 40 days. Men needed = 1400/40 = 35. Additional men = 35 - 35 + 35 - 14 = 21.
B
Correct answer
Explanation
Let total work = LCM(12,15) = 60 units. Ayushi + Aanchal = 5 units/day, Aanchal + Vaishnavi = 4 units/day. Since Ayushi's efficiency is twice Vaishnavi's, let Vaishnavi = x, then Ayushi = 2x. From second equation: Aanchal = 4 - x. Substitute in first: 2x + (4 - x) = 5, so x = 1. Therefore Vaishnavi = 1 unit/day, Ayushi = 2 units/day, and Aanchal = 3 units/day. Aanchal alone takes 60/3 = 20 days.
-
120.5 days / दिन
-
118.5 days / दिन
-
125 days / दिन
-
112.5 day / दिन
D
Correct answer
Explanation
A does 60% of work in 45 days, so A's rate = 60%/45 = 4/3% per day. For full work, A needs 100% ÷ (4/3%) = 75 days. Remaining 40% is finished by A+B in 18 days, so their combined rate = 40%/18 = 20/9% per day. B's rate = combined - A's rate = 20/9 - 4/3 = 8/9% per day. B alone needs 100% ÷ (8/9%) = 112.5 days.
-
24 days/24 दिन
-
36 days/36 दिन
-
18 days/18 दिन
-
9 days/9 दिन
C
Correct answer
Explanation
A and B together complete work in 6 days, so their combined rate is 1/6 per day. A completes 25% in 2 days alone, so A's rate is 0.25/2 = 1/8 per day. Therefore B's rate is 1/6 - 1/8 = 1/24 per day. The remaining 75% of work at B's rate takes (0.75)/(1/24) = 18 days. Options A (24 days), B (36 days), and D (9 days) don't match this calculation.
-
24 days/दिन
-
32 days/दिन
-
18 days/दिन
-
20 days/दिन
A
Correct answer
Explanation
Let a woman's efficiency = 1 unit/day. Then a man's efficiency = 0.75 units/day (25% less). 4 men + 6 women in 22 days: Total work = 22(4 × 0.75 + 6 × 1) = 22(3 + 6) = 22 × 9 = 198 units. 7 men + 3 women: Combined efficiency = 7 × 0.75 + 3 × 1 = 5.25 + 3 = 8.25 units/day. Days needed = 198/8.25 = 24 days. The key insight is that men are less efficient than women (75%), so we use 0.75 for men.
-
75
-
80
-
90
-
85
-
None of these
D
Correct answer
Explanation
5 women complete work in 119 days, so total work = 5 × 119 = 595 woman-days. If 10 men take same time, 10 × 119 = 1190 man-days = 595 woman-days, so 1 man = 0.5 woman. Combined rate: 5 women + 4 men = 5 + (4 × 0.5) = 7 women equivalent. Days = 595 ÷ 7 = 85. Option D is correct.
-
1 : 3
-
3 : 1
-
1 : 2
-
1 : 4
-
4 : 1
A
Correct answer
Explanation
Solving the system: 1/A + 1/B = 1/15, 1/B + 1/C = 1/20, 1/A + 1/C = 1/30. Adding first two and subtracting third gives 2/B = 1/12, so B = 24 days. Then 1/A = 1/15 - 1/24 = 1/40, so A = 40 days. And 1/C = 1/20 - 1/24 = 1/120, so C = 120 days. The ratio A:C = 40:120 = 1:3.
-
रु./Rs. 4550
-
रु./Rs.4250
-
रु./Rs. 4000
-
रु./Rs.4500
D
Correct answer
Explanation
P's work rate = 1/40 per day, Q's rate = 1/60 per day. Combined P+Q rate = 1/40 + 1/60 = 5/120 = 1/24 per day. In 15 days, P+Q complete 15/24 = 5/8 of the work. Therefore R completes the remaining 3/8 of the work. R's share = (3/8) × ₹12,000 = ₹4,500. Verification: P's share = (15/40) × 12000 = ₹4500, Q's share = (15/60) × 12000 = ₹3000, Total = 4500 + 3000 + 4500 = ₹12000 ✓
-
12 days/दिन
-
10 days/दिन
-
8 days/दिन
-
7.5 days/दिन
B
Correct answer
Explanation
Total area to paint = 2(length+breadth)×height + length×breadth = 2(40+30)×10 + 40×30 = 1400+1200 = 2600 m². A paints 240/2 = 120 m²/day, B paints 390/3 = 130 m²/day. Together they paint 250 m²/day. Time = 2600/250 = 10.4 days, but since they finish exactly on the 10th day with some capacity remaining, the answer rounds to 10 days.
-
70.%
-
41.8%
-
52%
-
75
-
None of these
A
Correct answer
Explanation
Work rates: A completes in 12 days, so rate = 1/12. B completes half work in twice A's time (24 days), rate = 1/48. C completes one-fourth work in 1.5× A's time (18 days), rate = 1/72. Total rate = 1/12 + 1/48 + 1/72 = 17/144. A's wage share = (1/12)/(17/144) = 12/17 = 70.6%, which rounds to approximately 70%.